11761 N FENTON AVE 91342
Certificate Information: 11761 N FENTON AVE 91342
- Application / Permit
- 17030-10000-04535
- Plan Check / Job No.
- G17LA00114
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- PROPOSED SITE GRADING TO CREATE TWO SINGLE FAMILY RESIDENCES AND THIRTEEN CONDOMINIUM UNITS ON A FLAT UNDEVELOPED LOT PER APPROVED TENTATIVE TRACT NO. 60855. CUT = 3,749 CU. YDS., FILL = 4,580 CU. YDS., R&R = 18,870 CU. YDS., IMPORT = 831 CU. YDS.
- Permit Issued
- Issued on 1/11/2021
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 3/15/2024
Permit Application Status History
| Submitted | 6/29/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2017 | FREDERICK WONG |
| Corrections Issued | 7/12/2017 | FREDERICK WONG |
| Applicant returned to address corrections | 8/21/2019 | DAN RYAN EVANGELISTA |
| Plan Check Approved | 1/11/2021 | DAN RYAN EVANGELISTA |
| Issued | 1/11/2021 | APPLICANT |
| Permit Finaled | 3/15/2024 | GERMAN RODRIGUEZ MENDOZA |
Permit Application Clearance Information
| Grading in hillside | Cleared | 7/20/2017 | DANIEL SKOLNICK |
| Tract Map conditions | Cleared | 7/20/2017 | DANIEL SKOLNICK |
| ZI | Cleared | 7/20/2017 | DANIEL SKOLNICK |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2017 | LEE GUILBEAUX |
| Stormwater Pollution Mitigatn | Cleared | 6/4/2018 | SAM NAVID |
| Permit | Cleared | 8/20/2019 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 8/20/2019 | GABRIEL ROBLES |
| Excavation more than 5-ft deep | Cleared | 8/21/2019 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 8/21/2019 | FREDERICK WONG |
| Hold | Cleared | 3/23/2021 | JASON SHEETS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Miller,, Karen Lynn; Lic. No.: GE2257 | 6634 VALJEAN AVE VAN NUYS, CA 91406 |
| Engineer | Podegracz, Joseph David; Lic. No.: C78425 | PO BOX 1083 FRAZIER PARK, CA 93225 |
| Geologist | Ruberti,, Rudolph F; Lic. No.: EG1708 | 6634 VALJEAN AVE VAN NUYS, CA 91406 |
Inspector Information
| BRIAN MILLER, (818) 374-4359 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 5/12/2021 | Approved | ALEXANDER ANDREWS |
| Deputy Grading | 5/13/2021 | Approved | ALEXANDER ANDREWS |
| Bottom/Toe | 5/14/2021 | Partial Approval | ALEXANDER HELFER |
| Deputy Grading | 5/14/2021 | Approved | ALEXANDER HELFER |
| SWPPP-Const. Storm Water | 5/14/2021 | Completed | ALEXANDER HELFER |
| Deputy Grading | 5/17/2021 | Approved | BRIAN MILLER |
| Deputy Grading | 5/18/2021 | Approved | KIRK LINKLATER |
| Deputy Grading | 5/19/2021 | Approved | KIRK LINKLATER |
| Deputy Grading | 5/20/2021 | Partial Approval | MATTHEW JENKINS |
| Deputy Grading | 5/21/2021 | Approved | KIRK LINKLATER |
| Deputy Grading | 5/26/2021 | Approved | BRIAN MILLER |
| Deputy Grading | 5/27/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 5/28/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 6/2/2021 | Approved | KIRK LINKLATER |
| Deputy Grading | 6/3/2021 | Partial Approval | MATTHEW JENKINS |
| Deputy Grading | 6/4/2021 | Approved | KIRK LINKLATER |
| Deputy Grading | 6/8/2021 | Approved | KIRK LINKLATER |
| Deputy Grading | 6/9/2021 | Approved | KIRK LINKLATER |
| Deputy Grading | 6/10/2021 | Approved | KIRK LINKLATER |
| Deputy Grading | 6/11/2021 | Approved | KIRK LINKLATER |
| Deputy Grading | 8/17/2021 | Approved | BRIAN MILLER |
| Deputy Grading | 8/18/2021 | No Access for Inspection | TIMOTHY POWELL |
| Deputy Grading | 8/19/2021 | Approved | BRIAN MILLER |
| Deputy Grading | 8/20/2021 | Approved | BRIAN MILLER |
