235 N HOOVER ST 90004

Certificate Information: 235 N HOOVER ST 90004

Application / Permit
17030-10000-06339
Plan Check / Job No.
B17LA14338
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(70) Grading - Hillside
Work Description
grading for 221 unit apartment with two level of below grade garage. approved bond # 628966
Permit Issued
Issued on 3/18/2020
Issuing Office
Metro
Current Status
Permit Finaled on 9/9/2024

Permit Application Status History

Submitted 8/18/2017 APPLICANT
Assigned to Plan Check Engineer 8/24/2017 SAM CHANG
Green Plans Picked Up 8/30/2017 APPLICANT
Corrections Issued 9/15/2017 SHUNYU ZHANG
Quality Review Completed 9/28/2017 MINYE PAK
Building Plans Picked Up 10/2/2017 APPLICANT
Disabled Access Plans Picked Up 10/27/2017 APPLICANT
Applicant returned to address corrections 12/7/2017 SHUNYU ZHANG
Applicant returned to address corrections 3/15/2018 SHUNYU ZHANG
Applicant returned to address corrections 4/5/2018 SAM CHANG
Applicant returned to address corrections 4/19/2018 SAM CHANG
Applicant returned to address corrections 5/2/2018 SAM CHANG
Applicant returned to address corrections 6/1/2018 SAM CHANG
Applicant returned to address corrections 6/25/2018 SAM CHANG
Applicant returned to address corrections 6/27/2018 SAM CHANG
Applicant returned to address corrections 7/20/2018 SAM CHANG
Applicant returned to address corrections 9/6/2018 SAM CHANG
Applicant returned to address corrections 8/1/2019 SAM CHANG
Plan Check Approved 10/28/2019 SAM CHANG
Issued 3/18/2020 LADBS
Permit Finaled 9/9/2024 RUSSELL BONVOULOIR

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/4/2018 PATRICK MISCHLICH
Eng Process Fee Ord 176,300 Cleared 7/24/2019 ELENA LOPEZ
Miscellaneous Cleared 8/26/2019 SOPHIE GABEL-SCHEINBAU
Miscellaneous Cleared 8/26/2019 SOPHIE GABEL-SCHEINBAU
Specific Plan Cleared 8/26/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 8/26/2019 SOPHIE GABEL-SCHEINBAU
Excavation more than 5-ft deep Cleared 8/29/2019 CALOSHA APPROVED
GPI Written Notices Cleared 8/29/2019 SHUNYU ZHANG
Work Adjacent to Public Way Cleared 10/9/2019 CHIU TAM

Contact Information

Contractor Penick T B & Sons Inc; Lic. No.: 185381-A 15435 INNOVATION DR STE 200      SAN DIEGO, CA 92128
Engineer Mensen,, Jodi Lindsey; Lic. No.: C79693 565 W HOWARD ST      PASADENA, CA 91103
Engineer Vandorpe, Thomas Daniel; Lic. No.: S4611 2200 W ORANGEWOOD AVE #150      ORANGE, CA 92868

Inspector Information

RAMAZANALI ALMASI, (213) 482-0398 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 4/6/2020 Not Ready for Inspection VASIL MIHALEV
Initial Grading 4/7/2020 Corrections Issued ALEXANDER HELFER
Initial Grading 4/10/2020 Approved ALEXANDER HELFER
Initial Grading 2/26/2021 Partial Approval ROBERT HUGHES
Initial Grading 5/17/2021 Partial Approval ROBERT HUGHES
Special/Order Compliance 5/20/2021 Corrections Issued ALEXANDER HELFER
Initial Grading 7/13/2021 Approved ALEXANDER HELFER
Deputy Grading 7/22/2021 Approved ROBERT HUGHES
Deputy Grading 7/23/2021 Approved ROBERT HUGHES
Deputy Grading 7/27/2021 Approved ROBERT HUGHES
Deputy Grading 7/28/2021 Approved ROBERT HUGHES
Deputy Grading 7/29/2021 Approved ROBERT HUGHES
Deputy Grading 8/2/2021 Approved ROBERT HUGHES
Deputy Grading 8/3/2021 Approved ROBERT HUGHES
Deputy Grading 8/4/2021 Approved ROBERT HUGHES
Deputy Grading 8/5/2021 Approved ROBERT HUGHES
Deputy Grading 8/6/2021 Approved ROBERT HUGHES
Deputy Grading 8/9/2021 Approved ROBERT HUGHES
Deputy Grading 8/10/2021 Approved ROBERT HUGHES
Deputy Grading 8/11/2021 Approved ROBERT HUGHES
Deputy Grading 8/12/2021 Approved ROBERT HUGHES
Deputy Grading 8/13/2021 Approved ROBERT HUGHES
Deputy Grading 8/17/2021 Approved ROBERT HUGHES
Deputy Grading 8/18/2021 Approved ROBERT HUGHES
Deputy Grading 8/19/2021 Approved ROBERT HUGHES
Deputy Grading 8/20/2021 Approved ROBERT HUGHES
Deputy Grading 8/23/2021 Approved ROBERT HUGHES
Initial Grading 8/23/2021 Approved ROBERT HUGHES
Deputy Grading 8/24/2021 Approved ROBERT HUGHES
Deputy Grading 8/25/2021 Approved ROBERT HUGHES
Deputy Grading 8/26/2021 Approved ROBERT HUGHES
Deputy Grading 8/27/2021 Approved ROBERT HUGHES
Deputy Grading 8/30/2021 Approved ROBERT HUGHES
Deputy Grading 8/31/2021 Approved ROBERT HUGHES
Deputy Grading 9/1/2021 Approved ROBERT HUGHES
Deputy Grading 9/2/2021 Approved ROBERT HUGHES
Deputy Grading 9/3/2021 Approved ALEXANDER HELFER
Deputy Grading 9/7/2021 Approved ROBERT HUGHES
Deputy Grading 9/8/2021 Approved ROBERT HUGHES
Deputy Grading 9/9/2021 Approved ROBERT HUGHES
Deputy Grading 9/10/2021 Approved ROBERT HUGHES
Deputy Grading 9/13/2021 Approved ROBERT HUGHES
Deputy Grading 9/15/2021 Approved ROBERT HUGHES
Deputy Grading 9/16/2021 Approved ROBERT HUGHES
Deputy Grading 9/17/2021 Approved ROBERT HUGHES
Deputy Grading 9/20/2021 Approved ROBERT HUGHES
Deputy Grading 9/21/2021 Approved ROBERT HUGHES
Deputy Grading 9/22/2021 Approved ROBERT HUGHES
Deputy Grading 9/23/2021 Approved ROBERT HUGHES
Deputy Grading 9/24/2021 Approved ROBERT HUGHES
Deputy Grading 9/27/2021 Approved ROBERT HUGHES
Deputy Grading 9/28/2021 Approved ROBERT HUGHES
Deputy Grading 9/29/2021 Approved ROBERT HUGHES
Deputy Grading 9/30/2021 Approved ROBERT HUGHES
Deputy Grading 10/1/2021 Approved ROBERT HUGHES
Deputy Grading 10/4/2021 Approved ROBERT HUGHES
Deputy Grading 10/5/2021 Approved ROBERT HUGHES
Deputy Grading 10/6/2021 Approved ROBERT HUGHES
Deputy Grading 10/7/2021 Approved ROBERT HUGHES
Deputy Grading 10/8/2021 Approved ROBERT HUGHES
Deputy Grading 10/19/2021 Conditional Approval LANNY MERRICK
Deputy Grading 10/20/2021 Conditional Approval LANNY MERRICK
Deputy Grading 10/21/2021 Approved ALEXANDER HELFER
Deputy Grading 10/22/2021 Conditional Approval LANNY MERRICK
Deputy Grading 10/26/2021 Approved ROBERT HUGHES
Deputy Grading 10/27/2021 Conditional Approval LANNY MERRICK
Deputy Grading 10/28/2021 Approved ALEXANDER HELFER
Deputy Grading 10/29/2021 Approved ROBERT HUGHES
Deputy Grading 11/1/2021 Approved ROBERT HUGHES
Deputy Grading 11/2/2021 Approved ROBERT HUGHES
Deputy Grading 11/3/2021 Approved ROBERT HUGHES
Deputy Grading 11/4/2021 Approved ROBERT HUGHES
Deputy Grading 11/4/2021 Conditional Approval LANNY MERRICK
