3427 N COLVILLE PL 91436
Certificate Information: 3427 N COLVILLE PL 91436
- Application / Permit
- 17047-10000-01654
- Plan Check / Job No.
- B17LA17997
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW POOL PER STANDARD PLAN 268
- Permit Issued
- Issued on 10/13/2017
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/3/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2017 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 10/12/2017 | KEVIN STEWART |
| Plan Check Approved | 10/13/2017 | YOUNG KIM |
| Issued | 10/13/2017 | LADBS |
| CofO in Progress | 2/10/2023 | VINCENT HANLEY |
| CofO Issued | 2/14/2023 | MICHAEL SMITH |
| Permit Finaled | 2/14/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/10/2017 | NAZILA NOORIFAR |
| Sewer availability | Cleared | 10/10/2017 | NAZILA NOORIFAR |
| Specific Plan | Cleared | 10/10/2017 | RICK TORRES |
| Specific Plan | Cleared | 10/10/2017 | RICK TORRES |
| Grading Pre-Inspection | Cleared | 10/12/2017 | VLADIMIR ARUTYUNYAN |
Contact Information
| Contractor | Benico Construction Inc; Lic. No.: 765501-B | 245 SOUTH LA PEER DRIVE BEVERLY HILLS, CA 90211 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/21/2019 | Approved | RONALD COWAN |
| Rough-Electrical | 11/21/2019 | Approved | RONALD COWAN |
| Rough-Plumbing | 11/21/2019 | Approved | RONALD COWAN |
| Final | 9/2/2022 | Corrections Issued | SEAN HAUPT |
| Pool Equipment Noise Test | 9/2/2022 | Approved | FELIPE PENICHE |
| SGSOV-Seismic Gas S/O Valve | 9/2/2022 | SGSOV Not Ready | SEAN HAUPT |
| ELECTRICAL-Final | 2/7/2023 | Approved | VINCENT HANLEY |
| Final | 2/7/2023 | Not Ready for Inspection | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 2/7/2023 | SGSOV Approved | VINCENT HANLEY |
| Final | 2/10/2023 | OK to Issue CofO | VINCENT HANLEY |