|
Pre-Inspection
|
6/13/2019
|
Approved
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
6/19/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
6/19/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
6/20/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
6/20/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
6/21/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
6/21/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
6/21/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
METHANE-Barrier
|
6/21/2019
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
METHANE-Subgrade
|
6/21/2019
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
6/24/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
6/24/2019
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
6/25/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Other (see comments)
|
6/26/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
6/26/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
6/26/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
6/27/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Shotcrete
|
6/27/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Methane Barrier
|
6/28/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
6/28/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
6/28/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/1/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/2/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
7/2/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/3/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
7/3/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/5/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
7/5/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Methane Barrier
|
7/8/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
7/8/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Methane Barrier
|
7/9/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/9/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
7/9/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/10/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
7/10/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/11/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Excavation/Setback/Form/Re-Bar
|
7/11/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Concrete
|
7/12/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
7/12/2019
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
7/12/2019
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
7/15/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/16/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
7/16/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/17/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
7/17/2019
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Deputy Methane Barrier
|
7/18/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/18/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
7/18/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Methane Barrier
|
7/19/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/19/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
7/19/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/22/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
7/22/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
METHANE-Barrier
|
7/22/2019
|
Approved
|
ERNESTO CORRAL
|
|
METHANE-Subgrade
|
7/22/2019
|
Approved
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/23/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
7/23/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
7/23/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
METHANE-Rough
|
7/23/2019
|
Approved
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/24/2019
|
Conditional Approval
|
JEFFREY FULTON
|
|
Deputy Reinf. Concrete
|
7/25/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Excavation/Setback/Form/Re-Bar
|
7/25/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Concrete
|
7/26/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
7/26/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Methane Barrier
|
7/29/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/29/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
7/29/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Methane Barrier
|
7/30/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/30/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
7/30/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
7/30/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
7/30/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Methane Barrier
|
7/31/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/31/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
7/31/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
7/31/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Masonry Wall/Backfill
|
7/31/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Methane Barrier
|
8/1/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/1/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
8/1/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Methane Barrier
|
8/2/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/2/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
8/2/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
8/2/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Methane Barrier
|
8/5/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/5/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Methane Barrier
|
8/6/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/6/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/7/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/8/2019
|
Conditional Approval
|
JEFFREY FULTON
|
|
Deputy Reinf. Concrete
|
8/9/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
8/13/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
8/13/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Methane Barrier
|
8/14/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
8/14/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Methane Barrier
|
8/15/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Masonry Wall/Backfill
|
8/15/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Methane Barrier
|
8/16/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
8/16/2019
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Deputy Methane Barrier
|
8/20/2019
|
Conditional Approval
|
FRED WOHLFARTH
|
|
Deputy Pre-Stress Concrete
|
8/20/2019
|
Conditional Approval
|
FRED WOHLFARTH
|
|
Deputy Reinf. Concrete
|
8/20/2019
|
Conditional Approval
|
FRED WOHLFARTH
|
|
Deputy Reinf. Masonry
|
8/20/2019
|
Conditional Approval
|
FRED WOHLFARTH
|
|
Excavation/Setback/Form/Re-Bar
|
8/20/2019
|
Partial Approval
|
FRED WOHLFARTH
|
|
Footing/Foundation/Slab
|
8/20/2019
|
Partial Approval
|
FRED WOHLFARTH
|
|
Deputy Methane Barrier
|
8/21/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Pre-Stress Concrete
|
8/21/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
8/21/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
8/21/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Green Building Rough
|
8/21/2019
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Reinforced Concrete Frame
|
8/21/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Verify Sprinkler Sign Off
|
8/21/2019
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Deputy Methane Barrier
|
8/22/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Pre-Stress Concrete
|
8/22/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
8/22/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
8/22/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
8/22/2019
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Deputy Pre-Stress Concrete
|
8/23/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
8/23/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
8/23/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Masonry Wall/Backfill
|
8/23/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Footing/Foundation/Slab
|
8/26/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Masonry Wall/Backfill
|
8/26/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
8/27/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/27/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
8/27/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Masonry Wall/Backfill
|
8/27/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
8/28/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/28/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
8/28/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
8/28/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
8/29/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/29/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
8/29/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
8/29/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
8/30/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/30/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
