832 S MARIPOSA AVE 90005

Certificate Information: 832 S MARIPOSA AVE 90005

Application / Permit
18010-10000-00378
Plan Check / Job No.
B18LA01955
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 7-Story 101 unit type IIIA/IA Apartment Building with 2-Story Subterranean Parking Garage. The 7 story superstructure includes 5 story of type IIIA construction above 2 story on-grade type IA construction. The project uses Tier2 of TOC Ordinance.
Permit Issued
Issued on 12/17/2019
Issuing Office
Metro
Current Status
CofO Issued on 12/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/9/2018 APPLICANT
Assigned to Plan Check Engineer 3/8/2018 QUAN NGHIEM
Corrections Issued 3/22/2018 QUAN NGHIEM
Quality Review Completed 3/28/2018 BILL STUTSMAN
Building Plans Picked Up 4/3/2018 APPLICANT
Applicant returned to address corrections 3/5/2019 QUAN NGHIEM
Applicant returned to address corrections 10/9/2019 QUAN NGHIEM
Plan Check Approved 12/17/2019 QUAN NGHIEM
Issued 12/17/2019 LADBS
TCO Issued (Expire Date: 11-28-2022) 6/1/2022 TED RIES
TCO Issued (Expire Date: 05-27-2023) 11/28/2022 ERNESTO CORRAL
CofO in Progress 12/29/2022 RAFAEL ESPINOZA
Permit Finaled 12/29/2022 ERNESTO CORRAL
CofO Issued 12/29/2022 ERNESTO CORRAL
Permit Finaled 12/29/2022 ERNESTO CORRAL

Permit Application Clearance Information

Project located in CRA area Cleared 8/17/2018 JIM URQUHART
Address approval Cleared 2/6/2019 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 2/6/2019 JEANETTE VONG
Highway dedication Cleared 2/6/2019 JEANETTE VONG
Site Plan review Cleared 2/6/2019 KIT AWAKUNI
Building over 3-story or 36-ft Cleared 3/29/2019 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 3/29/2019 CALOSHA APPROVED
Frnt yard landscape/Water mgmt Cleared 4/2/2019 SOPHIE GABEL-SCHEINBAU
Opn space landscape/Water mgmt Cleared 4/2/2019 SOPHIE GABEL-SCHEINBAU
Sewer availability Cleared 8/27/2019 JEANETTE VONG
Green Code Cleared 9/10/2019 QUAN NGHIEM
Density Bonus 12.22.A.31 Cleared 10/9/2019 NICHOLAS KAWAZOE
Low Impact Development Cleared 10/23/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 10/23/2019 JEANIE LAM
Fire Marshall Fire Life Safety Cleared 11/12/2019 WILLIAM JOHNS
Hydrant and Access approval Cleared 11/12/2019 JOHN CONNEALLY
DAS Clearance Cleared 11/13/2019 QUAN NGHIEM
Work Adjacent to Public Way Cleared 12/17/2019 TERRY PHAN

Contact Information

Contractor Frymer Construction; Lic. No.: 860661-B 2461 SANTA MONICA BLVD 134      SANTA MONICA, CA 90404

