330-332 N PATTON ST 90026
Certificate Information: 330-332 N PATTON ST 90026
- Application / Permit
- 17030-10000-08544
- Plan Check / Job No.
- B17LA23079
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (70) Grading - Hillside
- Work Description
- GRADING (5,900 CY) BF 190118 APPROVED FOR AN EXPORT OF 7,350 CUBIC YARDS
- Permit Issued
- Issued on 3/12/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 11/1/2022
Permit Application Status History
| Submitted | 12/18/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 12/28/2017 | LARRY LEE |
| Green Plans Picked Up | 1/3/2018 | APPLICANT |
| Corrections Issued | 1/8/2018 | LARRY LEE |
| Quality Review Completed | 1/9/2018 | SIAVOSH POURSABAHIAN |
| Building Plans Picked Up | 1/16/2018 | APPLICANT |
| Applicant returned to address corrections | 1/31/2018 | LARRY LEE |
| Applicant returned to address corrections | 2/13/2018 | LARRY LEE |
| Applicant returned to address corrections | 2/28/2018 | LARRY LEE |
| Applicant returned to address corrections | 4/10/2018 | LARRY LEE |
| Applicant returned to address corrections | 5/8/2018 | LARRY LEE |
| Applicant returned to address corrections | 5/29/2018 | LARRY LEE |
| Applicant returned to address corrections | 8/23/2019 | LARRY LEE |
| Applicant returned to address corrections | 9/4/2019 | LARRY LEE |
| Applicant returned to address corrections | 9/16/2019 | LARRY LEE |
| Plan Check Approved | 3/11/2020 | LARRY LEE |
| Issued | 3/12/2020 | LADBS |
| Permit Finaled | 10/31/2022 | MATTHEW JENKINS |
Permit Application Clearance Information
| Work Adjacent to Public Way | Cleared | 9/11/2019 | ROSA SILVA |
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2020 | CELINA MORENO |
| Haul Route | Cleared | 1/29/2020 | VERONICA LOPEZ |
Contact Information
| No Data Available. |
Inspector Information
| RAMAZANALI ALMASI, (213) 482-0398 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 3/16/2020 | Corrections Issued | ROBERT HUGHES |
| Initial Grading | 3/18/2020 | Approved | ALEXANDER HELFER |
| Deputy Grading | 5/21/2020 | Approved | ROBERT HUGHES |
| Deputy Grading | 5/26/2020 | Approved | VASIL MIHALEV |
| Deputy Grading | 5/26/2020 | Partial Approval | ROBERT HUGHES |
| Deputy Grading | 5/27/2020 | Approved | VASIL MIHALEV |
| Deputy Grading | 5/28/2020 | Partial Approval | ROBERT HUGHES |
| Special/Order Compliance | 5/28/2020 | Not Ready for Inspection | ROBERT HUGHES |
| Deputy Grading | 5/29/2020 | Approved | ROBERT HUGHES |
| Deputy Grading | 6/11/2020 | Approved | ROBERT HUGHES |
| Deputy Grading | 6/12/2020 | Approved | ROBERT HUGHES |
| Deputy Grading | 6/15/2020 | Approved | ROBERT HUGHES |
| Deputy Grading | 6/16/2020 | Approved | ROBERT HUGHES |
| Bottom/Toe | 6/30/2020 | Partial Approval | ALEXANDER HELFER |
| Sub-Drain | 6/30/2020 | Corrections Issued | ALEXANDER HELFER |
| Deputy Grading | 7/7/2020 | Approved | ROBERT HUGHES |
| Bottom/Toe | 7/9/2020 | Not Ready for Inspection | ALEXANDER HELFER |
| Sub-Drain | 7/16/2020 | Partial Approval | ROBERT HUGHES |
| Sub-Drain | 7/21/2020 | Approved | ROBERT HUGHES |
| Bottom/Toe | 8/2/2022 | Not Ready for Inspection | MATTHEW JENKINS |
| Final | 8/2/2022 | Not Ready for Inspection | MATTHEW JENKINS |
| Rough | 8/2/2022 | Not Ready for Inspection | MATTHEW JENKINS |
| Approved Compaction Report | 10/27/2022 | Approved | ROBERT HUGHES |
| Bottom/Toe | 10/31/2022 | Approved | MATTHEW JENKINS |
| Final | 10/31/2022 | Permit Finaled | MATTHEW JENKINS |
| Rough | 10/31/2022 | Approved | MATTHEW JENKINS |