7855 N HASKELL AVE 91406

Certificate Information: 7855 N HASKELL AVE 91406

Application / Permit
18010-10000-00755
Plan Check / Job No.
B18LA03399
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(22) Storage Building for Household Goods
Work Description
(N) 3 STORY STORAGE OF HOUSE HOLD GOODS BUILDING w/ NFPA 13. Per ZA 2017-4930-CU
Permit Issued
Issued on 10/11/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 10/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2018 APPLICANT
Disabled Access Plans Picked Up 5/9/2018 APPLICANT
Assigned to Plan Check Engineer 5/12/2018 HERNAN ARREOLA
Green Plans Picked Up 5/15/2018 APPLICANT
Corrections Issued 5/16/2018 HERNAN ARREOLA
Quality Review Completed 5/24/2018 BILL STUTSMAN
Building Plans Picked Up 6/4/2018 APPLICANT
Applicant returned to address corrections 8/15/2018 HERNAN ARREOLA
Applicant returned to address corrections 8/30/2018 HERNAN ARREOLA
Plan Check Approved 5/20/2019 HERNAN ARREOLA
Issued 10/11/2019 LADBS
CofO in Progress 10/6/2021 DANNY RODRIGUEZ
CofO Issued 10/13/2021 RICKEY JACKSON
Permit Finaled 10/13/2021 RICKEY JACKSON

Permit Application Clearance Information

Site Plan review Cleared 6/7/2018 NOAH MCCOY
Prkng lot landscape/Water mgmt Cleared 8/23/2018 NOAH MCCOY
ZA Case Cleared 8/23/2018 NOAH MCCOY
ZA Case Cleared 8/23/2018 NOAH MCCOY
DAS Clearance Cleared 9/11/2018 WAI LAU
Green Code Cleared 9/11/2018 KHEDER ALRAZAA
Hydrant and Access approval Cleared 10/25/2018 JOHN DALLAS
Eng Process Fee Ord 176,300 Cleared 10/29/2018 OSCAR GUTIERREZ
Sewer availability Cleared 10/29/2018 OSCAR GUTIERREZ
Low Impact Development Cleared 11/2/2018 RYAN HUDSON
Highway dedication Cleared 12/7/2018 RUDY TERRIQUEZ.
Roof/Waste drainage to street Cleared 5/10/2019 JEANETTE VONG
Building over 3-story or 36-ft Cleared 5/20/2019 CALOSHA APPROVED

Contact Information

Architect Wallace,, Enrique; Lic. No.: C15704 28836 VIA DE LUNA      LAGUNA NIGUEL, CA 92677
Contractor Monarch Construction Management Inc; Lic. No.: 777725-B 1001 DOVE ST STE 205      NEWPORT BEACH, CA 92660
Engineer , ; Lic. No.: S2609 25032 RANCHO CLEMENTE      LAGUNA HILLS, CA 92656
Engineer Powers,, Brian Frederick; Lic. No.: C75902 2090 WEST 31ST STREET      LOS ANGELES, CA 90018