8/30/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
8/30/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
9/3/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
9/3/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
9/3/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Methane Barrier
|
9/4/2019
|
Conditional Approval
|
JEFFREY FULTON
|
|
Deputy Pre-Stress Concrete
|
9/4/2019
|
Conditional Approval
|
JEFFREY FULTON
|
|
Deputy Reinf. Concrete
|
9/4/2019
|
Conditional Approval
|
JEFFREY FULTON
|
|
Deputy Reinf. Masonry
|
9/4/2019
|
Conditional Approval
|
JEFFREY FULTON
|
|
Masonry Wall/Backfill
|
9/4/2019
|
Conditional Approval
|
JEFFREY FULTON
|
|
Deputy Pre-Stress Concrete
|
9/5/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
9/5/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
9/5/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
9/6/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
9/6/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
9/6/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
9/6/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Masonry Wall/Backfill
|
9/6/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
9/9/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
9/9/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
9/9/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
9/10/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
9/10/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
9/10/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Masonry Wall/Backfill
|
9/10/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Reinforced Concrete Frame
|
9/10/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Pre-Stress Concrete
|
9/11/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
9/11/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
9/11/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
9/12/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Green Building Rough
|
9/12/2019
|
Approved
|
ERNESTO CORRAL
|
|
Reinforced Concrete Frame
|
9/12/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Verify Sprinkler Sign Off
|
9/12/2019
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Masonry Wall/Backfill
|
9/16/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
9/17/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
9/17/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
9/17/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Reinforced Concrete Frame
|
9/17/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Verify Sprinkler Sign Off
|
9/17/2019
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
9/18/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
9/18/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
9/18/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
9/19/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
9/19/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
9/19/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
9/20/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
9/20/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
9/20/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
9/23/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
9/23/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
9/23/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Pre-Stress Concrete
|
9/24/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
9/24/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
9/24/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Pre-Stress Concrete
|
9/25/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
9/25/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
9/25/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Pre-Stress Concrete
|
9/26/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
9/26/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
9/26/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
9/27/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
9/27/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
9/27/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
9/30/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
9/30/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
9/30/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Reinforced Concrete Frame
|
9/30/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Reinforced Masonry Frame
|
9/30/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Verify Sprinkler Sign Off
|
9/30/2019
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
10/1/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
10/1/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
10/1/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
10/2/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
10/2/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
10/2/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
10/3/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
10/3/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
10/3/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
10/4/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
10/4/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
10/4/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
10/8/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
10/8/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
10/8/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Footing/Foundation/Slab
|
10/8/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Reinforced Concrete Frame
|
10/8/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Verify Sprinkler Sign Off
|
10/8/2019
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Deputy Pre-Stress Concrete
|
10/9/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
10/9/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
10/9/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Pre-Stress Concrete
|
10/10/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
10/10/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
10/10/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Pre-Stress Concrete
|
10/11/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
10/11/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
10/11/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Pre-Stress Concrete
|
10/15/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
10/15/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
10/15/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
10/15/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
10/16/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
10/16/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
10/16/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Light Gage Steel Frame
|
10/16/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
10/17/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
10/17/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
10/17/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
10/18/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
10/18/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
10/18/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
10/18/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Reinforced Concrete Frame
|
10/18/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Verify Sprinkler Sign Off
|
10/18/2019
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
10/21/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
10/21/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
10/21/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
10/22/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
10/22/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
10/22/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
10/23/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
10/23/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
10/23/2019
|
Partial Approval
|
JAMES POWERS
|
|
Reinforced Concrete Frame
|
10/23/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Pre-Stress Concrete
|
10/24/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
10/24/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
10/24/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
10/25/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
10/25/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
10/25/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
10/25/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
10/28/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Pre-Stress Concrete
|
10/29/2019
|
Approved
|
JEFF BYTHEWAY
|
|
Deputy Reinf. Concrete
|
10/29/2019
|
Approved
|
JEFF BYTHEWAY
|
|
Deputy Reinf. Masonry
|
10/29/2019
|
Approved
|
JEFF BYTHEWAY
|
|
Deputy Pre-Stress Concrete
|
10/30/2019
|
Approved
|
JEFF BYTHEWAY
|
|
Deputy Reinf. Concrete
|
10/30/2019
|
Approved
|
JEFF BYTHEWAY
|
|
Deputy Reinf. Masonry
|
10/30/2019
|
Approved
|
JEFF BYTHEWAY
|
|
Excavation/Setback/Form/Re-Bar
|
10/30/2019
|
