917 S BERENDO ST 1-10 90006

Certificate Information: 917 S BERENDO ST 1-10 90006

Application / Permit
18010-10000-00075
Plan Check / Job No.
B18LA00410
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONSTRUCTION OF A NEW 12,192 SF, 10 UNIT, 4 STORY APARTMENT. GROUND LEVEL PARKING AND BASEMENT PARKING GARAGE WITH ROOF DECK. CONSTRUCTION TYPE III-A, AND IA FOR THE GARAGE
Permit Issued
Issued on 2/7/2019
Issuing Office
Metro
Current Status
CofO Issued on 10/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/9/2018 APPLICANT
Assigned to Plan Check Engineer 1/18/2018 MOHAMMAD FIROUZBAKHT
Corrections Issued 1/22/2018 MOHAMMAD FIROUZBAKHT
Quality Review Completed 1/26/2018 ARMEN JIVALAGIAN
Green Plans Picked Up 1/26/2018 APPLICANT
Disabled Access Plans Picked Up 1/30/2018 APPLICANT
Building Plans Picked Up 4/12/2018 APPLICANT
Plan Check Approved 2/4/2019 MOHAMMAD FIROUZBAKHT
Issued 2/7/2019 LADBS
TCO Issued (Expire Date: 11-14-2023) 5/18/2023 TED RIES
CofO in Progress 10/20/2023 RAFAEL ESPINOZA
CofO Issued 10/20/2023 ERNESTO CORRAL
Permit Finaled 10/20/2023 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 1/31/2018 ADRIAN SANCHEZ
Highway dedication Cleared 1/31/2018 ADRIAN SANCHEZ
Permit Cleared 1/31/2018 ADRIAN SANCHEZ
Project located in CRA area Cleared 1/31/2018 JIM URQUHART
Hydrant and Access approval Cleared 2/15/2018 JOHN CONNEALLY
Opn space landscape/Water mgmt Cleared 5/9/2018 BRIAN CARR
Green Code Cleared 5/14/2018 WILLIAM ROSE
DAS Clearance Cleared 9/5/2018 MOHAMMAD FIROUZBAKHT
Low Impact Development Cleared 1/15/2019 MITESH PATEL
Eng Process Fee Ord 176,300 Cleared 1/28/2019 CELINA MORENO
Roof/Waste drainage to street Cleared 1/28/2019 CELINA MORENO
Sewer availability Cleared 1/28/2019 CELINA MORENO
Work Adjacent to Public Way Cleared 2/1/2019 BOK GOH
Building over 3-story or 36-ft Cleared 2/4/2019 CALOSHA APPROVED
Fire Marshall Fire Life Safety Cleared 2/4/2019 PEJMAN NOORI

Contact Information

Architect Mac, Laren, Michael Bruce; Lic. No.: C29858 23705 VANOWEN # 309      WEST HILLS, CA 91307
Contractor Avcad Construction; Lic. No.: 641900-B 1042 SOUTH SHENANDOAH #101      LOS ANGELES, CA 90035