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/16/2020 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 5/8/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/11/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/14/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 5/15/2020 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 5/15/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/18/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/19/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/20/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/21/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/22/2020 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 5/22/2020 Partial Approval RAFAEL ESPINOZA
Deputy Shotcrete 5/26/2020 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 5/26/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/27/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 5/27/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 5/28/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 5/29/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 6/2/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 6/11/2020 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 6/11/2020 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 7/6/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/7/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/8/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 7/8/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/9/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 7/9/2020 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 7/9/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/10/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 7/10/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 7/14/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 7/15/2020 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 7/15/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Shotcrete 7/16/2020 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 7/16/2020 Partial Approval RAFAEL ESPINOZA
Deputy Shotcrete 7/17/2020 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 7/17/2020 Partial Approval RAFAEL ESPINOZA
Deputy Shotcrete 7/20/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 7/21/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 7/22/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 7/23/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 7/24/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 7/28/2020 Conditional Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 7/28/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 7/29/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 7/30/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 7/31/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 8/12/2020 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 8/18/2020 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 8/20/2020 Not Ready for Inspection RAFAEL ESPINOZA
Green Building Rough 8/21/2020 Approved RAFAEL ESPINOZA
Reinforced Concrete Frame 8/21/2020 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 8/21/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 8/28/2020 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 8/31/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 9/2/2020 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 9/2/2020 Partial Approval RAFAEL ESPINOZA
Reinforced Masonry Frame 9/2/2020 Partial Approval RAFAEL ESPINOZA
Deputy Shotcrete 9/4/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 9/21/2020 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 9/30/2020 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 10/6/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 10/7/2020 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 10/9/2020 Partial Approval RAFAEL ESPINOZA
Reinforced Masonry Frame 10/9/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 11/2/2020 Conditional Approval NICK DANERI
Footing/Foundation/Slab 11/10/2020 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 11/12/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 11/20/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 11/24/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 12/1/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/14/2020 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/16/2020 Corrections Issued RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/17/2020 Partial Approval RAFAEL ESPINOZA
Special/Order Compliance 12/17/2020 Approved RAFAEL ESPINOZA
Drywall Nailing 12/21/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 12/28/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 1/13/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 1/27/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/8/2021 Partial Approval NICK DANERI
Drywall Nailing 2/10/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/11/2021 Corrections Issued RAFAEL ESPINOZA
Drywall Nailing 2/16/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/16/2021 Partial Approval RAFAEL ESPINOZA
Deputy Shotcrete 2/18/2021 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 3/4/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 3/8/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/8/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 3/12/2021 Not Ready for Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/12/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/15/2021 Not Ready for Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/16/2021 Not Ready for Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/17/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/24/2021 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/30/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 4/12/2021 No Access for Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/14/2021 Partial Approval JAMES POWERS
Drywall Nailing 4/19/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/20/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 4/21/2021 Not Ready for Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/21/2021 Not Ready for Inspection RAFAEL ESPINOZA
Drywall Nailing 4/27/2021 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/27/2021 Partial Approval RAFAEL ESPINOZA
Pre-Inspection 5/4/2021 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 5/5/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 5/12/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 5/14/2021 Partial Approval RAFAEL ESPINOZA
Insulation 5/14/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 5/18/2021 Partial Approval RAFAEL ESPINOZA
Insulation 5/18/2021 Partial Approval RAFAEL ESPINOZA
Insulation 5/19/2021 Partial Approval RAFAEL ESPINOZA
Wood Frame 5/19/2021 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 5/20/2021 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 5/20/2021 Not Ready for Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 5/20/2021 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 5/21/2021 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 5/24/2021 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 5/26/2021 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 5/26/2021 Not Ready for Inspection RAFAEL ESPINOZA
Drywall Nailing 5/27/2021 Partial Approval RAFAEL ESPINOZA
Insulation 5/27/2021 Partial Approval RAFAEL ESPINOZA
Wood Frame 5/27/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 6/2/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 6/3/2021 Not Ready for Inspection RAFAEL ESPINOZA
Insulation 6/3/2021 Partial Approval RAFAEL ESPINOZA
Insulation 6/4/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 6/7/2021 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 6/8/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 6/9/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 6/11/2021 Partial Approval RAFAEL ESPINOZA
Insulation 6/11/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 6/21/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 6/21/2021 Partial Approval RAFAEL ESPINOZA
