Deputy Reinf. Concrete
|
1/6/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
1/7/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
1/8/2021
|
Conditional Approval
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
1/11/2021
|
Partial Inspection
|
NICK DANERI
|
|
METHANE-Barrier
|
1/11/2021
|
Not Ready for Inspection
|
NICK DANERI
|
|
METHANE-Subgrade
|
1/11/2021
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
2/23/2021
|
Partial Approval
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
2/23/2021
|
Not Ready for Inspection
|
NICK DANERI
|
|
METHANE-Barrier
|
2/23/2021
|
Not Ready for Inspection
|
NICK DANERI
|
|
METHANE-Subgrade
|
2/23/2021
|
Not Ready for Inspection
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
3/4/2021
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
3/5/2021
|
Partial Approval
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
3/5/2021
|
Partial Approval
|
NICK DANERI
|
|
METHANE-Barrier
|
3/5/2021
|
Not Ready for Inspection
|
NICK DANERI
|
|
METHANE-Subgrade
|
3/5/2021
|
Not Ready for Inspection
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
3/8/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
3/19/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
3/22/2021
|
Conditional Approval
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
3/22/2021
|
Not Ready for Inspection
|
NICK DANERI
|
|
METHANE-Barrier
|
3/22/2021
|
Not Ready for Inspection
|
NICK DANERI
|
|
METHANE-Subgrade
|
3/22/2021
|
Not Ready for Inspection
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
3/24/2021
|
Partial Approval
|
NICK DANERI
|
|
METHANE-Barrier
|
3/24/2021
|
Not Ready for Inspection
|
NICK DANERI
|
|
METHANE-Subgrade
|
3/24/2021
|
Not Ready for Inspection
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
3/25/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
4/20/2021
|
Conditional Approval
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
4/22/2021
|
Partial Approval
|
NICK DANERI
|
|
METHANE-Barrier
|
4/22/2021
|
Partial Inspection
|
NICK DANERI
|
|
METHANE-Subgrade
|
4/22/2021
|
Partial Inspection
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
4/26/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
4/27/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Shotcrete
|
5/3/2021
|
Conditional Approval
|
NICK DANERI
|
|
Green Building Rough
|
5/5/2021
|
Not Ready for Inspection
|
NICK DANERI
|
|
METHANE-Rough
|
5/5/2021
|
Not Ready for Inspection
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
5/5/2021
|
Not Ready for Inspection
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
5/5/2021
|
Not Ready for Inspection
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
5/6/2021
|
Partial Approval
|
JAMES POWERS
|
|
Green Building Rough
|
5/7/2021
|
Not Ready for Inspection
|
JAMES POWERS
|
|
METHANE-Rough
|
5/7/2021
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Reinforced Concrete Frame
|
5/7/2021
|
Partial Approval
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
5/7/2021
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Shotcrete
|
5/10/2021
|
Partial Approval
|
JAMES POWERS
|
|
Masonry Wall/Backfill
|
5/21/2021
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
5/24/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
6/24/2021
|
Partial Approval
|
JAMES POWERS
|
|
Green Building Rough
|
6/25/2021
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
METHANE-Rough
|
6/25/2021
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Reinforced Masonry Frame
|
6/25/2021
|
Partial Approval
|
JONATHAN QUACH
|
|
Verify Sprinkler Sign Off
|
6/25/2021
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Deputy Reinf. Masonry
|
6/29/2021
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
7/23/2021
|
Partial Approval
|
JONATHAN QUACH
|
|
METHANE-Barrier
|
7/23/2021
|
Approved
|
JONATHAN QUACH
|
|
METHANE-Subgrade
|
7/23/2021
|
Approved
|
JONATHAN QUACH
|
|
Deputy Reinf. Concrete
|
7/26/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Green Building Rough
|
10/4/2021
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
METHANE-Rough
|
10/4/2021
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Reinforced Concrete Frame
|
10/4/2021
|
Partial Approval
|
JONATHAN QUACH
|
|
Verify Sprinkler Sign Off
|
10/4/2021
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Green Building Rough
|
10/22/2021
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
METHANE-Rough
|
10/22/2021
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Reinforced Concrete Frame
|
10/22/2021
|
Partial Approval
|
JONATHAN QUACH
|
|
Verify Sprinkler Sign Off
|
10/22/2021
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Green Building Rough
|
11/23/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
METHANE-Rough
|
11/23/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Reinforced Concrete Frame
|
11/23/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Verify Sprinkler Sign Off
|
11/23/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Green Building Rough
|
11/30/2021
|
Not Ready for Inspection
|
NICK DANERI
|
|
METHANE-Rough
|
11/30/2021
|
Approved
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
11/30/2021
|
Partial Approval
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
11/30/2021
|
Not Ready for Inspection
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
12/2/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Steel/Welding
|
1/21/2022
|
Conditional Approval
|
TED RIES
|
|
Deputy Steel/Welding
|
1/24/2022
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Steel/Welding
|
1/25/2022
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Steel/Welding
|
1/26/2022
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Wood Construction
|
2/3/2022
|
Conditional Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/4/2022
|
Partial Approval
|
NICK DANERI
|
|
Structural Steel Frame
|
2/4/2022
|
Partial Inspection
|
NICK DANERI
|
|
Wood Frame
|
2/4/2022
|
Partial Approval
|
NICK DANERI
|
|
Deputy Drilled-In Anchors
|
2/7/2022
