225 E 43RD PL 90011
Certificate Information: 225 E 43RD PL 90011
- Application / Permit
- 18010-10000-00183
- Plan Check / Job No.
- B18LA00947
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED ADU PER AB 494 AND SB 229 WITH 3-CAR GARAGE
- Permit Issued
- Issued on 1/10/2020
- Issuing Office
- Metro
- Current Status
- Issued on 1/10/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/17/2018 | APPLICANT |
| Green Plans Picked Up | 2/7/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2018 | SINA KHOSRAVI |
| Corrections Issued | 2/15/2018 | SINA KHOSRAVI |
| Quality Review Completed | 2/23/2018 | BILL STUTSMAN |
| Building Plans Picked Up | 3/2/2018 | APPLICANT |
| Applicant returned to address corrections | 10/18/2018 | SINA KHOSRAVI |
| Applicant returned to address corrections | 12/9/2019 | SINA KHOSRAVI |
| Plan Check Approved | 12/20/2019 | SINA KHOSRAVI |
| Issued | 1/10/2020 | LADBS |
Permit Application Clearance Information
| Green Code | Cleared | 3/13/2018 | KATHRYN BUTTERWORTH |
| Address approval | Cleared | 3/21/2018 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 3/21/2018 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 3/21/2018 | ROBERT DUFF |
| Sewer availability | Cleared | 3/21/2018 | STEVE MELGAR |
| Low Impact Development | Cleared | 10/5/2018 | RYAN HUDSON |
| Construction near power lines | Cleared | 11/6/2018 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 6/26/2019 | JEANETTE VONG |
| Green Code | Cleared | 12/9/2019 | SINA KHOSRAVI |
| Hydrant and Access approval | Cleared | 12/9/2019 | JEREMY CARTER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yassin, Diaa Aldin; Lic. No.: C56295 | 2939 CAMINO DEL TOMASINI HACIENDA HEIGHTS, CA 91745 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 3/20/2020 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 3/24/2020 | Approved | JOAQUIN GREENOUGH |
| METHANE-Barrier | 3/24/2020 | Approved | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 3/24/2020 | Approved | JOAQUIN GREENOUGH |
| Wood Frame | 4/24/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 5/13/2020 | Corrections Issued | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 5/13/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 5/13/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| METHANE-Rough | 5/13/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 5/13/2020 | Approved | ROBERT MCDOWELL |
| Underground Mechanical | 5/13/2020 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 5/13/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 7/30/2020 | Conditional Approval | ROBERT MCDOWELL |
| Green Building Rough | 7/30/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 7/30/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Insulation | 10/27/2020 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 10/27/2020 | Partial Approval | OSVALDO PARAMO |
| Drywall Nailing | 11/16/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 11/16/2020 | Approved | ROBERT MCDOWELL |
| Shower Pan | 7/22/2021 | Not Ready for Inspection | JESUS PINEDA |
| Shower Pan | 9/2/2021 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 4/6/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 4/6/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 4/6/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 4/6/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Service/Power Release | 4/6/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Smoke Detectors | 4/6/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 4/6/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |