7540 WORLD WAY WEST 90045
Certificate Information: 7540 WORLD WAY WEST 90045
- Application / Permit
- 18010-10000-00614
- Plan Check / Job No.
- B18LA03113
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (3) Aircraft Hanger
- Work Description
- NEW DELTA AIRCRAFT MAINTENANCE HANGAR BUILDING: SINGLE HIGH BAY HANGAR AND OFFICE SPACE., OVERALL SIZE (IRREGULAR) APPROX. 375' X 360'.
- Permit Issued
- Issued on 9/5/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/8/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/16/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 2/22/2018 | EDUARDO RODRIGUEZ |
| Green Plans Picked Up | 2/28/2018 | APPLICANT |
| Disabled Access Plans Picked Up | 3/1/2018 | APPLICANT |
| Corrections Issued | 3/8/2018 | EDUARDO RODRIGUEZ |
| Quality Review Completed | 3/9/2018 | LIPING TENG |
| Building Plans Picked Up | 3/9/2018 | APPLICANT |
| Applicant returned to address corrections | 4/25/2018 | EDUARDO RODRIGUEZ |
| Applicant returned to address corrections | 5/17/2018 | EDUARDO RODRIGUEZ |
| Applicant returned to address corrections | 8/23/2018 | EDUARDO RODRIGUEZ |
| Plan Check Approved | 9/5/2018 | EDUARDO RODRIGUEZ |
| Issued | 9/5/2018 | LADBS |
| TCO Issued (Expire Date: 08-05-2020) | 2/7/2020 | JONATHAN ALLEN |
| CofO in Progress | 7/8/2020 | JONATHAN ALLEN |
| Permit Finaled | 7/8/2020 | JONATHAN ALLEN |
| CofO Issued | 7/8/2020 | JONATHAN ALLEN |
| Permit Finaled | 7/8/2020 | JONATHAN ALLEN |
Permit Application Clearance Information
| City owned building/parcel | Cleared | 2/28/2018 | HAROOT AVANESIAN |
| Project Permit | Cleared | 3/1/2018 | EDUARDO RODRIGUEZ |
| Address approval | Cleared | 3/22/2018 | STEVEN JIN |
| Construction within easement | Cleared | 3/22/2018 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/22/2018 | STEVEN JIN |
| Roof/Waste drainage to street | Cleared | 3/28/2018 | STEVEN JIN |
| Miscellaneous | Cleared | 4/12/2018 | STEVEN JIN |
| Sewer availability | Cleared | 4/24/2018 | STEVEN JIN |
| Abandoned oil well | Cleared | 7/10/2018 | JOHN CONNEALLY |
| Abandoned oil well approval | Cleared | 7/10/2018 | JOHN CONNEALLY |
| Hydrant and Access approval | Cleared | 7/10/2018 | JOHN CONNEALLY |
| DAS Clearance | Cleared | 7/13/2018 | WAI LAU |
| Airport buildings | Cleared | 8/10/2018 | ANDREW KO |
| Green Code | Cleared | 8/16/2018 | COLIN LOREDO |
| Low Impact Development | Cleared | 8/22/2018 | RYAN HUDSON |
| GPI Written Notices | Cleared | 8/29/2018 | EDUARDO RODRIGUEZ |
| Grading Pre-Inspection | Cleared | 8/29/2018 | EDUARDO RODRIGUEZ |
Contact Information
| Architect | Berentes, Allen Wallin; Lic. No.: C18332 | 5014 BLACKHORSE ROAD RANCHO PALOS VERDES, CA 90275 |
| Contractor | Skanska Usa Building Inc; Lic. No.: 817578-B | 389 INTERPACE PARKWAY 5TH FL PARSIPPANY, NJ 07054 |
