5170 W ADAMS BLVD 90016

Certificate Information: 5170 W ADAMS BLVD 90016

Application / Permit
18010-10000-00077
Plan Check / Job No.
B18LA00415
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(11) Hotel
Work Description
New 3-story, Type VA, 43- guest room Hotel with retail and restaurant on Ground floor over 1 level, Type IA, subterranean parking garage. Core and Shell only.
Permit Issued
Issued on 4/10/2019
Issuing Office
Metro
Current Status
CofO Issued on 11/8/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/19/2018 APPLICANT
Assigned to Plan Check Engineer 2/1/2018 KESETE HAREGOT
Corrections Issued 2/14/2018 KESETE HAREGOT
Quality Review Completed 2/20/2018 JOHN VASQUEZ
Building Plans Picked Up 2/21/2018 APPLICANT
Applicant returned to address corrections 12/21/2018 KESETE HAREGOT
Applicant returned to address corrections 1/10/2019 KESETE HAREGOT
Applicant returned to address corrections 2/26/2019 KESETE HAREGOT
Plan Check Approved 4/5/2019 KESETE HAREGOT
Issued 4/10/2019 LADBS
TCO Issued (Expire Date: 01-17-2022) 7/21/2021 ERNESTO CORRAL
CofO in Progress 10/25/2021 EDWIN GREGORYONA
CofO Issued 11/8/2021 ERNESTO CORRAL
Permit Finaled 11/8/2021 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/12/2018 NAZILA NOORIFAR
Permit Cleared 6/12/2018 NAZILA NOORIFAR
Project located in CRA area Cleared 8/9/2018 JIM URQUHART
Project located in CRA area Cleared 8/9/2018 JIM URQUHART
Driveway location Cleared 12/3/2018 COLLINS ALLAN
Address approval Cleared 12/6/2018 CELINA MORENO
ZI Cleared 12/7/2018 CHRISTOPHER PINA
Frnt yard landscape/Water mgmt Cleared 12/21/2018 LATANYA ROUX
Hydrant and Access approval Cleared 1/9/2019 JOHN CONNEALLY
Sewer availability Cleared 1/10/2019 NAZILA NOORIFAR
ZA Case Cleared 1/10/2019 DIANA JIMENEZ
Bicycle Parking Cleared 1/14/2019 KAREN LE
Low Impact Development Cleared 1/15/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 1/15/2019 STEVE MELGAR
Stormwater Pollution Mitigatn Cleared 1/16/2019 ORVAL HERNANDEZ-MARCI
Work Adjacent to Public Way Cleared 1/18/2019 TERRY PHAN
Fire Marshall Fire Life Safety Cleared 1/31/2019 MENOA AGHAJANI
Green Code Cleared 1/31/2019 COLIN LOREDO
Highway dedication Cleared 2/25/2019 MICHAEL CASTILLO
DAS Clearance Cleared 2/26/2019 ELIZABETH TOMS
Construction near power lines Cleared 3/26/2019 RIDWAN HARDY
Construction within easement Cleared 3/26/2019 RIDWAN HARDY
Miscellaneous Cleared 4/3/2019 MICHAEL CASTILLO

Contact Information

Architect Denari,, Neil Martin; Lic. No.: C29351 NEIL M. DENARI ARCHITECTS   4335 W. ADAMS BLVD.    LOS ANGELES, CA 90018
Contractor Owner-Builder       ,
Engineer Funk,, David Lyle; Lic. No.: S5421 319 MAIN STREET      EL SEGUNDO, CA 90245
Engineer Larocca,, Francis Joseph; Lic. No.: C75121 1821 PACIFIC COAST HWY 38      HERMOSA BEACH, CA 90254
Engineer Rosell,, David T; Lic. No.: L6281 3505 CADILLACE AVENUE BLDG 0-108      COSTA MESA, CA 92626

