20101 W VENTURA BLVD 91364
Certificate Information: 20101 W VENTURA BLVD 91364
- Application / Permit
- 18010-10000-00165
- Plan Check / Job No.
- B18LA00870
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant - Drive Through Fast Food
- Work Description
- New one-story restaurant with Drive-thru per DIR-2016-3785-SPP
- Permit Issued
- Issued on 1/15/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2018 | CHRISTOPHER KOMANCHECK |
| Disabled Access Plans Picked Up | 1/30/2018 | APPLICANT |
| Green Plans Picked Up | 1/30/2018 | APPLICANT |
| Corrections Issued | 2/9/2018 | CHRISTOPHER KOMANCHECK |
| Quality Review Completed | 2/14/2018 | SHUNYU ZHANG |
| Building Plans Picked Up | 2/15/2018 | APPLICANT |
| Applicant returned to address corrections | 3/2/2018 | CHRISTOPHER KOMANCHECK |
| Applicant returned to address corrections | 5/8/2019 | CHRISTOPHER KOMANCHECK |
| Plan Check Approved | 8/22/2019 | CHRISTOPHER KOMANCHECK |
| Issued | 1/15/2020 | LADBS |
| TCO Issued (Expire Date: 05-17-2021) | 11/18/2020 | RICKEY JACKSON |
| TCO Issued (Expire Date: 10-31-2021) | 5/4/2021 | RICKEY JACKSON |
| TCO Issued (Expire Date: 04-16-2022) | 10/18/2021 | JEFFREY DURAN |
| TCO Issued (Expire Date: 10-12-2022) | 4/15/2022 | RICKEY JACKSON |
| TCO Issued (Expire Date: 04-09-2023) | 10/11/2022 | RICKEY JACKSON |
| TCO Issued (Expire Date: 10-01-2023) | 4/4/2023 | RICKEY JACKSON |
| TCO Issued (Expire Date: 04-01-2024) | 10/4/2023 | RICKEY JACKSON |
| TCO Issued (Expire Date: 09-22-2024) | 3/26/2024 | JEFFREY DURAN |
| CofO in Progress | 9/19/2024 | CAMERON CHABAN |
| Permit Finaled | 9/19/2024 | JEFFREY DURAN |
| CofO Issued | 9/19/2024 | JEFFREY DURAN |
| Permit Finaled | 9/19/2024 | JEFFREY DURAN |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 10/17/2018 | JOHN DALLAS |
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2018 | JEANETTE VONG |
| "D" conditions | Cleared | 11/2/2018 | NOAH MCCOY |
| Drive-through fast food | Cleared | 11/2/2018 | NOAH MCCOY |
| ZA Case | Cleared | 11/2/2018 | NOAH MCCOY |
| ZA Case | Cleared | 11/2/2018 | NOAH MCCOY |
| ZA Case | Cleared | 11/2/2018 | NOAH MCCOY |
| ZA Case | Cleared | 11/2/2018 | NOAH MCCOY |
| ZA Case | Cleared | 11/2/2018 | NOAH MCCOY |
| ZA Case | Cleared | 11/2/2018 | NOAH MCCOY |
| Food Service Establishment | Cleared | 11/7/2018 | PAWAN VERMA |
| Prkng lot landscape/Water mgmt | Cleared | 11/8/2018 | NOAH MCCOY |
| Site Plan review | Cleared | 11/8/2018 | NOAH MCCOY |
| Specific Plan | Cleared | 11/8/2018 | NOAH MCCOY |
| ZA Case | Cleared | 11/8/2018 | NOAH MCCOY |
| ZA Case | Cleared | 11/8/2018 | NOAH MCCOY |
| DAS Clearance | Cleared | 11/14/2018 | SHINE LIN |
| Green Code | Cleared | 11/15/2018 | COLIN LOREDO |
| Fire Marshall Fire Life Safety | Cleared | 12/13/2018 | DOMINIQUE MEDINA |
| Low Impact Development | Cleared | 12/13/2018 | RYAN HUDSON |
| Driveway location | Cleared | 2/5/2019 | ALBERT ISAGULIAN |
| Driveway location | Cleared | 2/5/2019 | ALBERT ISAGULIAN |
| Internal circulation | Cleared | 2/5/2019 | ALBERT ISAGULIAN |
| Roof/Waste drainage to street | Cleared | 2/5/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 3/1/2019 | KARAN PATEL |
| Highway dedication | Cleared | 4/18/2019 | JULIUS GARCIA |
| Permit | Cleared | 4/22/2019 | MARKOS PEREZ-BRAN |
| GPI Written Notices | Cleared | 5/8/2019 | CHRISTOPHER KOMANCHECK |
| Grading Pre-Inspection | Cleared | 5/8/2019 | CHRISTOPHER KOMANCHECK |
| Food establishment approval | Cleared | 5/15/2019 | LACDHS APPROVED |
| Miscellaneous | Cleared | 8/21/2019 | MARC WOERSCHING |
Contact Information
| Architect | Hatfield, Russell; Lic. No.: C22468 | 195 S 'C' STREET, SUITE 200 TUSTIN, CA 92780 |
| Contractor | Cirks Construction Inc; Lic. No.: 763589-B | 1442 E LINCOLN AVENUE #334 ORANGE, CA 92865 |
| Engineer | Decker, Randy Jacob; Lic. No.: C81077 | 265 SOUTH ANITA DR STE 111 ORANGE, CA 92868 |
| Engineer | Gatus, Edgar Lozano; Lic. No.: C70687 | 1416 W DAMON AVE ANAHEIM, CA 92802 |
| Engineer | Sheppard, Steven Thomas; Lic. No.: S5446 | 28782 EL MIO LANE MISSION VIEJO, CA 92692 |
Inspector Information
| ROBERT DAVIS, (818) 374-1125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/3/2020 | Partial Approval | JEFFREY DURAN |
| Footing/Foundation/Slab | 3/3/2020 | Partial Approval | JEFFREY DURAN |