Wood Frame 6/21/2021 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 6/24/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 6/25/2021 Partial Approval JONATHAN QUACH
Light Gage Steel Frame 6/25/2021 Not Ready for Inspection JONATHAN QUACH
Verify Sprinkler Sign Off 6/25/2021 Not Ready for Inspection JONATHAN QUACH
Insulation 6/30/2021 Partial Approval RAFAEL ESPINOZA
Insulation 7/1/2021 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 7/2/2021 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 7/9/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 7/12/2021 Partial Approval RAFAEL ESPINOZA
Insulation 7/12/2021 Partial Approval RAFAEL ESPINOZA
Insulation 7/14/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 7/14/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 7/16/2021 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 7/16/2021 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 7/19/2021 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 7/19/2021 Not Ready for Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 7/21/2021 Partial Approval EDWIN GREGORYONA
Insulation 7/23/2021 Partial Approval EDWIN GREGORYONA
Insulation 7/26/2021 Partial Approval EDWIN GREGORYONA
Pre-Inspection 7/26/2021 Approved EDWIN GREGORYONA
Interior/Exterior Lathing 7/27/2021 Partial Approval JONATHAN QUACH
Drywall Nailing 7/28/2021 Partial Approval EDWIN GREGORYONA
Insulation 7/28/2021 Partial Approval EDWIN GREGORYONA
Pre-Inspection 7/30/2021 Not Ready for Inspection JONATHAN QUACH
Drywall Nailing 8/3/2021 Partial Inspection RAFAEL ESPINOZA
Insulation 8/3/2021 Partial Approval RAFAEL ESPINOZA
Wood Frame 8/4/2021 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 8/5/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 8/10/2021 Partial Approval RAFAEL ESPINOZA
Insulation 8/10/2021 Partial Approval RAFAEL ESPINOZA
Insulation 8/11/2021 Corrections Issued RAFAEL ESPINOZA
Insulation 8/12/2021 Partial Approval RAFAEL ESPINOZA
Insulation 8/19/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 8/20/2021 Partial Approval RAFAEL ESPINOZA
Insulation 8/24/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 8/24/2021 Partial Approval RAFAEL ESPINOZA
Wood Frame 8/26/2021 Not Ready for Inspection RAFAEL ESPINOZA
Insulation 8/27/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 8/27/2021 Partial Approval RAFAEL ESPINOZA
Insulation 9/2/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 9/7/2021 Partial Approval RAFAEL ESPINOZA
Insulation 9/7/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 9/10/2021 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 9/14/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 9/16/2021 Partial Approval RAFAEL ESPINOZA
Insulation 9/20/2021 Partial Approval RAFAEL ESPINOZA
Wood Frame 9/20/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 9/30/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 10/5/2021 Partial Approval RAFAEL ESPINOZA
Insulation 10/5/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 10/7/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 10/20/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 10/22/2021 Not Ready for Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 10/27/2021 Partial Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 10/28/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 11/1/2021 Partial Approval RAFAEL ESPINOZA
Insulation 11/1/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 11/1/2021 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 11/4/2021 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 11/4/2021 Not Ready for Inspection RAFAEL ESPINOZA
Drywall Nailing 11/9/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 11/16/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 11/22/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 11/22/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 11/30/2021 Partial Approval RAFAEL ESPINOZA
Special/Order Compliance 11/30/2021 Approved RAFAEL ESPINOZA
Wood Frame 11/30/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 12/16/2021 Partial Approval DAVID BURKHEAD
Light Gage Steel Frame 12/20/2021 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 12/22/2021 Partial Approval NICK DANERI
Interior/Exterior Lathing 12/28/2021 Partial Approval NICK DANERI
Drywall Nailing 1/3/2022 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 1/3/2022 Partial Approval RAFAEL ESPINOZA
Deputy Drilled-In Anchors 1/26/2022 Conditional Approval NICK DANERI
Masonry Wall/Backfill 1/26/2022 Not Ready for Inspection RAFAEL ESPINOZA
Interior/Exterior Lathing 2/1/2022 Approved RAFAEL ESPINOZA
Masonry Wall/Backfill 2/3/2022 Not Ready for Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 2/22/2022 Partial Approval TED RIES
Masonry Wall/Backfill 2/28/2022 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 3/11/2022 Partial Approval NICK DANERI
Footing/Foundation/Slab 3/16/2022 Not Ready for Inspection RAFAEL ESPINOZA
Drywall Nailing 3/29/2022 Partial Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 4/21/2022 Partial Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 4/21/2022 Not Ready for Inspection RAFAEL ESPINOZA
Drywall Nailing 4/25/2022 Approved RAFAEL ESPINOZA
Final 4/25/2022 Not Ready for Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 4/25/2022 Approved RAFAEL ESPINOZA
Green Building Final 4/25/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 4/25/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 4/25/2022 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 4/25/2022 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 4/25/2022 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 4/25/2022 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 4/25/2022 Not Ready for Inspection RAFAEL ESPINOZA
Special/Order Compliance 5/4/2022 Partial Inspection RAFAEL ESPINOZA
Special/Order Compliance 5/6/2022 Approved RAFAEL ESPINOZA
Reinforced Concrete Frame 5/10/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/11/2022 Conditional Approval NICK DANERI
Final 5/18/2022 Partial Inspection RAFAEL ESPINOZA
Green Building Final 5/18/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 5/18/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 5/18/2022 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 5/18/2022 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 5/18/2022 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 5/18/2022 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 5/18/2022 Not Ready for Inspection RAFAEL ESPINOZA
Final 5/20/2022 Partial Inspection RAFAEL ESPINOZA
Green Building Final 5/20/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 5/20/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 5/20/2022 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 5/20/2022 SGSOV Approved RAFAEL ESPINOZA
Smoke Detectors 5/20/2022 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 5/20/2022 Approved RAFAEL ESPINOZA
Wood Frame 5/20/2022 Approved RAFAEL ESPINOZA
Final 5/25/2022 Partial Inspection RAFAEL ESPINOZA
Green Building Final 5/25/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 5/25/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 5/25/2022 Not Ready for Inspection RAFAEL ESPINOZA
Smoke Detectors 5/25/2022 Not Ready for Inspection RAFAEL ESPINOZA
Green Building Final 5/26/2022 Approved RAFAEL ESPINOZA
Final 5/27/2022 Not Ready for Inspection RAFAEL ESPINOZA
Green Building Final 5/27/2022 Approved RAFAEL ESPINOZA
Reinforced Concrete Frame 5/27/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 5/27/2022 Not Ready for Inspection RAFAEL ESPINOZA
Smoke Detectors 5/27/2022 Not Ready for Inspection RAFAEL ESPINOZA
Special/Order Compliance 5/31/2022 Partial Inspection RAFAEL ESPINOZA
Special/Order Compliance 11/9/2022 Partial Inspection RAFAEL ESPINOZA
Final 12/22/2022 Partial Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 12/22/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 12/22/2022 Not Ready for Inspection RAFAEL ESPINOZA
Smoke Detectors 12/22/2022 Approved RAFAEL ESPINOZA
Final 12/29/2022 OK to Issue CofO RAFAEL ESPINOZA
Reinforced Concrete Frame 12/29/2022 Approved RAFAEL ESPINOZA
Reinforced Masonry Frame 12/29/2022 Approved RAFAEL ESPINOZA