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/2/2019 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 12/3/2019 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 12/6/2019 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 12/9/2019 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 12/11/2019 Conditional Approval LARRY ARNICK
Footing/Foundation/Slab 12/11/2019 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 12/12/2019 Conditional Approval LARRY ARNICK
Deputy Shotcrete 12/16/2019 Conditional Approval LARRY ARNICK
Green Building Rough 12/16/2019 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 12/16/2019 Partial Inspection LARRY ARNICK
Verify Sprinkler Sign Off 12/16/2019 Not Ready for Inspection LARRY ARNICK
Deputy Shotcrete 12/17/2019 Conditional Approval LARRY ARNICK
Reinforced Masonry Frame 12/18/2019 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 12/19/2019 Conditional Approval LARRY ARNICK
Deputy Shotcrete 12/19/2019 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 12/20/2019 Partial Approval JAMES POWERS
Deputy Shotcrete 12/20/2019 Partial Approval JAMES POWERS
Deputy Shotcrete 12/30/2019 Conditional Approval LARRY ARNICK
Green Building Rough 12/30/2019 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 12/30/2019 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 12/30/2019 Not Ready for Inspection LARRY ARNICK
Deputy Shotcrete 12/31/2019 Conditional Approval LARRY ARNICK
Reinforced Masonry Frame 12/31/2019 Partial Approval LARRY ARNICK
Deputy Shotcrete 1/2/2020 Conditional Approval LARRY ARNICK
Green Building Rough 1/2/2020 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 1/2/2020 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 1/2/2020 Not Ready for Inspection LARRY ARNICK
Deputy Shotcrete 1/3/2020 Conditional Approval LARRY ARNICK
Footing/Foundation/Slab 1/9/2020 Not Ready for Inspection LARRY ARNICK
Green Building Rough 1/10/2020 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 1/10/2020 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 1/10/2020 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 1/31/2020 Approved LARRY ARNICK
Green Building Rough 2/5/2020 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 2/5/2020 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 2/5/2020 Not Ready for Inspection LARRY ARNICK
Reinforced Masonry Frame 2/10/2020 Partial Approval LARRY ARNICK
Green Building Rough 2/12/2020 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 2/12/2020 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 2/12/2020 Not Ready for Inspection LARRY ARNICK
Reinforced Masonry Frame 2/13/2020 Partial Approval LARRY ARNICK
Structural Steel Frame 2/13/2020 Partial Approval LARRY ARNICK
Deputy Shotcrete 2/14/2020 Conditional Approval LARRY ARNICK
Green Building Rough 3/13/2020 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 3/13/2020 Partial Approval LARRY ARNICK
Special/Order Compliance 3/13/2020 Partial Inspection LARRY ARNICK
Verify Sprinkler Sign Off 3/13/2020 Partial Inspection LARRY ARNICK
Deputy Wood Construction 4/14/2020 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 4/15/2020 Partial Approval LARRY ARNICK
Green Building Rough 4/22/2020 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 4/22/2020 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 4/22/2020 Not Ready for Inspection LARRY ARNICK
Deputy Steel/Welding 4/24/2020 Conditional Approval LARRY ARNICK
Green Building Rough 4/24/2020 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 4/24/2020 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 4/24/2020 Not Ready for Inspection LARRY ARNICK
Deputy Wood Construction 5/6/2020 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 5/7/2020 Partial Approval LARRY ARNICK
Deputy Wood Construction 5/15/2020 Conditional Approval LARRY ARNICK
Deputy Wood Construction 5/27/2020 Conditional Approval LARRY ARNICK
Green Building Rough 5/27/2020 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 5/27/2020 Not Ready for Inspection LARRY ARNICK
Wood Frame 5/27/2020 Not Ready for Inspection LARRY ARNICK
Deputy Wood Construction 5/29/2020 Conditional Approval LARRY ARNICK
Deputy Wood Construction 6/3/2020 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 6/3/2020 Not Ready for Inspection LARRY ARNICK
Green Building Rough 6/9/2020 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 6/9/2020 Not Ready for Inspection LARRY ARNICK
Wood Frame 6/9/2020 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 6/16/2020 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 6/18/2020 Partial Approval LARRY ARNICK
Deputy Wood Construction 6/22/2020 Conditional Approval LARRY ARNICK
Insulation 6/22/2020 Partial Approval LARRY ARNICK
Insulation 6/26/2020 Partial Approval LARRY ARNICK
Drywall Nailing 7/9/2020 Partial Approval LARRY ARNICK
Green Building Rough 7/9/2020 Not Ready for Inspection LARRY ARNICK
Green Building Rough 8/3/2020 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 8/3/2020 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 8/3/2020 Not Ready for Inspection LARRY ARNICK
Wood Frame 8/3/2020 Partial Approval LARRY ARNICK
Insulation 8/5/2020 Partial Approval LARRY ARNICK
Drywall Nailing 8/11/2020 Partial Approval LARRY ARNICK
Green Building Rough 8/11/2020 Not Ready for Inspection LARRY ARNICK
Green Building Rough 8/21/2020 Approved LARRY ARNICK
Light Gage Steel Frame 8/21/2020 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 8/21/2020 Not Ready for Inspection LARRY ARNICK
Wood Frame 8/21/2020 Not Ready for Inspection LARRY ARNICK
Insulation 8/24/2020 Partial Approval LARRY ARNICK
Light Gage Steel Frame 9/14/2020 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 9/18/2020 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 9/30/2020 Partial Approval LARRY ARNICK
Insulation 10/26/2020 Partial Approval LARRY ARNICK
Special/Order Compliance 1/15/2021 Approved LARRY ARNICK
Pre-Inspection 2/3/2021 Partial Inspection LARRY ARNICK
Light Gage Steel Frame 2/16/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 2/25/2021 Not Ready for Inspection RUSSELL BONVOULOIR
Drywall Nailing 3/1/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 3/3/2021 Partial Approval EDWIN GREGORYONA
Special/Order Compliance 4/8/2021 Partial Inspection EDWIN GREGORYONA
Insulation 4/12/2021 Partial Approval TIMOTHY BUXTON
Drywall Nailing 4/16/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 4/26/2021 Partial Approval EDWIN GREGORYONA
Reinforced Masonry Frame 4/26/2021 Partial Inspection EDWIN GREGORYONA
Special/Order Compliance 4/27/2021 Approved EDWIN GREGORYONA
Light Gage Steel Frame 4/30/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 5/5/2021 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 5/10/2021 Partial Approval EDWIN GREGORYONA
Pre-Inspection 5/21/2021 Approved EDWIN GREGORYONA
Special/Order Compliance 6/4/2021 Approved EDWIN GREGORYONA
Special/Order Compliance 6/9/2021 Approved EDWIN GREGORYONA
Special/Order Compliance 6/15/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 10/12/2021 Approved EDWIN GREGORYONA
Final 10/12/2021 Conditional Approval EDWIN GREGORYONA
Green Building Final 10/12/2021 Approved EDWIN GREGORYONA
Reinforced Concrete Frame 10/12/2021 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 10/12/2021 SGSOV Approved EDWIN GREGORYONA
Smoke Detectors 10/12/2021 Approved EDWIN GREGORYONA
Verify Sprinkler Sign Off 10/12/2021 Approved EDWIN GREGORYONA
Wood Frame 10/12/2021 Approved EDWIN GREGORYONA
Final 10/15/2021 Conditional Approval EDWIN GREGORYONA