1635 N FERRARI DR 90210
Certificate Information: 1635 N FERRARI DR 90210
- Application / Permit
- 18010-10000-00486
- Plan Check / Job No.
- B18LA02459
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW TWO STORY SFD W/BASEMENT
- Permit Issued
- Issued on 2/5/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/7/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 2/22/2018 | TSE MING HUANG |
| Green Plans Picked Up | 2/26/2018 | APPLICANT |
| Corrections Issued | 3/8/2018 | TSE MING HUANG |
| Quality Review Completed | 3/19/2018 | VERONICA LOPEZ |
| Building Plans Picked Up | 3/20/2018 | APPLICANT |
| Applicant returned to address corrections | 5/29/2018 | TSE MING HUANG |
| Applicant returned to address corrections | 8/2/2018 | TSE MING HUANG |
| Applicant returned to address corrections | 8/14/2018 | TSE MING HUANG |
| Applicant returned to address corrections | 10/12/2018 | TSE MING HUANG |
| Applicant returned to address corrections | 11/13/2018 | TSE MING HUANG |
| Applicant returned to address corrections | 12/3/2018 | TSE MING HUANG |
| Plan Check Approved | 12/19/2018 | TSE MING HUANG |
| Issued | 2/5/2020 | LADBS |
| CofO in Progress | 7/14/2022 | CARLOS MATAMOROS |
| Permit Finaled | 7/27/2022 | DANIEL ORRANTE |
| CofO Issued | 7/27/2022 | DANIEL ORRANTE |
| Permit Finaled | 7/27/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Encroachment in public way | Cleared | 4/23/2018 | JAMES KHO |
| Eng Process Fee Ord 176,300 | Cleared | 4/23/2018 | MICHAEL CASTILLO |
| Hydrant and Access approval | Cleared | 4/23/2018 | GEORGE SUCHAND |
| Permit | Cleared | 4/23/2018 | MICHAEL CASTILLO |
| BHO/Hillside ordinance | Cleared | 7/13/2018 | CARLA VALLADARES |
| BHO/Hillside ordinance | Cleared | 7/13/2018 | CARLA VALLADARES |
| BHO/Hillside ordinance | Cleared | 7/13/2018 | CARLA VALLADARES |
| Sewer availability | Cleared | 7/13/2018 | CARLA VALLADARES |
| Low Impact Development | Cleared | 7/18/2018 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 7/26/2018 | MICHAEL CASTILLO |
| Green Code | Cleared | 8/2/2018 | COLIN LOREDO |
| Building over 3-story or 36-ft | Cleared | 12/3/2018 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 12/3/2018 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 12/3/2018 | TSE MING HUANG |
| Grading Pre-Inspection | Cleared | 12/3/2018 | TSE MING HUANG |
Contact Information
| Contractor | Sun Developers Inc; Lic. No.: 865631-B | 23371 MULHOLLAND DRIVE #295 WOODLAND HILLS, CA 91364 |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
| Geologist | Hogrefe,, Scott Joseph; Lic. No.: EG1516 | 3157 ESCOLLERA AVE SANTA ROSA VALLEY, CA 93012 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/9/2020 | Partial Inspection | ANTHONY MCDOWALL |
| Pre-Inspection | 3/17/2020 | Approved | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 3/18/2020 | Partial Approval | ANTHONY MCDOWALL |
| Piling/Pier/Caisson | 4/28/2020 | Corrections Issued | ANTHONY MCDOWALL |
| Piling/Pier/Caisson | 4/29/2020 | Partial Approval | ANTHONY MCDOWALL |
| Piling/Pier/Caisson | 5/6/2020 | Partial Inspection | ANTHONY MCDOWALL |
| Piling/Pier/Caisson | 5/15/2020 | Partial Approval | ANTHONY MCDOWALL |
| Deputy Reinf. Concrete | 5/18/2020 | Conditional Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 5/19/2020 | Corrections Issued | ANTHONY MCDOWALL |
| Piling/Pier/Caisson | 5/19/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Piling/Pier/Caisson | 5/20/2020 | Partial Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 6/11/2020 | Partial Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 6/15/2020 | Partial Approval | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 6/25/2020 | Partial Approval | ANTHONY MCDOWALL |
| Deputy Reinf. Concrete | 6/30/2020 | Conditional Approval | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 7/13/2020 | Corrections Issued | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 7/14/2020 | Partial Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 7/28/2020 | Partial Approval | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 9/25/2020 | Corrections Issued | CARLOS MATAMOROS |
| Special/Order Compliance | 9/26/2020 | Partial Inspection | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 9/28/2020 | Partial Approval | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2020 | Partial Approval | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 10/15/2020 | Partial Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 10/21/2020 | Partial Approval | ANTHONY MCDOWALL |
| Underground Mechanical | 11/2/2020 | Corrections Issued | ANTHONY MCDOWALL |
| Underground Mechanical | 11/5/2020 | Partial Approval | MATT KELLERMAN |
| Footing/Foundation/Slab | 11/13/2020 | Partial Approval | ANTHONY MCDOWALL |