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/27/2019 Approved LESLIE TRUJILLO
Deputy Reinf. Concrete 5/15/2019 Conditional Approval LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 7/5/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 9/23/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/25/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 9/25/2019 Approved LESLIE TRUJILLO
Deputy Shotcrete 10/7/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 10/8/2019 Conditional Approval LESLIE TRUJILLO
Green Building Rough 10/10/2019 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 10/10/2019 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 10/10/2019 Conditional Approval LESLIE TRUJILLO
Reinforced Masonry Frame 10/15/2019 Partial Approval DANIEL MC AULIFFE
Deputy Shotcrete 10/18/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/24/2019 Conditional Approval LESLIE TRUJILLO
Green Building Rough 10/25/2019 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 10/25/2019 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 10/25/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 11/22/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 11/23/2019 Conditional Approval LESLIE TRUJILLO
Masonry Wall/Backfill 11/26/2019 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 12/2/2019 Conditional Approval LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 12/11/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 12/12/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 12/16/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 12/20/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 1/6/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 1/8/2020 Conditional Approval LESLIE TRUJILLO
Green Building Rough 1/9/2020 Not Ready for Inspection LESLIE TRUJILLO
Reinforced Masonry Frame 1/9/2020 Not Ready for Inspection LESLIE TRUJILLO
Verify Sprinkler Sign Off 1/9/2020 Not Ready for Inspection LESLIE TRUJILLO
Masonry Wall/Backfill 1/10/2020 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 1/13/2020 Conditional Approval LESLIE TRUJILLO
Green Building Rough 1/14/2020 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 1/14/2020 Corrections Issued LESLIE TRUJILLO
Verify Sprinkler Sign Off 1/14/2020 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 1/15/2020 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 1/27/2020 Partial Approval RAFAEL ESPINOZA
Green Building Rough 1/27/2020 Conditional Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 1/27/2020 Partial Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 2/21/2020 Not Ready for Inspection LESLIE TRUJILLO
Footing/Foundation/Slab 2/28/2020 Not Ready for Inspection RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 3/3/2020 Approved RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/5/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/9/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 3/9/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 3/12/2020 No Access for Inspection LESLIE TRUJILLO
Deputy Reinf. Masonry 3/16/2020 Conditional Approval RAFAEL ESPINOZA
Green Building Rough 3/18/2020 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 3/18/2020 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 3/18/2020 Not Ready for Inspection RAFAEL ESPINOZA
Masonry Wall/Backfill 3/19/2020 Partial Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 3/19/2020 Partial Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 4/30/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/5/2020 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 5/15/2020 Conditional Approval RAFAEL ESPINOZA
Wood Frame 5/15/2020 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 5/22/2020 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 5/26/2020 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 6/12/2020 Partial Approval RAFAEL ESPINOZA
Wood Frame 6/12/2020 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 6/15/2020 Conditional Approval RAFAEL ESPINOZA
Insulation 6/23/2020 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 6/26/2020 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 6/29/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 7/13/2020 Partial Approval RAFAEL ESPINOZA
Insulation 7/13/2020 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 7/13/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 7/16/2020 Partial Approval RAFAEL ESPINOZA
Wood Frame 7/21/2020 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 8/25/2020 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 8/28/2020 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 9/3/2020 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 9/15/2020 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 9/17/2020 Approved RAFAEL ESPINOZA
Insulation 9/29/2020 Corrections Issued RAFAEL ESPINOZA
Insulation 10/14/2020 Partial Approval RAFAEL ESPINOZA
Insulation 10/26/2020 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 10/27/2020 Partial Approval RAFAEL ESPINOZA
Wood Frame 10/28/2020 Partial Approval RAFAEL ESPINOZA
Insulation 12/18/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 1/5/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 1/5/2021 Conditional Approval RAFAEL ESPINOZA
Insulation 1/19/2021 Corrections Issued RAFAEL ESPINOZA
Insulation 1/20/2021 Conditional Approval NICK DANERI
Drywall Nailing 1/25/2021 Approved RAFAEL ESPINOZA
Special/Order Compliance 2/18/2021 Partial Inspection RAFAEL ESPINOZA
Special/Order Compliance 4/15/2021 Partial Inspection DANIEL COLLINS
Special/Order Compliance 4/21/2021 Partial Inspection RAFAEL ESPINOZA
Pre-Inspection 8/30/2021 Partial Inspection RAFAEL ESPINOZA
Pre-Inspection 3/7/2022 Partial Inspection RAFAEL ESPINOZA
Final 7/19/2022 Partial Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 7/19/2022 Approved RAFAEL ESPINOZA
Green Building Final 7/19/2022 Not Ready for Inspection RAFAEL ESPINOZA
Green Building Rough 7/19/2022 Approved RAFAEL ESPINOZA
Reinforced Concrete Frame 7/19/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 7/19/2022 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 7/19/2022 SGSOV Approved RAFAEL ESPINOZA
Smoke Detectors 7/19/2022 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 7/19/2022 Not Ready for Inspection RAFAEL ESPINOZA
Final 9/20/2022 Corrections Issued RAFAEL ESPINOZA
Green Building Final 9/20/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 9/20/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 9/20/2022 Not Ready for Inspection RAFAEL ESPINOZA
Smoke Detectors 9/20/2022 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 9/20/2022 Not Ready for Inspection RAFAEL ESPINOZA
Final 9/28/2022 Partial Inspection RAFAEL ESPINOZA
Green Building Final 10/3/2022 Approved RAFAEL ESPINOZA
Pre-Inspection 10/3/2022 Approved RAFAEL ESPINOZA
Reinforced Concrete Frame 10/3/2022 Partial Approval RAFAEL ESPINOZA
Reinforced Masonry Frame 10/3/2022 Partial Approval RAFAEL ESPINOZA
Smoke Detectors 10/3/2022 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 10/3/2022 Not Ready for Inspection RAFAEL ESPINOZA
Final 10/14/2022 Partial Inspection GREGORY POMISH
Reinforced Concrete Frame 10/14/2022 Partial Inspection GREGORY POMISH
Reinforced Masonry Frame 10/14/2022 Partial Inspection GREGORY POMISH
Smoke Detectors 10/14/2022 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 10/14/2022 Partial Inspection GREGORY POMISH
Final 10/31/2022 Partial Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 10/31/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 10/31/2022 Not Ready for Inspection RAFAEL ESPINOZA
Smoke Detectors 10/31/2022 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 10/31/2022 Not Ready for Inspection RAFAEL ESPINOZA
Pre-Inspection 11/17/2022 Approved RAFAEL ESPINOZA
Interior/Exterior Lathing 6/27/2023 No Access for Inspection RAFAEL ESPINOZA
Special/Order Compliance 10/18/2023 Partial Inspection GREGORY POMISH
Final 10/20/2023 OK to Issue CofO RAFAEL ESPINOZA
Reinforced Concrete Frame 10/20/2023 Approved RAFAEL ESPINOZA
Reinforced Masonry Frame 10/20/2023 Approved RAFAEL ESPINOZA
Smoke Detectors 10/20/2023 Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 10/20/2023 Approved RAFAEL ESPINOZA