| Engineer | Bouquet, Thomas Campbell; Lic. No.: S4007 | 155 N LAKE AVE SUITE 600 PASADENA, CA 91101 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/15/2018 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Reinf. Concrete | 10/15/2018 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Shotcrete | 10/15/2018 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Drilled-In Anchors | 10/16/2018 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Reinf. Concrete | 10/16/2018 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Shotcrete | 10/16/2018 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Drilled-In Anchors | 10/17/2018 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Reinf. Concrete | 10/17/2018 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Shotcrete | 10/17/2018 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Drilled-In Anchors | 10/18/2018 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Reinf. Concrete | 10/18/2018 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Shotcrete | 10/18/2018 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Drilled-In Anchors | 10/19/2018 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Reinf. Concrete | 10/19/2018 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Shotcrete | 10/19/2018 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Grading | 2/20/2019 | Conditional Approval | ALAN NOVAK |
| Excavation/Setback/Form/Re-Bar | 3/13/2019 | Partial Approval | ALAN NOVAK |
| Footing/Foundation/Slab | 4/12/2019 | Partial Approval | ALAN NOVAK |
| METHANE-Barrier | 4/12/2019 | Partial Approval | ALAN NOVAK |
| METHANE-Subgrade | 4/12/2019 | Partial Approval | ALAN NOVAK |
| SWPPP-Const. Storm Water | 4/12/2019 | Completed | ALAN NOVAK |
| Wall Anchors | 5/8/2019 | Not Ready for Inspection | ALAN NOVAK |
| Pre-Inspection | 5/13/2019 | Approved | ALAN NOVAK |
| Footing/Foundation/Slab | 5/14/2019 | Partial Approval | ALAN NOVAK |
| METHANE-Barrier | 5/14/2019 | Approved | ALAN NOVAK |
| METHANE-Subgrade | 5/14/2019 | Approved | ALAN NOVAK |
| Footing/Foundation/Slab | 5/21/2019 | Partial Approval | ALAN NOVAK |
| Footing/Foundation/Slab | 5/30/2019 | Partial Approval | ALAN NOVAK |
| Light Gage Steel Frame | 6/5/2019 | Partial Inspection | ALAN NOVAK |
| Excavation/Setback/Form/Re-Bar | 6/14/2019 | Partial Approval | ALAN NOVAK |
| Light Gage Steel Frame | 6/14/2019 | Partial Approval | ALAN NOVAK |
| Light Gage Steel Frame | 6/17/2019 | Partial Approval | ALAN NOVAK |
| Excavation/Setback/Form/Re-Bar | 6/19/2019 | Partial Approval | ALAN NOVAK |
| Footing/Foundation/Slab | 6/19/2019 | Partial Approval | ALAN NOVAK |
| Excavation/Setback/Form/Re-Bar | 6/21/2019 | Partial Approval | ALAN NOVAK |
| Light Gage Steel Frame | 6/25/2019 | Partial Inspection | ALAN NOVAK |
| Light Gage Steel Frame | 7/1/2019 | Partial Approval | JONATHAN ALLEN |
| Excavation/Setback/Form/Re-Bar | 7/2/2019 | Partial Inspection | ALAN NOVAK |
| Footing/Foundation/Slab | 7/2/2019 | Partial Inspection | ALAN NOVAK |
| Light Gage Steel Frame | 7/9/2019 | Partial Approval | ALAN NOVAK |
| Drywall Nailing | 7/10/2019 | Partial Approval | ALAN NOVAK |
| Footing/Foundation/Slab | 7/10/2019 | Partial Approval | ALAN NOVAK |
| Light Gage Steel Frame | 7/12/2019 | Not Ready for Inspection | ALBERT COMISARI |