| Piling/Pier/Caisson | 3/3/2020 | Partial Approval | JEFFREY DURAN |
| Pre-Inspection | 3/3/2020 | Approved | JEFFREY DURAN |
| Deputy Reinf. Concrete | 4/17/2020 | Conditional Approval | JEFFREY DURAN |
| Excavation/Setback/Form/Re-Bar | 4/20/2020 | Approved | HAMID PISHEHVAR |
| Footing/Foundation/Slab | 4/20/2020 | Approved | HAMID PISHEHVAR |
| Structural Steel Frame | 4/20/2020 | Approved | HAMID PISHEHVAR |
| Wall Anchors | 4/20/2020 | Approved | HAMID PISHEHVAR |
| Deputy Reinf. Concrete | 4/21/2020 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Concrete | 4/29/2020 | Conditional Approval | JEFFREY DURAN |
| Excavation/Setback/Form/Re-Bar | 4/29/2020 | Partial Approval | ROBERT DAVIS |
| Deputy Reinf. Concrete | 4/30/2020 | Conditional Approval | JEFFREY DURAN |
| Deputy Steel/Welding | 5/1/2020 | Conditional Approval | JEFFREY DURAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2020 | Partial Approval | ROBERT DAVIS |
| Deputy Reinf. Concrete | 5/15/2020 | Conditional Approval | JEFFREY DURAN |
| Deputy Wood Construction | 5/18/2020 | Conditional Approval | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2020 | Not Ready for Inspection | ROBERT DAVIS |
| Deputy Wood Construction | 5/19/2020 | Conditional Approval | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2020 | Partial Approval | ROBERT DAVIS |
| Green Building Rough | 5/19/2020 | Not Ready for Inspection | ROBERT DAVIS |
| Light Gage Steel Frame | 5/19/2020 | Not Ready for Inspection | ROBERT DAVIS |
| Verify Sprinkler Sign Off | 5/19/2020 | Not Ready for Inspection | ROBERT DAVIS |
| Deputy Steel/Welding | 5/21/2020 | Conditional Approval | ROBERT DAVIS |
| Deputy Wood Construction | 6/9/2020 | Approved | HAMID PISHEHVAR |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2020 | Partial Approval | HAMID PISHEHVAR |
| Green Building Rough | 6/9/2020 | Not Ready for Inspection | HAMID PISHEHVAR |
| Insulation | 6/9/2020 | Approved | HAMID PISHEHVAR |
| Verify Sprinkler Sign Off | 6/9/2020 | Partial Approval | HAMID PISHEHVAR |
| Wood Frame | 6/9/2020 | Partial Approval | HAMID PISHEHVAR |
| Drywall Nailing | 6/12/2020 | Approved | ROBERT DAVIS |
| Green Building Rough | 6/12/2020 | Approved | ROBERT DAVIS |
| Interior/Exterior Lathing | 6/19/2020 | Approved | ROBERT DAVIS |
| Deputy Steel/Welding | 7/7/2020 | Conditional Approval | JEFFREY DURAN |
| T-Bar Ceiling | 7/15/2020 | Not Ready for Inspection | VAHE KELEDJIAN |
| T-Bar Ceiling | 7/20/2020 | Conditional Approval | ROBERT DAVIS |
| Final | 10/26/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Green Building Final | 10/26/2020 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 10/26/2020 | SGSOV Approved | JEFFREY FULTON |
| Smoke Detectors | 10/26/2020 | Approved | JEFFREY FULTON |
| Verify Sprinkler Sign Off | 10/26/2020 | Approved | JEFFREY FULTON |
| Wood Frame | 10/26/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 11/2/2020 | Not Ready for Inspection | ROBERT DAVIS |
| Green Building Final | 11/2/2020 | Not Ready for Inspection | ROBERT DAVIS |
| Wood Frame | 11/2/2020 | Approved | ROBERT DAVIS |
| Final | 11/13/2020 | Not Ready for Inspection | HAMID PISHEHVAR |
| Green Building Final | 11/13/2020 | Not Ready for Inspection | HAMID PISHEHVAR |
| Special/Order Compliance | 4/21/2021 | Approved | HAMID PISHEHVAR |
| Special/Order Compliance | 10/6/2021 | Not Ready for Inspection | JEFFREY DURAN |
| Special/Order Compliance | 3/23/2022 | Not Ready for Inspection | CAMERON CHABAN |
| Special/Order Compliance | 9/13/2022 | Not Ready for Inspection | JEFFREY DURAN |
| Special/Order Compliance | 3/15/2023 | Partial Inspection | CAMERON CHABAN |
| Final | 4/13/2023 | Partial Inspection | CAMERON CHABAN |
| Green Building Final | 4/13/2023 | Conditional Approval | CAMERON CHABAN |
| Special/Order Compliance | 4/13/2023 | Not Ready for Inspection | STEVEN LEVITT |
| Special/Order Compliance | 9/6/2023 | Partial Inspection | CAMERON CHABAN |
| Special/Order Compliance | 3/5/2024 | Partial Inspection | ROBERT DAVIS |
| Final | 3/18/2024 | OK for TCO | CAMERON CHABAN |
| Green Building Final | 3/18/2024 | Conditional Approval | CAMERON CHABAN |
| Special/Order Compliance | 8/27/2024 | Partial Inspection | ROBERT DAVIS |
| Final | 9/19/2024 | OK to Issue CofO | CAMERON CHABAN |
| Green Building Final | 9/19/2024 | Approved | CAMERON CHABAN |