| Deputy Grading | 8/23/2021 | Approved | BRIAN MILLER |
| Deputy Grading | 9/3/2021 | Approved | BRIAN MILLER |
| Bottom/Toe | 9/7/2021 | Not Ready for Inspection | TIMOTHY POWELL |
| Deputy Grading | 9/7/2021 | Approved | TIMOTHY POWELL |
| Excavation | 9/7/2021 | Corrections Issued | TIMOTHY POWELL |
| Initial Grading | 9/7/2021 | Not Ready for Inspection | TIMOTHY POWELL |
| SWPPP-Const. Storm Water | 9/7/2021 | Not Required | TIMOTHY POWELL |
| Initial Grading | 9/8/2021 | Approved | TIMOTHY POWELL |
| Deputy Grading | 9/9/2021 | Approved | TIMOTHY POWELL |
| Excavation | 9/9/2021 | Partial Inspection | TIMOTHY POWELL |
| Bottom/Toe | 9/10/2021 | Partial Inspection | TIMOTHY POWELL |
| Bottom/Toe | 9/13/2021 | Corrections Issued | BRIAN MILLER |
| Deputy Grading | 9/13/2021 | Approved | BRIAN MILLER |
| SWPPP-Const. Storm Water | 9/13/2021 | Completed | BRIAN MILLER |
| Deputy Grading | 9/14/2021 | Approved | BRIAN MILLER |
| Bottom/Toe | 9/15/2021 | Partial Approval | BRIAN MILLER |
| Deputy Grading | 9/15/2021 | Approved | BRIAN MILLER |
| SWPPP-Const. Storm Water | 9/15/2021 | Completed | BRIAN MILLER |
| Deputy Grading | 9/16/2021 | Approved | BRIAN MILLER |
| Deputy Grading | 9/17/2021 | Approved | BRIAN MILLER |
| Deputy Grading | 9/20/2021 | Approved | BRIAN MILLER |
| Excavation | 9/20/2021 | Partial Approval | BRIAN MILLER |
| Bottom/Toe | 9/21/2021 | Partial Approval | BRIAN MILLER |
| Deputy Grading | 9/21/2021 | Approved | BRIAN MILLER |
| SWPPP-Const. Storm Water | 9/21/2021 | Not Required | BRIAN MILLER |
| Deputy Grading | 9/22/2021 | Approved | BRIAN MILLER |
| Bottom/Toe | 9/23/2021 | Partial Approval | BRIAN MILLER |
| Deputy Grading | 9/23/2021 | Approved | BRIAN MILLER |
| SWPPP-Const. Storm Water | 9/23/2021 | Completed | BRIAN MILLER |
| Deputy Grading | 9/24/2021 | Approved | BRIAN MILLER |
| Deputy Grading | 9/27/2021 | Approved | BRIAN MILLER |
| Special/Order Compliance | 10/1/2021 | Approved | BRIAN MILLER |
| Bottom/Toe | 10/4/2021 | Partial Approval | BRIAN MILLER |
| Deputy Grading | 10/4/2021 | Approved | BRIAN MILLER |
| SWPPP-Const. Storm Water | 10/4/2021 | Completed | BRIAN MILLER |
| Deputy Grading | 10/5/2021 | Approved | BRIAN MILLER |
| Deputy Grading | 10/6/2021 | Approved | BRIAN MILLER |
| Deputy Grading | 10/7/2021 | Approved | TIMOTHY POWELL |
| Deputy Grading | 10/13/2021 | Approved | BRIAN MILLER |
| Deputy Grading | 10/14/2021 | Approved | BRIAN MILLER |
| Deputy Grading | 10/15/2021 | Conditional Approval | LANNY MERRICK |
| Deputy Grading | 10/18/2021 | Approved | TIMOTHY POWELL |
| Deputy Grading | 10/19/2021 | Approved | TIMOTHY POWELL |
| Deputy Grading | 10/20/2021 | Approved | TIMOTHY POWELL |
| Deputy Grading | 10/21/2021 | Approved | TIMOTHY POWELL |
| Deputy Grading | 10/22/2021 | Approved | TIMOTHY POWELL |
| Special/Order Compliance | 10/25/2021 | Approved | BRIAN MILLER |
| Special/Order Compliance | 3/14/2023 | Corrections Issued | ROBERT PINA |
| Approved Compaction Report | 3/28/2023 | Corrections Issued | BRIAN MILLER |
| Approved Compaction Report | 5/2/2023 | Approved | BRIAN MILLER |
| Bottom/Toe | 3/6/2024 | Approved | MANUEL TEJADA |
| Final | 3/6/2024 | Corrections Issued | MANUEL TEJADA |
| Rough | 3/6/2024 | Approved | MANUEL TEJADA |
| SWPPP-Const. Storm Water | 3/6/2024 | Completed | MANUEL TEJADA |
| Approved Compaction Report | 3/14/2024 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 3/15/2024 | Permit Finaled | GERMAN RODRIGUEZ MENDOZA |