609 N DILLON ST 90026
Certificate Information: 609 N DILLON ST 90026
- Application / Permit
- 17030-10000-04895
- Plan Check / Job No.
- B15LA16153
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (70) Grading - Hillside
- Work Description
- SITE PREPARATION & EXCAVATION & BACKFIIL FOR NEW 2 STORY TYPE V-A , 52 UNITS MIXED USE APARTMENT BUILDING ( 5 Extremely Low Income unit per 12.22.A.31, TOC Tier 1) OVER GROUND LEVEL TYPE I-A RETAIL OVER TWO LEVELS OF TYPE I-A SUBTERRANEAN PARKING ( TOTAL 3 STORY BUILDING). BF 200020 APPROVED FOR AN EXPORT OF 22,025 CUBIC YARDS
- Permit Issued
- Issued on 7/20/2020
- Issuing Office
- Current Status
- Permit Finaled on 5/16/2022
Permit Application Status History
| Submitted | 12/8/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2015 | GARO TELMI |
| Corrections Issued | 12/22/2015 | GARO TELMI |
| Quality Review Completed | 12/31/2015 | BILL STUTSMAN |
| Building Plans Picked Up | 1/5/2016 | APPLICANT |
| Applicant returned to address corrections | 6/28/2017 | GARO TELMI |
| Applicant returned to address corrections | 7/11/2017 | GARO TELMI |
| Applicant returned to address corrections | 7/20/2017 | GARO TELMI |
| Applicant returned to address corrections | 8/17/2017 | GARO TELMI |
| Applicant returned to address corrections | 1/5/2018 | GARO TELMI |
| Applicant returned to address corrections | 7/25/2018 | GARO TELMI |
| Applicant returned to address corrections | 9/14/2018 | GARO TELMI |
| Applicant returned to address corrections | 11/15/2018 | GARO TELMI |
| Applicant returned to address corrections | 5/7/2019 | GARO TELMI |
| Applicant returned to address corrections | 2/19/2020 | GARO TELMI |
| Applicant returned to address corrections | 3/5/2020 | GARO TELMI |
| Applicant returned to address corrections | 5/27/2020 | GARO TELMI |
| Applicant returned to address corrections | 6/15/2020 | GARO TELMI |
| Plan Check Approved | 7/15/2020 | GARO TELMI |
| Issued | 7/20/2020 | APPLICANT |
| Permit Finaled | 5/16/2022 | ROBERT HUGHES |
Permit Application Clearance Information
| Drainage to Storm Drain | Cleared | 8/30/2018 | SOPHEA EK |
| Encroachment in public way | Cleared | 8/31/2018 | ADRIAN SANCHEZ |
| Construction near power lines | Cleared | 9/19/2018 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2018 | ADRIAN SANCHEZ |
| Miscellaneous | Cleared | 9/24/2018 | YOVANA PEREZ |
| Excavation more than 5-ft deep | Cleared | 11/8/2018 | CALOSHA APPROVED |
| Work Adjacent to Public Way | Cleared | 1/10/2019 | TERRY PHAN |
| Roof/Waste drainage to street | Cleared | 1/28/2019 | KAREN LE |
| Haul Route | Cleared | 7/14/2020 | VERONICA LOPEZ |
Contact Information
| Architect | O'Herlihy,, Lorcan Patrick; Lic. No.: C24245 | 4106 W JEFFERSON BLVD LOS ANGELES, CA 90016 |
| Contractor | Owner-Builder | , |
| Engineer | Anhorn,, Jerald Edward; Lic. No.: L7159 | 123 S LA SALLE REDLANDS, CA 92374 |
| Engineer | Berliner,, Neal David; Lic. No.: GE2576 | 4913 MONUMENT ST SIMI VALLEY, CA 93063 |
| Engineer | Funk,, David Lyle; Lic. No.: S5421 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
| Engineer | Knur,, Reinard Thomas; Lic. No.: GE2755 | 1435 MONCADO DR GLENDALE, CA 91207 |
| Engineer | Ortiz,, David Arturo; Lic. No.: C56818 | 7248 BECKFORD AVE RESEDA, CA 91335 |
| Engineer | Tofani,, Glenn David; Lic. No.: C44229 | 77 BUNSEN IRVINE, CA 92618 |
| Engineer | Young,, Don Yuk-Man; Lic. No.: C35713 | 149 PASADENA AVE STE B SOUTH PASADENA, CA 91030 |
Inspector Information
| RAMAZANALI ALMASI, (213) 482-0398 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 7/22/2020 | Approved | ROBERT HUGHES |
| Deputy Grading | 9/15/2020 | Approved | ROBERT HUGHES |
| Bottom/Toe | 10/22/2020 | Partial Approval | ALEXANDER HELFER |
| Excavation | 10/22/2020 | Partial Approval | ALEXANDER HELFER |
| Initial Grading | 10/22/2020 | Approved | ALEXANDER HELFER |
| Approved Compaction Report | 12/29/2020 | Approved | ALEXANDER HELFER |
| Bottom/Toe | 5/12/2021 | Partial Approval | ROBERT HUGHES |
| Excavation | 5/12/2021 | Partial Approval | ROBERT HUGHES |
| Drainage Devices/Catch Basin | 3/18/2022 | Approved | ALEXANDER HELFER |
| Drainage Devices/Catch Basin | 3/30/2022 | Partial Approval | ROBERT HUGHES |
| Irrigation/Landscape | 3/30/2022 | Not Ready for Inspection | ROBERT HUGHES |
| Special/Order Compliance | 3/30/2022 | Not Ready for Inspection | ROBERT HUGHES |
| Drainage Devices/Catch Basin | 4/13/2022 | Partial Approval | ROBERT HUGHES |
| Approved Compaction Report | 5/12/2022 | Approved | ALEXANDER HELFER |
| Bottom/Toe | 5/16/2022 | Approved | ROBERT HUGHES |
| Final | 5/16/2022 | Permit Finaled | ROBERT HUGHES |
| Rough | 5/16/2022 | Approved | ROBERT HUGHES |