Partial Approval
|
JEFF BYTHEWAY
|
|
Footing/Foundation/Slab
|
10/30/2019
|
Partial Approval
|
JEFF BYTHEWAY
|
|
Deputy Pre-Stress Concrete
|
10/31/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
10/31/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
10/31/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Pre-Stress Concrete
|
11/1/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Concrete
|
11/1/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Masonry
|
11/1/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Excavation/Setback/Form/Re-Bar
|
11/1/2019
|
Not Ready for Inspection
|
LESLIE TRUJILLO
|
|
Reinforced Concrete Frame
|
11/1/2019
|
Not Ready for Inspection
|
LESLIE TRUJILLO
|
|
Verify Sprinkler Sign Off
|
11/1/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Pre-Stress Concrete
|
11/4/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
11/4/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
11/4/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
11/4/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
11/4/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/4/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Masonry Wall/Backfill
|
11/4/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
11/5/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Light Gage Steel Frame
|
11/5/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
11/6/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
11/6/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
11/7/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
11/8/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
11/8/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
11/8/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
11/8/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
11/8/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Verify Sprinkler Sign Off
|
11/8/2019
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
11/12/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
11/12/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
11/12/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
11/12/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
11/13/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Pre-Stress Concrete
|
11/13/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
11/13/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
11/13/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Drilled-In Anchors
|
11/14/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
11/14/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
11/14/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
11/14/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
11/14/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/14/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
11/15/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
11/15/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
11/15/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
11/15/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
11/15/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/15/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
11/18/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
11/18/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/18/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
11/19/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/20/2019
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
11/21/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
11/21/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
11/21/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Drilled-In Anchors
|
11/22/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
11/22/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
11/22/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
11/25/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
11/25/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
11/25/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
11/25/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
11/25/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/25/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
11/26/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
11/26/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
11/26/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
11/26/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
11/26/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Reinforced Concrete Frame
|
11/26/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Verify Sprinkler Sign Off
|
11/26/2019
|
Approved
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
11/27/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
11/27/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
11/27/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
12/3/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
12/3/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
12/3/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
12/3/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
12/4/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
12/4/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
12/4/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
12/4/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Light Gage Steel Frame
|
12/4/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
12/5/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Pre-Stress Concrete
|
12/5/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
12/5/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
12/5/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Drilled-In Anchors
|
12/6/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
12/6/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
12/6/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
12/6/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
12/6/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/6/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
12/9/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Pre-Stress Concrete
|
12/9/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
12/9/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
12/9/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
12/9/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
12/10/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
12/10/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
12/10/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
12/10/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
12/11/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
12/11/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
12/11/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
12/11/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/11/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Wall Anchors
|
12/11/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
12/12/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
12/12/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
12/12/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
12/13/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
12/13/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
12/13/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
12/13/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
12/13/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/13/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
12/16/2019
|
Conditional Approval
|
JEFFREY FULTON
|
|
Deputy Reinf. Concrete
|
12/16/2019
|
Conditional Approval
|
JEFFREY FULTON
|
|
Deputy Reinf. Masonry
|
12/16/2019
|
Conditional Approval
|
JEFFREY FULTON
|
|
Deputy Drilled-In Anchors
|
12/17/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
12/17/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
12/17/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
12/17/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/17/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
12/17/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
12/18/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
12/18/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
12/18/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
12/18/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
12/19/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
12/19/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
12/19/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/19/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Light Gage Steel Frame
|
12/19/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
12/20/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
12/20/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
12/20/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
12/23/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
12/23/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
12/23/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
12/30/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
12/30/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
12/30/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
12/31/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
12/31/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
12/31/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
1/2/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
1/2/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
1/2/2020
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
1/2/2020
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/2/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
1/3/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
1/3/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
1/3/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
1/6/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
1/6/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
1/6/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
1/6/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Wood Frame
|
1/6/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
1/7/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
1/7/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
1/7/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
1/7/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
1/8/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
1/8/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
1/8/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
1/9/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
1/9/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
1/9/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
1/10/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
1/10/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
1/10/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Reinforced Masonry Frame
|
1/10/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
1/13/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
1/13/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
1/13/2020
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
1/13/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
1/14/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/15/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Structural Steel Frame
|
1/15/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
1/21/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
1/22/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
1/22/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
1/22/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
1/23/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
1/23/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
1/23/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
1/24/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
1/24/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
1/24/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
1/24/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Light Gage Steel Frame
|
1/24/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
1/27/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
1/27/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
1/27/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
1/27/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Light Gage Steel Frame
|
1/27/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
1/28/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
1/28/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
1/28/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
1/28/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Wood Frame
|
1/28/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
1/29/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
1/29/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
1/30/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
2/3/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
2/3/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Light Gage Steel Frame
|
2/3/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
2/4/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/4/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Light Gage Steel Frame
|
2/4/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
2/5/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/5/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Insulation
|
2/5/2020
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Deputy Steel/Welding
|
2/6/2020
|
Conditional Approval
|
DANIEL COLLINS
|
|
Deputy Wood Construction
|
2/6/2020
|
Conditional Approval
|
DANIEL COLLINS
|
|
Drywall Nailing
|
2/6/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
2/6/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
2/7/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Wood Construction
|
2/10/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/10/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
2/11/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
2/18/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/18/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
2/19/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
2/19/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
2/20/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
2/21/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
2/21/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/21/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
2/24/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
2/24/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
2/24/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/24/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
2/25/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
2/25/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/27/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Wall Anchors
|
2/27/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Wood Frame
|
2/27/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
2/28/2020
|
Partial Approval
|
RONALD PACHECO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/2/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
3/2/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
3/4/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Wood Frame
|
3/4/2020
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Deputy Wood Construction
|
3/5/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/5/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
3/5/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/6/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
3/6/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
3/9/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/10/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
3/10/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/13/2020
|
No Access for Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
3/13/2020
|
No Access for Inspection
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
3/16/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/17/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
3/17/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Wood Frame
|
3/17/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
3/18/2020
|
Conditional Approval
|
DANIEL COLLINS
|
|
Deputy Steel/Welding
|
3/18/2020
|
Conditional Approval
|
DANIEL COLLINS
|
|
Deputy Steel/Welding
|
3/19/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Steel/Welding
|
3/20/2020
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Steel/Welding
|
3/23/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
3/23/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/23/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
3/23/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
3/25/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/25/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
3/25/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
3/26/2020
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/26/2020
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
3/26/2020
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
3/27/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/27/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
3/27/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
4/1/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/1/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
4/1/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
4/3/2020
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/3/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
4/3/2020
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
4/6/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/6/2020
|
Corrections Issued
|
RAFAEL ESPINOZA
|
|
Insulation
|
4/6/2020
|
Corrections Issued
|
RAFAEL ESPINOZA
|
|
Drywall Nailing
|
4/11/2020
|
Off-Hour Fees Due
|