| Piling/Pier/Caisson | 1/4/2021 | Partial Approval | ANTHONY MCDOWALL |
| Piling/Pier/Caisson | 1/7/2021 | Partial Approval | ANTHONY MCDOWALL |
| Underground Mechanical | 1/19/2021 | Partial Approval | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 1/25/2021 | Partial Approval | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2021 | Partial Approval | ANTHONY MCDOWALL |
| Masonry Wall/Backfill | 2/1/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2021 | Partial Approval | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2021 | Approved | ANTHONY MCDOWALL |
| Piling/Pier/Caisson | 5/7/2021 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 5/13/2021 | Partial Approval | ANTHONY MCDOWALL |
| Deputy Reinf. Concrete | 5/17/2021 | Conditional Approval | ANTHONY MCDOWALL |
| Sewer | 7/19/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Green Building Rough | 7/21/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Sewer | 7/21/2021 | Partial Approval | ANTHONY MCDOWALL |
| Structural Steel Frame | 7/21/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Verify Sprinkler Sign Off | 7/21/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| HVAC-Rough | 8/3/2021 | Not Ready for Inspection | MATT KELLERMAN |
| PLUMBING-Rough | 8/3/2021 | Not Ready for Inspection | MATT KELLERMAN |
| PLUMBING-Rough | 8/5/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 8/6/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 8/11/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| PLUMBING-Rough | 8/12/2021 | Approved | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 8/17/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 8/20/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 8/30/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 9/13/2021 | Not Ready for Inspection | MATT KELLERMAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 9/16/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 9/28/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 10/1/2021 | No Access for Inspection | MATT KELLERMAN |
| ELECTRICAL-Rough | 10/5/2021 | Partial Approval | MATT KELLERMAN |
| Green Building Rough | 10/7/2021 | Corrections Issued | MATT KELLERMAN |
| Structural Steel Frame | 10/7/2021 | Approved | MATT KELLERMAN |
| Verify Sprinkler Sign Off | 10/7/2021 | Approved | MATT KELLERMAN |
| BUILDING-Rough-Frame | 10/8/2021 | Conditional Approval | CARLOS MATAMOROS |
| Green Building Rough | 10/20/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 10/20/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 10/20/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Shower Pan | 10/22/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 11/1/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 11/1/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Shower Pan | 11/1/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 11/9/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 11/15/2021 | Corrections Issued | STEPHANIE SWANSON |
| Drywall Nailing | 11/15/2021 | Conditional Approval | STEPHANIE SWANSON |
| HVAC-Rough | 11/15/2021 | Corrections Issued | STEPHANIE SWANSON |
| Drywall Nailing | 11/17/2021 | Conditional Approval | RYAN SALAZAR |
| Interior/Exterior Lathing | 11/17/2021 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 11/19/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 11/19/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 11/19/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 12/28/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Sewer | 3/18/2022 | Approved | BRENDAN LOONEY |
| Gas Test | 4/20/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 5/16/2022 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Final | 5/19/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 5/20/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 5/25/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 5/25/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 5/27/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 6/14/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 6/15/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 6/15/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Green Building Final | 6/15/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 6/15/2022 | SGSOV Approved | GERMAN RODRIGUEZ MENDOZA |
| Service/Power Release | 6/15/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Smoke Detectors | 6/15/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 7/13/2022 | OK to Issue CofO | CARLOS MATAMOROS |
| Green Building Final | 7/13/2022 | Approved | CARLOS MATAMOROS |
| Service/Power Release | 7/13/2022 | Approved | CARLOS MATAMOROS |