20101 W VENTURA BLVD 91364

Certificate Information: 20101 W VENTURA BLVD 91364

Application / Permit
18010-10000-00166
Plan Check / Job No.
B18LA00870
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(22) Storage Building
Work Description
(N) ONE-STORY COVERED TRASH ENCLOSURE WITH BICYCLE PARKING (18' x 21'-4", 333 SF) FOR (N) DRIVE-THRU RESTAURANT PER DIR-2016-3785-SPP
Permit Issued
Issued on 1/15/2020
Issuing Office
Metro
Current Status
CofO Issued on 9/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/17/2018 APPLICANT
Assigned to Plan Check Engineer 1/25/2018 CHRISTOPHER KOMANCHECK
Disabled Access Plans Picked Up 1/30/2018 APPLICANT
Green Plans Picked Up 1/30/2018 APPLICANT
Corrections Issued 2/9/2018 CHRISTOPHER KOMANCHECK
Quality Review Completed 2/14/2018 SHUNYU ZHANG
Building Plans Picked Up 2/15/2018 APPLICANT
Applicant returned to address corrections 3/2/2018 CHRISTOPHER KOMANCHECK
Applicant returned to address corrections 5/8/2019 CHRISTOPHER KOMANCHECK
Plan Check Approved 8/22/2019 CHRISTOPHER KOMANCHECK
Issued 1/15/2020 LADBS
CofO in Progress 3/26/2024 CAMERON CHABAN
Permit Finaled 9/17/2024 JEFFREY DURAN
CofO Issued 9/17/2024 JEFFREY DURAN
Permit Finaled 9/17/2024 JEFFREY DURAN

Permit Application Clearance Information

Hydrant and Access approval Cleared 10/17/2018 JOHN DALLAS
Sewer availability Cleared 10/17/2018 RUDY TERRIQUEZ.
Eng Process Fee Ord 176,300 Cleared 11/1/2018 JEANETTE VONG
"D" conditions Cleared 11/9/2018 NOAH MCCOY
ZA Case Cleared 11/9/2018 NOAH MCCOY
ZA Case Cleared 11/9/2018 NOAH MCCOY
ZA Case Cleared 11/9/2018 NOAH MCCOY
ZA Case Cleared 11/9/2018 NOAH MCCOY
ZA Case Cleared 11/9/2018 NOAH MCCOY
ZA Case Cleared 11/9/2018 NOAH MCCOY
ZA Case Cleared 11/9/2018 NOAH MCCOY
ZA Case Cleared 11/9/2018 NOAH MCCOY
Green Code Cleared 11/15/2018 COLIN LOREDO
Specific Plan Cleared 1/15/2019 RINA LARA
Roof/Waste drainage to street Cleared 2/5/2019 APEKSHYA BAJRACHARYA
GPI Written Notices Cleared 5/8/2019 CHRISTOPHER KOMANCHECK
Grading Pre-Inspection Cleared 5/8/2019 CHRISTOPHER KOMANCHECK
Highway dedication Cleared 5/15/2019 ERIK BEASLEY
Low Impact Development Cleared 5/15/2019 SEAN SHAHMIRI

Contact Information

Architect Hatfield, Russell; Lic. No.: C22468 195 S 'C' STREET, SUITE 200      TUSTIN, CA 92780
Contractor Cirks Construction Inc; Lic. No.: 763589-B 1442 E LINCOLN AVENUE #334      ORANGE, CA 92865
Engineer Decker, Randy Jacob; Lic. No.: C81077 265 SOUTH ANITA DR STE 111      ORANGE, CA 92868
Engineer Gatus, Edgar Lozano; Lic. No.: C70687 1416 W DAMON AVE      ANAHEIM, CA 92802
Engineer Sheppard, Steven Thomas; Lic. No.: S5446 28782 EL MIO LANE      MISSION VIEJO, CA 92692

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/3/2020 Partial Approval JEFFREY DURAN
Footing/Foundation/Slab 3/3/2020 Approved JEFFREY DURAN
Pre-Inspection 3/3/2020 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 4/20/2020 Approved HAMID PISHEHVAR
Excavation/Setback/Form/Re-Bar 4/27/2020 Partial Approval ROBERT DAVIS
Green Building Rough 5/7/2020 Not Ready for Inspection ROBERT DAVIS
Verify Sprinkler Sign Off 5/7/2020 Not Ready for Inspection ROBERT DAVIS
Wood Frame 5/7/2020 Not Ready for Inspection ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 5/12/2020 Approved ROBERT DAVIS
Green Building Rough 5/12/2020 Approved ROBERT DAVIS
Verify Sprinkler Sign Off 5/12/2020 Not Ready for Inspection ROBERT DAVIS
Wood Frame 5/12/2020 Not Ready for Inspection ROBERT DAVIS
Drywall Nailing 9/17/2020 Approved HAMID PISHEHVAR
Final 9/17/2020 Not Ready for Inspection HAMID PISHEHVAR
Green Building Final 9/17/2020 Approved HAMID PISHEHVAR
Reinforced Masonry Frame 9/17/2020 Approved HAMID PISHEHVAR
SGSOV-Seismic Gas S/O Valve 9/17/2020 SGSOV Approved HAMID PISHEHVAR
Smoke Detectors 9/17/2020 Approved HAMID PISHEHVAR
Structural Steel Frame 9/17/2020 Approved HAMID PISHEHVAR
Verify Sprinkler Sign Off 9/17/2020 Approved HAMID PISHEHVAR
Wood Frame 9/17/2020 Approved HAMID PISHEHVAR
Final 10/1/2020 Not Ready for Inspection ROBERT DAVIS
Final 10/16/2020 Partial Approval HAMID PISHEHVAR
Final 10/27/2020 Partial Inspection HAMID PISHEHVAR
Final 4/13/2023 Partial Inspection CAMERON CHABAN
Final 3/26/2024 OK to Issue CofO CAMERON CHABAN