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Steel/Welding
|
2/8/2022
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Steel/Welding
|
2/10/2022
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Steel/Welding
|
2/14/2022
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Wood Construction
|
2/23/2022
|
Conditional Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/23/2022
|
Partial Approval
|
NICK DANERI
|
|
Pre-Inspection
|
2/23/2022
|
Conditional Approval
|
NICK DANERI
|
|
Wood Frame
|
2/23/2022
|
Partial Approval
|
NICK DANERI
|
|
Deputy Wood Construction
|
3/16/2022
|
Conditional Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/17/2022
|
Partial Approval
|
NICK DANERI
|
|
Wood Frame
|
3/17/2022
|
Partial Approval
|
NICK DANERI
|
|
Deputy Wood Construction
|
4/6/2022
|
Conditional Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/7/2022
|
Partial Approval
|
NICK DANERI
|
|
Wood Frame
|
4/7/2022
|
Corrections Issued
|
NICK DANERI
|
|
Drywall Nailing
|
6/1/2022
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/1/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Drywall Nailing
|
6/8/2022
|
Partial Approval
|
NICK DANERI
|
|
Special/Order Compliance
|
6/22/2022
|
Partial Inspection
|
NICK DANERI
|
|
Insulation
|
8/23/2022
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
8/29/2022
|
Partial Approval
|
NICK DANERI
|
|
Wood Frame
|
9/16/2022
|
Partial Approval
|
NICK DANERI
|
|
Wood Frame
|
9/21/2022
|
Partial Inspection
|
NICK DANERI
|
|
Green Building Rough
|
9/26/2022
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Insulation
|
9/26/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Reinforced Masonry Frame
|
9/26/2022
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Verify Sprinkler Sign Off
|
9/26/2022
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Masonry Wall/Backfill
|
9/28/2022
|
Partial Approval
|
DAVID BURKHEAD
|
|
Insulation
|
10/5/2022
|
Partial Approval
|
TED RIES
|
|
Drywall Nailing
|
10/24/2022
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Insulation
|
10/24/2022
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Wood Frame
|
10/24/2022
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Drywall Nailing
|
10/27/2022
|
Partial Approval
|
GREGORY POMISH
|
|
Insulation
|
11/1/2022
|
Corrections Issued
|
NICK DANERI
|
|
Wood Frame
|
11/10/2022
|
Partial Approval
|
NICK DANERI
|
|
Insulation
|
11/15/2022
|
Partial Approval
|
NICK DANERI
|
|
Wood Frame
|
11/29/2022
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
12/20/2022
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
1/19/2023
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
2/2/2023
|
Partial Approval
|
NICK DANERI
|
|
Interior/Exterior Lathing
|
2/7/2023
|
Partial Approval
|
ALAN MORELOS
|
|
Interior/Exterior Lathing
|
3/3/2023
|
Partial Approval
|
ALFREDO LOPEZ
|
|
Pre-Inspection
|
4/11/2023
|
Corrections Issued
|
NICK DANERI
|
|
Special/Order Compliance
|
4/11/2023
|
Partial Inspection
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
6/2/2023
|
Partial Approval
|
NICK DANERI
|
|
Pre-Inspection
|
8/18/2023
|
Partial Inspection
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
8/31/2023
|
Partial Approval
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
8/31/2023
|
Partial Approval
|
NICK DANERI
|
|
Special/Order Compliance
|
9/19/2023
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
10/23/2023
|
Partial Approval
|
NICK DANERI
|
|
Special/Order Compliance
|
10/23/2023
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
10/30/2023
|
Partial Approval
|
NICK DANERI
|
|
Pre-Inspection
|
12/6/2023
|
Corrections Issued
|
NICK DANERI
|
|
Final
|
1/25/2024
|
Corrections Issued
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
1/25/2024
|
Approved
|
NICK DANERI
|
|
Green Building Final
|
1/25/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Green Building Rough
|
1/25/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
1/25/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Reinforced Masonry Frame
|
1/25/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
SGSOV-Seismic Gas S/O Valve
|
1/25/2024
|
SGSOV Not Ready
|
NICK DANERI
|
|
Smoke Detectors
|
1/25/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
1/25/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Final
|
2/6/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Green Building Final
|
2/6/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Green Building Rough
|
2/6/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
2/6/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Reinforced Masonry Frame
|
2/6/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
SGSOV-Seismic Gas S/O Valve
|
2/6/2024
|
SGSOV Not Ready
|
NICK DANERI
|
|
Smoke Detectors
|
2/6/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
2/6/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Special/Order Compliance
|
2/12/2024
|
Partial Inspection
|
NICK DANERI
|
|
Special/Order Compliance
|
3/13/2024
|
Partial Inspection
|
NICK DANERI
|
|
Final
|
6/11/2024
|
Corrections Issued
|
NICK DANERI
|
|
Green Building Final
|
6/11/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Green Building Rough
|
6/11/2024
|
Approved
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
6/11/2024
|
Approved
|
NICK DANERI
|
|
Reinforced Masonry Frame
|
6/11/2024
|
Approved
|
NICK DANERI
|
|
SGSOV-Seismic Gas S/O Valve
|
6/11/2024
|
SGSOV Approved
|
NICK DANERI
|
|
Smoke Detectors
|
6/11/2024
|
Approved
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
6/11/2024
|
Approved
|
NICK DANERI
|
|
Special/Order Compliance
|
6/12/2024
|
Partial Inspection
|
NICK DANERI
|
|
Special/Order Compliance
|
7/5/2024
|
Not Ready for Inspection
|
LUIS CCAMACHO
|
|
Special/Order Compliance
|
7/10/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Verify Rec and Parks Fee Memo
|
7/10/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Final
|
7/12/2024
|
Conditional Approval
|
NICK DANERI
|
|
Green Building Final
|
7/12/2024
|
Approved
|
NICK DANERI
|