11825 W KLING ST 91607

Certificate Information: 11825 W KLING ST 91607

Application / Permit
17047-20000-00807
Plan Check / Job No.
B17VN06957
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) POOL (42'X 17') & SPA (6'-6" X 10'-4") PER ENG'R DESIGN
Permit Issued
Issued on 5/12/2020
Issuing Office
Current Status
CofO Issued on 1/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/16/2017 APPLICANT
Assigned to Plan Check Engineer 5/25/2017 NILOOFAR MEHRAIN
Corrections Issued 5/30/2017 NILOOFAR MEHRAIN
Quality Review Completed 5/30/2017 GUANG MIN TUNG
Building Plans Picked Up 5/31/2017 APPLICANT
Green Plans Picked Up 5/31/2017 APPLICANT
Applicant returned to address corrections 12/7/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 3/29/2018 NILOOFAR MEHRAIN
Plan Check Approved 4/26/2018 NILOOFAR MEHRAIN
Plan Check Approved 5/12/2020 NILOOFAR MEHRAIN
Issued 5/12/2020 APPLICANT
CofO in Progress 8/30/2023 JACK KARGODORIAN
No Progress 12/28/2023 JUAN VALENZUELA
CofO in Progress 1/4/2024 RUBEN SALAS
CofO Issued 1/4/2024 RUBEN SALAS
Permit Finaled 1/4/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/6/2017 KENNETH PHAM
Sewer availability Cleared 7/6/2017 KENNETH PHAM
Miscellaneous Cleared 3/21/2018 STEVEN WECHSLER
Specific Plan Cleared 3/21/2018 STEVEN WECHSLER
Tract Map conditions Cleared 3/21/2018 STEVEN WECHSLER
Miscellaneous Cleared 3/22/2018 STEVEN WECHSLER

Contact Information

Contractor Owner-Builder       ,
Engineer Kamkar,, Albert; Lic. No.: C38311 12340 SANTA MONICA BLVD 236      SANTA MONICA, CA 90025

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pool Equipment Noise Test 6/16/2023 Approved FELIPE PENICHE
Excavation/Setback/Form/Re-Bar 6/26/2023 Approved DAVID MATSON
Final 6/26/2023 Corrections Issued DAVID MATSON
Pre-Gunite 6/26/2023 Approved DAVID MATSON
SGSOV-Seismic Gas S/O Valve 6/26/2023 SGSOV Not Ready DAVID MATSON
Final 8/29/2023 OK to Issue CofO JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 8/29/2023 SGSOV Approved JACK KARGODORIAN