3377 N CHARLESTON WAY 90068
Certificate Information: 3377 N CHARLESTON WAY 90068
- Application / Permit
- 17047-20000-01750
- Plan Check / Job No.
- B17VN15942
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 16'-0" X8'-0" (MAX DEPTH 5'-0") POOL WITH AN 8'-0" X 8'-0" (MAX DEPTH 3'-6") SPA PER STANDARD PLAN #265.
- Permit Issued
- Issued on 1/29/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/19/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 10/19/2017 | JOHNNY WU |
| Plan Check Approved | 10/19/2017 | JOHNNY WU |
| Issued | 1/29/2018 | LADBS |
| CofO in Progress | 3/12/2025 | BRENDAN MORELLI |
| Permit Finaled | 3/13/2025 | DEROLD HAUFF |
| CofO Issued | 3/13/2025 | DEROLD HAUFF |
| Permit Finaled | 3/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhang, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 2/2/2018 | Corrections Issued | LUIS BARRALES |
| Gunite | 2/5/2018 | Not Ready for Inspection | BRIAN SULLIVAN |
| Pre-Gunite | 2/7/2018 | Approved | BRIAN SULLIVAN |
| Grounding or Bonding | 8/16/2018 | Approved | BRIAN SULLIVAN |
| Special/Order Compliance | 10/2/2018 | Corrections Issued | BRIAN SULLIVAN |
| Enclosure/Fence | 10/5/2018 | Approved | BRIAN SULLIVAN |
| Pool Equipment Noise Test | 10/23/2018 | No Access for Inspection | JUSTIN CURTIS |
| Pool Equipment Noise Test | 5/23/2023 | Approved | ZEYDI STEWART |
| Excavation/Setback/Form/Re-Bar | 9/30/2024 | Approved | BRIAN SULLIVAN |
| Final | 9/30/2024 | Corrections Issued | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 9/30/2024 | SGSOV Not Ready | BRIAN SULLIVAN |
| Final | 3/11/2025 | OK to Issue CofO | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 3/11/2025 | SGSOV Approved | BRENDAN MORELLI |