7339 W PYRAMID PL 90046

Certificate Information: 7339 W PYRAMID PL 90046

Application / Permit
17047-10000-01726
Plan Check / Job No.
B17LA18811
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 25ft X 13Ft POOL AND OPEN PATIO DECK
Permit Issued
Issued on 1/17/2018
Issuing Office
Valley
Current Status
CofO Issued on 3/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2017 APPLICANT
Assigned to Plan Check Engineer 10/19/2017 XIAOZHE ZHANG
Corrections Issued 11/3/2017 XIAOZHE ZHANG
Quality Review Completed 11/13/2017 BILL STUTSMAN
Building Plans Picked Up 11/20/2017 APPLICANT
Plan Check Approved 12/7/2017 XIAOZHE ZHANG
Issued 1/17/2018 LADBS
CofO in Progress 3/14/2023 BRIAN SULLIVAN
Permit Finaled 3/23/2023 DEROLD HAUFF
CofO Issued 3/23/2023 DEROLD HAUFF
Permit Finaled 3/23/2023 DEROLD HAUFF

Permit Application Clearance Information

Miscellaneous Cleared 11/29/2017 BRIAN CARR
Specific Plan Cleared 11/29/2017 BRIAN CARR
ZI Cleared 11/29/2017 BRIAN CARR
Eng Process Fee Ord 176,300 Cleared 12/1/2017 STEVE MELGAR
Low Impact Development Cleared 12/1/2017 SAM NAVID
Sewer availability Cleared 12/1/2017 STEVE MELGAR
Grading Pre-Inspection Cleared 12/7/2017 XIAOZHE ZHANG

Contact Information

Architect Neubert, Aaron Douglas; Lic. No.: C29005 3052 BERKELEY CIRCLE      LOS ANGELES, CA 90026
Contractor Bulson & Company Inc.; Lic. No.: 980611-B 14044 VENTURA BLVD., #308      SHERMAN OAKS, CA 91423
Contractor Owner-Builder       ,
Engineer Phillips, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026
Engineer Shirley, Peter Franklin; Lic. No.: C75050 4429 DAWES AVE      CULVER CITY, CA 90230

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/16/2018 No Access for Inspection BRIAN SULLIVAN
Pre-Inspection 2/20/2018 Approved BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 2/26/2018 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 3/5/2018 Partial Approval BRIAN SULLIVAN
Pre-Gunite 5/4/2018 Approved BRIAN SULLIVAN
Gas Piping or Gas Test 11/1/2019 Approved BRIAN SULLIVAN
Enclosure/Fence 11/29/2022 Corrections Issued BRIAN SULLIVAN
Special/Order Compliance 2/2/2023 Approved BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 2/24/2023 Approved BRIAN SULLIVAN
Final 2/24/2023 Corrections Issued BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 2/24/2023 SGSOV Approved BRIAN SULLIVAN
Final 3/14/2023 OK to Issue CofO BRIAN SULLIVAN