| Excavation/Setback/Form/Re-Bar | 7/17/2019 | Partial Approval | JONATHAN ALLEN |
| Light Gage Steel Frame | 7/18/2019 | Partial Approval | JONATHAN ALLEN |
| Deputy Reinf. Concrete | 7/22/2019 | Approved | JONATHAN ALLEN |
| Deputy Steel/Welding | 7/22/2019 | Approved | JONATHAN ALLEN |
| Deputy Reinf. Concrete | 7/23/2019 | Conditional Approval | JONATHAN ALLEN |
| Deputy Steel/Welding | 7/23/2019 | Conditional Approval | JONATHAN ALLEN |
| Deputy Reinf. Concrete | 7/24/2019 | Approved | JONATHAN ALLEN |
| Deputy Steel/Welding | 7/24/2019 | Approved | JONATHAN ALLEN |
| Deputy Reinf. Concrete | 7/25/2019 | Approved | JONATHAN ALLEN |
| Deputy Steel/Welding | 7/25/2019 | Approved | JONATHAN ALLEN |
| Light Gage Steel Frame | 7/25/2019 | Partial Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 7/26/2019 | Approved | JONATHAN ALLEN |
| Deputy Steel/Welding | 7/26/2019 | Approved | JONATHAN ALLEN |
| Light Gage Steel Frame | 7/31/2019 | Partial Approval | JONATHAN ALLEN |
| Drywall Nailing | 8/7/2019 | Partial Approval | ALAN NOVAK |
| Green Building Rough | 8/7/2019 | Approved | ALAN NOVAK |
| T-Bar Ceiling | 8/9/2019 | Approved | JONATHAN ALLEN |
| Special/Order Compliance | 8/14/2019 | Approved | JONATHAN ALLEN |
| Excavation/Setback/Form/Re-Bar | 8/19/2019 | Partial Inspection | ALAN NOVAK |
| Excavation/Setback/Form/Re-Bar | 8/26/2019 | Partial Approval | JONATHAN ALLEN |
| Light Gage Steel Frame | 9/3/2019 | Approved | JONATHAN ALLEN |
| Drywall Nailing | 9/11/2019 | Approved | JONATHAN ALLEN |
| Deputy Steel/Welding | 9/19/2019 | Conditional Approval | JONATHAN ALLEN |
| Deputy Steel/Welding | 9/20/2019 | Conditional Approval | JONATHAN ALLEN |
| Deputy Steel/Welding | 9/23/2019 | Approved | JONATHAN ALLEN |
| Light Gage Steel Frame | 10/10/2019 | Corrections Issued | JONATHAN ALLEN |
| Footing/Foundation/Slab | 10/18/2019 | Conditional Approval | JONATHAN ALLEN |
| SWPPP-Const. Storm Water | 10/18/2019 | Completed | JONATHAN ALLEN |
| Special/Order Compliance | 10/30/2019 | Approved | JONATHAN ALLEN |
| Special/Order Compliance | 11/22/2019 | Approved | JONATHAN ALLEN |
| Wood Frame | 12/26/2019 | Partial Approval | JONATHAN ALLEN |
| Drywall Nailing | 12/31/2019 | Not Ready for Inspection | ALBERT COMISARI |
| Special/Order Compliance | 1/3/2020 | Not Ready for Inspection | JONATHAN ALLEN |
| Drywall Nailing | 1/6/2020 | Partial Approval | JONATHAN ALLEN |
| Special/Order Compliance | 1/29/2020 | Approved | JONATHAN ALLEN |
| Final | 7/8/2020 | OK to Issue CofO | JONATHAN ALLEN |
| Footing/Foundation/Slab | 7/8/2020 | Approved | JONATHAN ALLEN |
| Green Building Final | 7/8/2020 | Approved | JONATHAN ALLEN |
| METHANE-Final | 7/8/2020 | Approved | JONATHAN ALLEN |
| METHANE-Rough | 7/8/2020 | Approved | JONATHAN ALLEN |
| Reinforced Masonry Frame | 7/8/2020 | Approved | JONATHAN ALLEN |
| SGSOV-Seismic Gas S/O Valve | 7/8/2020 | SGSOV Approved | JONATHAN ALLEN |
| Smoke Detectors | 7/8/2020 | Approved | JONATHAN ALLEN |
| Structural Steel Frame | 7/8/2020 | Approved | JONATHAN ALLEN |
| Verify Sprinkler Sign Off | 7/8/2020 | Approved | JONATHAN ALLEN |