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/11/2020
|
Off-Hour Fees Due
|
|
|
Insulation
|
4/11/2020
|
Off-Hour Fees Due
|
|
|
Drywall Nailing
|
4/18/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/18/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Insulation
|
4/18/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/20/2020
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Insulation
|
4/20/2020
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Wood Frame
|
4/20/2020
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Insulation
|
4/25/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Interior/Exterior Lathing
|
4/25/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Special/Order Compliance
|
4/27/2020
|
Approved
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
4/29/2020
|
Conditional Approval
|
JONATHAN QUACH
|
|
Light Gage Steel Frame
|
4/29/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Wood Frame
|
4/29/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Wood Frame
|
5/5/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Drywall Nailing
|
5/6/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/6/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
5/6/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
5/6/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
5/6/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
5/7/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
5/7/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
5/9/2020
|
Partial Approval
|
DAVID TSAU
|
|
Deputy Wood Construction
|
5/11/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/12/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
5/12/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/13/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
5/13/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/15/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
5/15/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/19/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
5/19/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
5/19/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
5/20/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
5/22/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Wood Frame
|
5/22/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
5/27/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
5/29/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/2/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
6/2/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Interior/Exterior Lathing
|
6/2/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
6/2/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Methane Barrier
|
6/4/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Methane Barrier
|
6/5/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/5/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
6/5/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/8/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Insulation
|
6/8/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
6/8/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/9/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Insulation
|
6/9/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/11/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
6/11/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/15/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
6/15/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
6/15/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
6/18/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Pre-Inspection
|
6/18/2020
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
6/18/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
6/22/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
6/23/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
6/23/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
6/23/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
6/24/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
6/25/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
6/25/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
6/26/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/30/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
6/30/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
6/30/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/1/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
7/1/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Interior/Exterior Lathing
|
7/1/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/6/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Insulation
|
7/6/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
7/6/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/8/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
7/8/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Interior/Exterior Lathing
|
7/8/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
7/9/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
7/9/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
7/10/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/10/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
7/10/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/13/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Interior/Exterior Lathing
|
7/13/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/15/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
7/15/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
7/17/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/17/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
7/17/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
7/17/2020
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Insulation
|
7/22/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
7/22/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
7/23/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/23/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
7/23/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
7/23/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
7/27/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Interior/Exterior Lathing
|
7/27/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/28/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
7/28/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Interior/Exterior Lathing
|
7/28/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
7/29/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Interior/Exterior Lathing
|
7/29/2020
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
7/29/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
7/31/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
7/31/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Interior/Exterior Lathing
|
7/31/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
7/31/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
8/3/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/3/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Insulation
|
8/3/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
8/3/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
8/4/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
8/4/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/4/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
8/4/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
8/4/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
8/5/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/5/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
8/5/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
8/5/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
8/6/2020
|
Conditional Approval
|
LANNY MERRICK
|
|
Insulation
|
8/10/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
8/10/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/12/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
8/12/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
8/12/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
8/12/2020
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Insulation
|
8/14/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Interior/Exterior Lathing
|
8/14/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
8/14/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/19/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
8/19/2020
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
8/19/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/21/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Interior/Exterior Lathing
|
8/21/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
8/25/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
8/26/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
8/27/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/27/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
8/27/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Interior/Exterior Lathing
|