Inspector Information

GREGORY POMISH, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI
EDWIN GREGORYONA, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/7/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 5/13/2020 Conditional Approval ROBERT COLE
Footing/Foundation/Slab 5/22/2020 Partial Approval ROBERT COLE
Deputy Reinf. Concrete 5/27/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 5/28/2020 Conditional Approval ROBERT COLE
Masonry Wall/Backfill 5/28/2020 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 5/29/2020 Conditional Approval ROBERT COLE
Masonry Wall/Backfill 5/29/2020 Partial Approval ROBERT COLE
Footing/Foundation/Slab 6/10/2020 Partial Approval ROBERT COLE
Excavation/Setback/Form/Re-Bar 6/16/2020 Partial Approval ROBERT COLE
Deputy Reinf. Concrete 6/17/2020 Conditional Approval ROBERT COLE
Deputy Drilled-In Anchors 6/22/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 6/24/2020 Conditional Approval ROBERT COLE
Footing/Foundation/Slab 6/24/2020 Partial Approval ROBERT COLE
Masonry Wall/Backfill 6/24/2020 Partial Approval ROBERT COLE
Deputy Reinf. Concrete 6/25/2020 Conditional Approval ROBERT COLE
Masonry Wall/Backfill 6/25/2020 Partial Approval ROBERT COLE
Deputy Drilled-In Anchors 6/30/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 6/30/2020 Conditional Approval ROBERT COLE
Masonry Wall/Backfill 6/30/2020 Partial Inspection ROBERT COLE
Deputy Reinf. Concrete 7/2/2020 Conditional Approval ROBERT COLE
Masonry Wall/Backfill 7/2/2020 Partial Approval ROBERT COLE
Deputy Drilled-In Anchors 7/7/2020 Conditional Approval ROBERT COLE
Masonry Wall/Backfill 7/7/2020 Partial Approval ROBERT COLE
Deputy Reinf. Masonry 7/10/2020 Conditional Approval ROBERT COLE
Masonry Wall/Backfill 7/10/2020 Partial Inspection JEFFREY FULTON
Deputy Reinf. Masonry 7/13/2020 Conditional Approval ROBERT COLE
Deputy Steel/Welding 7/13/2020 Conditional Approval ROBERT COLE
Masonry Wall/Backfill 7/13/2020 Partial Approval ROBERT COLE
Deputy Reinf. Masonry 7/14/2020 Conditional Approval ROBERT COLE
Masonry Wall/Backfill 7/14/2020 Partial Approval ROBERT COLE
Deputy Drilled-In Anchors 7/15/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 7/16/2020 Conditional Approval ROBERT COLE
Masonry Wall/Backfill 7/16/2020 Partial Approval ROBERT COLE
Deputy Reinf. Masonry 7/20/2020 Approved HAMID PISHEHVAR
Masonry Wall/Backfill 7/20/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 7/22/2020 Conditional Approval ROBERT DAVIS
Masonry Wall/Backfill 7/22/2020 Partial Approval ROBERT DAVIS
Masonry Wall/Backfill 7/24/2020 Partial Approval ROBERT DAVIS
Deputy Reinf. Masonry 7/27/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 7/28/2020 Approved DANNY RODRIGUEZ
Masonry Wall/Backfill 7/28/2020 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 7/30/2020 No Result Entered ROBERT COLE
Deputy Steel/Welding 7/30/2020 Approved JOHN KITCKO
Masonry Wall/Backfill 7/30/2020 Partial Approval JOHN KITCKO
Deputy Reinf. Masonry 7/31/2020 Approved DANNY RODRIGUEZ
Masonry Wall/Backfill 7/31/2020 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 8/4/2020 Conditional Approval JEFFREY DURAN
Light Gage Steel Frame 8/4/2020 Partial Approval ROBERT DAVIS
Masonry Wall/Backfill 8/4/2020 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 8/5/2020 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 8/5/2020 Corrections Issued DANNY RODRIGUEZ
Deputy Reinf. Masonry 8/7/2020 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 8/7/2020 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 8/7/2020 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 8/10/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 8/10/2020 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 8/10/2020 Partial Approval DANNY RODRIGUEZ
Deputy Drilled-In Anchors 8/11/2020 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/12/2020 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 8/13/2020 No Result Entered ROBERT COLE
Masonry Wall/Backfill 8/14/2020 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 8/18/2020 Conditional Approval JEFFREY DURAN
Masonry Wall/Backfill 8/18/2020 Partial Inspection JEFFREY FULTON
Masonry Wall/Backfill 8/19/2020 Partial Inspection JEFFREY FULTON
