1504 N KENTER AVE 90049

Certificate Information: 1504 N KENTER AVE 90049

Application / Permit
17047-30000-01286
Plan Check / Job No.
B17WL04168
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(n) pool structure on piles see permit # 16010-30000-06356
Permit Issued
Issued on 8/16/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/25/2017 APPLICANT
Assigned to Plan Check Engineer 7/27/2017 MANUEL GARCIA
Corrections Issued 8/4/2017 MANUEL GARCIA
Quality Review Completed 8/4/2017 STEVEN KIM
Building Plans Picked Up 8/15/2017 APPLICANT
Applicant returned to address corrections 8/28/2017 MANUEL GARCIA
Plan Check Approved 7/26/2019 MANUEL GARCIA
Issued 8/16/2019 LADBS
CofO in Progress 1/7/2026 KEVIN SARGSYAN
Permit Finaled 1/9/2026 RICHARD STEINBACH
CofO Issued 1/9/2026 RICHARD STEINBACH
Permit Finaled 1/9/2026 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/5/2018 STEVE MELGAR
Sewer availability Cleared 2/5/2018 STEVE MELGAR
Grading Pre-Inspection Cleared 8/6/2019 MANUEL GARCIA

Contact Information

Contractor Abbott R T Construction Inc; Lic. No.: 746685-B 543 COUNTRY CLUB DRIVE BOX 205      SIMI VALLEY, CA 93065

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 12/19/2019 Partial Approval TIM CHRISTENSEN
Deputy Other (see comments) 12/20/2019 Conditional Approval TIM CHRISTENSEN
Piling/Pier/Caisson 1/2/2020 Partial Approval ANDREW NAVE
Deputy Other (see comments) 1/3/2020 Conditional Approval DANNY TOLENTINO
Deputy Other (see comments) 1/6/2020 No Access for Inspection MICHAEL TEMPLE
Piling/Pier/Caisson 1/8/2020 Partial Approval TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 1/21/2020 Partial Approval TIM CHRISTENSEN
Deputy Other (see comments) 1/29/2020 Conditional Approval TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 2/6/2020 Partial Approval TIM CHRISTENSEN
Deputy Other (see comments) 2/14/2020 Conditional Approval TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 3/3/2020 Partial Approval TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 3/17/2020 Partial Approval TIM CHRISTENSEN
Piling/Pier/Caisson 4/30/2020 Conditional Approval TIM CHRISTENSEN
Deputy Other (see comments) 5/1/2020 Conditional Approval TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 5/22/2020 Partial Approval ROBERT SHELLY
Pool Piping 5/22/2020 Approved ROBERT SHELLY
Rough-Plumbing 6/3/2020 Approved TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 4/27/2021 Partial Approval JUAN VALENZUELA
Deputy Other (see comments) 5/4/2021 Conditional Approval ROBERT SHELLY
Deputy Drilled-In Anchors 6/24/2021 Conditional Approval ADAM ESCOTO
Excavation/Setback/Form/Re-Bar 7/7/2021 Partial Approval JUAN VALENZUELA
Grading Pre-Inspection 7/20/2021 Corrections Issued JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 8/18/2021 Partial Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 8/31/2021 Partial Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 10/4/2021 Not Ready for Inspection JUAN VALENZUELA
Deck 10/13/2021 Approved JUAN VALENZUELA
Grounding or Bonding 10/13/2021 Approved JUAN VALENZUELA
Gas Piping or Gas Test 11/23/2021 Partial Approval JUAN VALENZUELA
Deputy Drilled-In Anchors 4/26/2024 Conditional Approval MICHAEL PELHAM
Enclosure/Fence 4/26/2024 Approved CHRISTOPHER WILSON
Pool Equipment Noise Test 12/9/2025 Approved JAMES VORHIS
ELECTRICAL-Final 1/7/2026 Approved KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 1/7/2026 Approved KEVIN SARGSYAN
Final 1/7/2026 OK to Issue CofO KEVIN SARGSYAN
PLUMBING-Final 1/7/2026 Approved KEVIN SARGSYAN
Pre-Gunite 1/7/2026 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 1/7/2026 SGSOV Approved KEVIN SARGSYAN