7620 W WILLOW GLEN ROAD 90046
Certificate Information: 7620 W WILLOW GLEN ROAD 90046
- Application / Permit
- 17047-30000-01018
- Plan Check / Job No.
- B17WL03243
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New Swimming pool and spa per city standard plan.
- Permit Issued
- Issued on 6/14/2018
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2017 | RICARDO RAMIREZ |
| Green Plans Picked Up | 7/7/2017 | APPLICANT |
| Corrections Issued | 7/17/2017 | RICARDO RAMIREZ |
| Quality Review Completed | 7/21/2017 | STEVEN KIM |
| Building Plans Picked Up | 8/3/2017 | APPLICANT |
| Applicant returned to address corrections | 9/6/2017 | RICARDO RAMIREZ |
| Plan Check Approved | 10/13/2017 | RICARDO RAMIREZ |
| Plan Check Approved | 4/17/2018 | RICARDO RAMIREZ |
| Issued | 6/14/2018 | LADBS |
| CofO in Progress | 1/31/2023 | STUART CHAPMAN |
| Permit Finaled | 3/25/2023 | DANIEL ORRANTE |
| CofO Issued | 3/25/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/25/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/29/2017 | RAVIL MANAPOV |
| Sewer availability | Cleared | 8/29/2017 | RAVIL MANAPOV |
| Grading Pre-Inspection | Cleared | 10/13/2017 | RICARDO RAMIREZ |
Contact Information
| Contractor | Specialized Home Builders Inc; Lic. No.: 903190-B | 2355 WESTWOOD BLVD #388 LOS ANGELES, CA 90064 |
| Engineer | Azizisefat, Solayman; Lic. No.: C57840 | 19510 VENTURA BLVD STE 110 TARZANA, CA 91356 |
| Engineer | Balshem, Efim Bercovich; Lic. No.: C34313 | 1125 16TH ST UNIT 5 SANTA MONICA, CA 90403 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 2/23/2021 | Approved | RAUL BARAJAS |
| Rough-Electrical | 3/2/2021 | Partial Approval | RAUL BARAJAS |
| Pre-Gunite | 3/30/2021 | Corrections Issued | RAUL BARAJAS |
| Pre-Gunite | 5/12/2021 | Approved | RAUL BARAJAS |
| Gas Piping or Gas Test | 4/27/2022 | Approved | RAUL BARAJAS |
| Rough-Electrical | 4/27/2022 | Partial Approval | RAUL BARAJAS |
| Grounding or Bonding | 8/17/2022 | Approved | RAUL BARAJAS |
| Enclosure/Fence | 10/28/2022 | Corrections Issued | RAUL BARAJAS |
| Enclosure/Fence | 11/1/2022 | Approved | RAUL BARAJAS |
| Equipment Noise Level | 11/16/2022 | Not Ready for Inspection | JUSTIN CURTIS |
| Pool Equipment Noise Test | 11/16/2022 | Not Ready for Inspection | JUSTIN CURTIS |
| Equipment Noise Level | 11/18/2022 | No Access for Inspection | ZEYDI STEWART |
| Pool Equipment Noise Test | 11/29/2022 | Approved | ZEYDI STEWART |
| SGSOV-Seismic Gas S/O Valve | 12/7/2022 | SGSOV Not Ready | BRIAN SULLIVAN |
| Final | 12/12/2022 | Corrections Issued | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 12/23/2022 | Approved | STUART CHAPMAN |
| Final | 12/23/2022 | OK for TCO | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 12/23/2022 | SGSOV Approved | STUART CHAPMAN |
| Final | 12/29/2022 | Corrections Issued | STUART CHAPMAN |
| Final | 1/31/2023 | OK to Issue CofO | STUART CHAPMAN |