Deputy Steel/Welding 8/24/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 8/31/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 9/1/2020 Approved HAMID PISHEHVAR
Light Gage Steel Frame 9/1/2020 Approved HAMID PISHEHVAR
Green Building Rough 9/2/2020 Partial Approval HAMID PISHEHVAR
Insulation 9/2/2020 Approved HAMID PISHEHVAR
Structural Steel Frame 9/2/2020 Partial Approval HAMID PISHEHVAR
Verify Sprinkler Sign Off 9/2/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 9/8/2020 Conditional Approval RICKEY JACKSON
Footing/Foundation/Slab 9/8/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 9/11/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 9/25/2020 No Result Entered ROBERT COLE
Light Gage Steel Frame 10/7/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 10/7/2020 Corrections Issued DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/8/2020 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 10/8/2020 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/9/2020 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 10/27/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Drilled-In Anchors 11/4/2020 No Result Entered ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 11/4/2020 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 11/4/2020 Partial Approval DANNY RODRIGUEZ
Deputy Other (see comments) 11/6/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/6/2020 No Result Entered ROBERT COLE
Deputy Drilled-In Anchors 11/18/2020 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 11/18/2020 Conditional Approval JEFFREY DURAN
Light Gage Steel Frame 11/19/2020 Partial Approval HAMID PISHEHVAR
Drywall Nailing 12/17/2020 Partial Approval HAMID PISHEHVAR
Green Building Rough 12/17/2020 Approved HAMID PISHEHVAR
Insulation 12/17/2020 Partial Approval HAMID PISHEHVAR
Insulation 12/23/2020 Partial Inspection DAVID BURKHEAD
Light Gage Steel Frame 12/23/2020 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 12/29/2020 Approved HAMID PISHEHVAR
Light Gage Steel Frame 12/29/2020 Approved HAMID PISHEHVAR
Drywall Nailing 1/11/2021 Partial Approval HAMID PISHEHVAR
Insulation 1/11/2021 Partial Approval HAMID PISHEHVAR
Insulation 1/12/2021 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 1/13/2021 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 1/14/2021 Partial Approval DANNY RODRIGUEZ
Insulation 1/14/2021 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 1/15/2021 Partial Approval DANNY RODRIGUEZ
Insulation 1/19/2021 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 1/20/2021 Partial Approval DANNY RODRIGUEZ
Insulation 1/21/2021 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 1/26/2021 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 1/26/2021 Partial Approval DANNY RODRIGUEZ
Insulation 2/2/2021 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 2/5/2021 Partial Approval DANNY RODRIGUEZ
Insulation 2/18/2021 Partial Approval DANNY RODRIGUEZ
Interior/Exterior Lathing 2/25/2021 Partial Approval DANNY RODRIGUEZ
Pre-Inspection 3/25/2021 Partial Inspection DANNY RODRIGUEZ
Pre-Inspection 4/8/2021 Partial Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 4/14/2021 Approved HAMID PISHEHVAR
T-Bar Ceiling 4/15/2021 Partial Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 4/27/2021 Conditional Approval DANNY RODRIGUEZ
T-Bar Ceiling 4/28/2021 Approved HAMID PISHEHVAR
Drywall Nailing 8/2/2021 Not Ready for Inspection DANNY RODRIGUEZ
Final 8/2/2021 Corrections Issued DANNY RODRIGUEZ
Green Building Final 8/2/2021 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 8/2/2021 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 8/2/2021 SGSOV Not Ready DANNY RODRIGUEZ
Smoke Detectors 8/2/2021 Approved DANNY RODRIGUEZ
Structural Steel Frame 8/2/2021 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 9/27/2021 Approved DANNY RODRIGUEZ
Final 9/27/2021 Partial Inspection DANNY RODRIGUEZ
Green Building Final 9/27/2021 Approved DANNY RODRIGUEZ
Reinforced Masonry Frame 9/27/2021 Approved DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 9/27/2021 SGSOV No Gas DANNY RODRIGUEZ
Structural Steel Frame 9/27/2021 Approved DANNY RODRIGUEZ
Final 9/30/2021 OK to Issue CofO DANNY RODRIGUEZ