235 N HOOVER ST 90004
Certificate Information: 235 N HOOVER ST 90004
- Application / Permit
- 17030-10001-06339
- Plan Check / Job No.
- B21LA03829
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (70) Grading - Hillside
- Work Description
- Supplemental to 17030-10000-06339. Includes changes to Grading plan to match the reduced height of shoring at the East side of the site ( reduce amount of grading work) *REQUESTING "UNDER-CONSTRUCTION EXPEDITE" 2 OF 2
- Permit Issued
- Issued on 5/27/2021
- Issuing Office
- Current Status
- Permit Finaled on 7/9/2024
Permit Application Status History
| Submitted | 3/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2021 | SAM CHANG |
| Corrections Issued | 3/15/2021 | SAM CHANG |
| Quality Review Completed | 3/16/2021 | EUGENE BARBEAU |
| Building Plans Picked Up | 4/6/2021 | APPLICANT |
| Plan Check Approved | 5/12/2021 | SAM CHANG |
| Issued | 5/27/2021 | APPLICANT |
| Permit Finaled | 7/8/2024 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Penick T B & Sons Inc; Lic. No.: 185381-A | 15435 INNOVATION DR STE 200 SAN DIEGO, CA 92128 |
| Engineer | Mensen,, Jodi Lindsey; Lic. No.: C79693 | 565 W HOWARD ST PASADENA, CA 91103 |
| Engineer | Vandorpe, Thomas Daniel; Lic. No.: S4611 | 2200 W ORANGEWOOD AVE #150 ORANGE, CA 92868 |
Inspector Information
| RAMAZANALI ALMASI, (213) 482-0398 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Bottom/Toe | 10/11/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Fill/Backfill | 10/11/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Rough | 10/11/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Irrigation/Landscape | 11/6/2023 | Partial Inspection | JONATHAN HOM |
| Rough | 11/6/2023 | Partial Inspection | JONATHAN HOM |
| Irrigation/Landscape | 11/9/2023 | Partial Approval | ROBERT HUGHES |
| Fill/Backfill | 11/15/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Drainage Devices/Catch Basin | 11/20/2023 | Partial Inspection | RUSSELL BONVOULOIR |
| Fill/Backfill | 11/20/2023 | Partial Inspection | RUSSELL BONVOULOIR |
| Bottom/Toe | 7/8/2024 | Approved | RUSSELL BONVOULOIR |
| Final | 7/8/2024 | Permit Finaled | RUSSELL BONVOULOIR |
| Rough | 7/8/2024 | Approved | RUSSELL BONVOULOIR |