8/27/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
8/28/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
8/31/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
9/1/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
9/2/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
9/3/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
9/4/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
9/8/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
9/8/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Interior/Exterior Lathing
|
9/8/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
9/9/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Excavation/Setback/Form/Re-Bar
|
9/9/2020
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
9/10/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
9/11/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
9/11/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
9/14/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
9/15/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
9/15/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
9/17/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
9/17/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
9/17/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
9/18/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
9/21/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
9/22/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
9/22/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Interior/Exterior Lathing
|
9/22/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
9/23/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
9/24/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
9/25/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
9/28/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/29/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
9/29/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
9/29/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
9/30/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
10/1/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
10/5/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
10/6/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
10/6/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
10/6/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Interior/Exterior Lathing
|
10/13/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
10/16/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Interior/Exterior Lathing
|
10/16/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
10/20/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
10/22/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
10/22/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
10/22/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
10/23/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
10/28/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
11/5/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
11/6/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
11/6/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
11/10/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
11/12/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Masonry Wall/Backfill
|
11/12/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Interior/Exterior Lathing
|
11/16/2020
|
Approved
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
12/4/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
12/11/2020
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
12/11/2020
|
Partial Approval
|
NICK DANERI
|
|
Masonry Wall/Backfill
|
12/16/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Final
|
1/15/2021
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
1/15/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Green Building Final
|
1/15/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
1/15/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Reinforced Masonry Frame
|
1/15/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
SGSOV-Seismic Gas S/O Valve
|
1/15/2021
|
SGSOV Not Ready
|
RAFAEL ESPINOZA
|
|
Smoke Detectors
|
1/15/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Pre-Inspection
|
2/1/2021
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Smoke Detectors
|
2/17/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Special/Order Compliance
|
2/17/2021
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Final
|
2/18/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
2/18/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Green Building Final
|
2/18/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
2/18/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Reinforced Masonry Frame
|
2/18/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
SGSOV-Seismic Gas S/O Valve
|
2/18/2021
|
SGSOV Not Ready
|
RAFAEL ESPINOZA
|
|
Final
|
3/10/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
3/10/2021
|
Approved
|
RAFAEL ESPINOZA
|
|
Green Building Final
|
3/10/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
3/10/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Reinforced Masonry Frame
|
3/10/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
SGSOV-Seismic Gas S/O Valve
|
3/10/2021
|
SGSOV Approved
|
RAFAEL ESPINOZA
|
|
Smoke Detectors
|
3/10/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Special/Order Compliance
|
3/16/2021
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Special/Order Compliance
|
3/19/2021
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Final
|
4/20/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Green Building Final
|
4/20/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
4/20/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Reinforced Masonry Frame
|
4/20/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Smoke Detectors
|
4/20/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Final
|
4/23/2021
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Green Building Final
|
4/23/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
4/23/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Reinforced Masonry Frame
|
4/23/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Smoke Detectors
|
4/23/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Deputy Drilled-In Anchors
|
4/27/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Final
|
6/2/2021
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Green Building Final
|
6/2/2021
|
Approved
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
6/2/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Reinforced Masonry Frame
|
6/2/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Smoke Detectors
|
6/2/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Final
|
6/21/2021
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
6/21/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Reinforced Masonry Frame
|
6/21/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Smoke Detectors
|
6/21/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Final
|
7/8/2021
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
7/8/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Reinforced Masonry Frame
|
7/8/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Smoke Detectors
|
7/8/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Special/Order Compliance
|
7/9/2021
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
7/13/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Shotcrete
|
7/13/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Excavation/Setback/Form/Re-Bar
|
8/9/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Excavation/Setback/Form/Re-Bar
|
8/11/2021
|
Approved
|
RAFAEL ESPINOZA
|
|
Final
|
8/12/2021
|
Corrections Issued
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
8/12/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Reinforced Masonry Frame
|
8/12/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Smoke Detectors
|
8/12/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Special/Order Compliance
|
8/12/2021
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Special/Order Compliance
|
8/18/2021
|
Approved
|
RAFAEL ESPINOZA
|
|
Special/Order Compliance
|
8/25/2021
|
Approved
|
RAFAEL ESPINOZA
|
|
Final
|
10/26/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
10/26/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Reinforced Masonry Frame
|
10/26/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Smoke Detectors
|
10/26/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Final
|
12/16/2021
|
Conditional Approval
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
12/16/2021
|
Approved
|
EDWIN GREGORYONA
|
|
Reinforced Masonry Frame
|
12/16/2021
|
Approved
|
EDWIN GREGORYONA
|
|
Smoke Detectors
|
12/16/2021
|
Approved
|
EDWIN GREGORYONA
|
|
Final
|
12/23/2021
|
Not Ready for Inspection
|
NICK DANERI
|
|
Special/Order Compliance
|
1/5/2022
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Final
|
1/25/2022
|
OK to Issue CofO
|
RAFAEL ESPINOZA
|