4604 S WESTERN AVE 90062
Certificate Information: 4604 S WESTERN AVE 90062
- Application / Permit
- 18010-10000-00801
- Plan Check / Job No.
- B18LA03591
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- New 5-story, 49-unit, apartment building TOC Tier 4 100% affordable
- Permit Issued
- Issued on 11/6/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/16/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 5/31/2018 | HERNAN ARREOLA |
| Corrections Issued | 6/6/2018 | HERNAN ARREOLA |
| Quality Review Completed | 6/19/2018 | BILL STUTSMAN |
| Building Plans Picked Up | 6/21/2018 | APPLICANT |
| Applicant returned to address corrections | 10/30/2018 | HERNAN ARREOLA |
| Applicant returned to address corrections | 11/26/2018 | HERNAN ARREOLA |
| Plan Check Approved | 10/25/2019 | HERNAN ARREOLA |
| Issued | 11/6/2019 | LADBS |
| TCO Issued (Expire Date: 05-19-2026) | 11/20/2025 | RAFAEL ESPINOZA |
| Permit Finaled | 1/16/2026 | ERNESTO CORRAL |
| CofO Issued | 1/16/2026 | ERNESTO CORRAL |
| Permit Finaled | 1/16/2026 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 6/12/2018 | STEVE MELGAR |
| ZA Case | Cleared | 6/12/2018 | DIANA JIMENEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2018 | NAZILA NOORIFAR |
| Permit | Cleared | 6/29/2018 | JAMES MORALEZ |
| Highway dedication | Cleared | 10/5/2018 | ADOLFO GUTIERREZ |
| Project located in CRA area | Cleared | 10/10/2018 | JIM URQUHART |
| Hydrant and Access approval | Cleared | 10/11/2018 | ROBERT DUFF |
| Sewer availability | Cleared | 10/11/2018 | CELINA MORENO |
| Construction near power lines | Cleared | 10/12/2018 | RIDWAN HARDY |
| Work Adjacent to Public Way | Cleared | 10/17/2018 | PHILLIP WILSON |
| Low Impact Development | Cleared | 11/20/2018 | JORGE MEJIA LEMUS |
| Green Code | Cleared | 11/21/2018 | COLIN LOREDO |
| DAS Clearance | Cleared | 12/4/2018 | HERNAN ARREOLA |
| Frnt yard landscape/Water mgmt | Cleared | 1/17/2019 | RICK TORRES |
| Miscellaneous | Cleared | 1/17/2019 | RICK TORRES |
| Opn space landscape/Water mgmt | Cleared | 1/17/2019 | RICK TORRES |
| Roof/Waste drainage to street | Cleared | 1/24/2019 | KAREN LE |
| Building over 3-story or 36-ft | Cleared | 7/3/2019 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 7/3/2019 | CALOSHA APPROVED |
| Fire Marshall Fire Life Safety | Cleared | 9/24/2019 | OSCAR SALGADO JR |
| Density Bonus 12.22.A.31 | Cleared | 10/3/2019 | JAMES MCCARTHY |
| Miscellaneous | Cleared | 10/24/2019 | TREVOR MARTIN |
Contact Information
| Architect | El, Bayar, Sami M; Lic. No.: C26080 | 22834 BRENFORD STREET WOODLAND HILLS, CA 91364 |
| Contractor | Roth Group The; Lic. No.: 841003-B | 329 PACIFIC COAST HIGHWAY HERMOSA BEACH, CA 90254 |
| Engineer | Heydar,, Ahmad; Lic. No.: S3679 | 28025 DOROTHY DR STE 104 AGOURA HILLS, CA 91301 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Reinforced Concrete Frame | 5/5/2020 | Not Ready for Inspection | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 7/31/2020 | Partial Approval | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 8/5/2020 | Partial Approval | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 8/10/2020 | Partial Approval | JAMES POWERS |
| Masonry Wall/Backfill | 8/17/2020 | Partial Approval | JAMES POWERS |
| Masonry Wall/Backfill | 8/20/2020 | Partial Approval | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 9/17/2020 | Partial Approval | JAMES POWERS |
| Masonry Wall/Backfill | 9/17/2020 | Not Ready for Inspection | JAMES POWERS |
| Deputy Other (see comments) | 1/15/2021 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 1/15/2021 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 1/20/2021 | Partial Approval | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 1/20/2021 | Not Ready for Inspection | JAMES POWERS |
| Masonry Wall/Backfill | 1/20/2021 | Partial Approval | JAMES POWERS |
| Deputy Other (see comments) | 3/2/2021 | Partial Approval | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 3/2/2021 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 3/2/2021 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 3/5/2021 | Partial Approval | JAMES POWERS |
| Deputy Drilled-In Anchors | 3/10/2021 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 4/26/2021 | Conditional Approval | NICK DANERI |
| Deputy Wood Construction | 5/26/2021 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 6/4/2021 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 6/8/2021 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 6/9/2021 | Approved | JOEY BUCHANAN |
| Deputy Wood Construction | 6/28/2021 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 6/29/2021 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 6/30/2021 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 7/30/2021 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 8/12/2021 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 9/24/2021 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 10/19/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Wood Construction | 10/28/2021 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 12/21/2021 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 1/13/2022 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 3/11/2022 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 5/16/2022 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 5/17/2022 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 5/23/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Wood Construction | 5/26/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Wood Construction | 6/7/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Wood Construction | 8/31/2022 | Conditional Approval | WINSTON DUNNING |
| Deputy Wood Construction | 9/16/2022 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2023 | Approved | JAMES POWERS |
| Insulation | 4/11/2023 | Partial Approval | JAMES POWERS |
| Interior/Exterior Lathing | 4/11/2023 | Partial Approval | JAMES POWERS |
| Wood Frame | 4/11/2023 | Approved | JAMES POWERS |
| Drywall Nailing | 4/21/2023 | Partial Approval | LARRY ARNICK |
| Interior/Exterior Lathing | 8/2/2023 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 8/10/2023 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 8/23/2023 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 10/13/2023 | Partial Approval | JAMES POWERS |
| Insulation | 10/24/2023 | Not Ready for Inspection | LARRY ARNICK |
| Light Gage Steel Frame | 10/27/2023 | Partial Approval | LARRY ARNICK |
| Drywall Nailing | 11/3/2023 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 11/6/2023 | Not Ready for Inspection | JAMES POWERS |
| Insulation | 11/14/2023 | Partial Approval | LARRY ARNICK |
| Drywall Nailing | 10/2/2024 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 10/22/2024 | Not Ready for Inspection | JAMES POWERS |
| Interior/Exterior Lathing | 10/22/2024 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 12/10/2024 | Partial Approval | JAMES POWERS |
| Pre-Inspection | 10/24/2025 | Not Ready for Inspection | LARRY ARNICK |
| Pre-Inspection | 10/28/2025 | Not Ready for Inspection | JAMES POWERS |
| Final | 11/18/2025 | OK for TCO | JAMES POWERS |
| Footing/Foundation/Slab | 11/18/2025 | Approved | JAMES POWERS |
| Green Building Final | 11/18/2025 | Approved | JAMES POWERS |
| Green Building Rough | 11/18/2025 | Approved | JAMES POWERS |
| Reinforced Masonry Frame | 11/18/2025 | Approved | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 11/18/2025 | SGSOV Approved | JAMES POWERS |
| Smoke Detectors | 11/18/2025 | Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 11/18/2025 | Approved | JAMES POWERS |
| Final | 1/13/2026 | Not Ready for Inspection | JAMES POWERS |
| Final | 1/16/2026 | Not Ready for Inspection | JAMES POWERS |