Sub-Drain 11/4/2021 Approved ALEXANDER HELFER
Deputy Grading 11/5/2021 Approved ROBERT HUGHES
Sub-Drain 11/5/2021 Not Ready for Inspection ROBERT HUGHES
Deputy Grading 11/8/2021 Approved PATRICK MISCHLICH
Sub-Drain 11/8/2021 Partial Approval LANNY MERRICK
Deputy Grading 11/9/2021 Approved ALEXANDER HELFER
Deputy Grading 11/10/2021 Approved VASIL MIHALEV
Deputy Grading 11/12/2021 Approved VASIL MIHALEV
Sub-Drain 11/12/2021 Approved ALEXANDER HELFER
Drainage Devices/Catch Basin 12/2/2021 Not Ready for Inspection ROBERT HUGHES
Sub-Drain 12/2/2021 Partial Approval ROBERT HUGHES
Drainage Devices/Catch Basin 12/3/2021 Partial Approval LANNY MERRICK
Excavation 12/6/2021 Not Ready for Inspection ROBERT HUGHES
Initial Grading 12/6/2021 Approved ROBERT HUGHES
Sub-Drain 12/6/2021 Not Ready for Inspection ROBERT HUGHES
Bottom/Toe 12/7/2021 Partial Approval ROBERT HUGHES
Sub-Drain 12/8/2021 Partial Approval ROBERT HUGHES
Drainage Devices/Catch Basin 12/10/2021 Partial Approval LANNY MERRICK
Fill/Backfill 12/10/2021 Partial Approval LANNY MERRICK
Fill/Backfill 12/13/2021 Partial Inspection ALEXANDER HELFER
Fill/Backfill 12/14/2021 Not Ready for Inspection LANNY MERRICK
Rough 1/13/2022 Partial Approval LANNY MERRICK
Sub-Drain 1/14/2022 Partial Approval ROBERT HUGHES
Deputy Grading 1/21/2022 Approved ROBERT HUGHES
Bottom/Toe 1/27/2022 Partial Approval ROBERT HUGHES
Fill/Backfill 1/31/2022 Partial Approval LANNY MERRICK
Fill/Backfill 2/1/2022 Partial Approval LANNY MERRICK
Deputy Grading 2/2/2022 Conditional Approval LANNY MERRICK
Deputy Grading 2/3/2022 Approved ROBERT HUGHES
Deputy Grading 2/4/2022 Conditional Approval LANNY MERRICK
Fill/Backfill 2/4/2022 Partial Approval LANNY MERRICK
Bottom/Toe 2/9/2022 Partial Approval LANNY MERRICK
Fill/Backfill 2/9/2022 Not Ready for Inspection LANNY MERRICK
Deputy Grading 2/11/2022 Approved ROBERT HUGHES
Sub-Drain 2/23/2022 Approved ALEXANDER HELFER
Sub-Drain 3/4/2022 Partial Approval ROBERT HUGHES
Deputy Grading 5/17/2022 Approved ROBERT HUGHES
Deputy Grading 6/1/2022 Approved ROBERT HUGHES
Deputy Grading 6/3/2022 Approved KIRK LINKLATER
Deputy Grading 6/6/2022 Approved MICHAEL TEMPLE
Deputy Grading 6/21/2022 Approved ROBERT HUGHES
Deputy Grading 6/22/2022 Approved ROBERT HUGHES
Drainage Devices/Catch Basin 8/2/2022 Partial Inspection MATTHEW JENKINS
Fill/Backfill 8/2/2022 Partial Inspection MATTHEW JENKINS
Drainage Devices/Catch Basin 8/3/2022 Partial Approval MATTHEW JENKINS
Fill/Backfill 8/3/2022 Partial Inspection MATTHEW JENKINS
Fill/Backfill 5/8/2023 Partial Approval LANNY MERRICK
Irrigation/Landscape 5/8/2023 Not Ready for Inspection LANNY MERRICK
Sub-Drain 5/8/2023 Partial Approval LANNY MERRICK
Fill/Backfill 9/19/2023 Partial Inspection JONATHAN HOM
Fill/Backfill 9/22/2023 Partial Approval RUSSELL BONVOULOIR
Bottom/Toe 10/24/2023 Partial Approval ROBERT HUGHES
Fill/Backfill 10/24/2023 Partial Approval ROBERT HUGHES
Rough 10/24/2023 Not Ready for Inspection ROBERT HUGHES
Drainage Devices/Catch Basin 11/17/2023 Not Ready for Inspection ROBERT HUGHES
Fill/Backfill 11/17/2023 Not Ready for Inspection ROBERT HUGHES
Rough 12/14/2023 Partial Inspection RUSSELL BONVOULOIR
Rough 1/19/2024 Partial Inspection RUSSELL BONVOULOIR
Bottom/Toe 7/2/2024 Corrections Issued ALEXANDER HELFER
Final 7/2/2024 Not Ready for Inspection ALEXANDER HELFER
Rough 7/2/2024 Not Ready for Inspection ALEXANDER HELFER
Bottom/Toe 7/8/2024 Approved RUSSELL BONVOULOIR
Final 7/8/2024 Corrections Issued RUSSELL BONVOULOIR
Rough 7/8/2024 Approved RUSSELL BONVOULOIR
Approved Compaction Report 7/30/2024 Not Ready for Inspection LANNY MERRICK
Approved Compaction Report 8/30/2024 Approved LANNY MERRICK
Final 9/9/2024 Permit Finaled RUSSELL BONVOULOIR