2334 N WESTRIDGE ROAD 90049
Certificate Information: 2334 N WESTRIDGE ROAD 90049
- Application / Permit
- 17020-20000-03571
- Plan Check / Job No.
- B17VN18884
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- (N) (23'-8" X 71') DETACHED DECK ON PILES ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 11/14/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/8/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 1/4/2018 | RAPHAEL ROSAS |
| Corrections Issued | 1/11/2018 | RAPHAEL ROSAS |
| Quality Review Completed | 1/12/2018 | STEVEN KIM |
| Building Plans Picked Up | 1/18/2018 | APPLICANT |
| Plan Check Approved | 11/14/2018 | RAPHAEL ROSAS |
| Issued | 11/14/2018 | LADBS |
| CofO in Progress | 11/16/2023 | KEVIN SARGSYAN |
| Permit Finaled | 11/21/2023 | DANIEL ORRANTE |
| CofO Issued | 11/21/2023 | DANIEL ORRANTE |
| Permit Finaled | 11/21/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2018 | KENNETH PHAM |
| Low Impact Development | Cleared | 11/5/2018 | ORVAL HERNANDEZ-MARCIAL |
| Miscellaneous | Cleared | 11/5/2018 | KAYLA PEJI |
| Grading Pre-Inspection | Cleared | 11/14/2018 | RAPHAEL ROSAS |
| Roof/Waste drainage to street | Cleared | 11/14/2018 | LEE GUILBEAUX |
Contact Information
| Contractor | Proline Pool & Spas; Lic. No.: 507962-C53 | 17040 GRESHAM STREET NORTHRIDGE, CA 91325 |
| Engineer | Azizisefat, Solayman; Lic. No.: C57840 | 19510 VENTURA BLVD STE 110 TARZANA, CA 91356 |
| Engineer | Haro, Ruben Jr; Lic. No.: GE2990 | 1554 CIPRES CT CAMARILLO, CA 93010 |
| Geologist | Bovenizer, Ernest; Lic. No.: EG2515 | 7622 GODDARD AVENUE LOS ANGELES, CA 90045 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/23/2019 | Partial Inspection | RICHARD STEINBACH |
| Piling/Pier/Caisson | 5/9/2019 | Partial Approval | TIM CHRISTENSEN |
| Deputy Reinf. Concrete | 5/21/2019 | Conditional Approval | TIM CHRISTENSEN |
| Piling/Pier/Caisson | 5/23/2019 | Partial Approval | TIM CHRISTENSEN |
| Deputy Reinf. Concrete | 5/29/2019 | Conditional Approval | TIM CHRISTENSEN |
| Deputy Reinf. Concrete | 8/28/2019 | Conditional Approval | TIM CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 8/28/2019 | Corrections Issued | TIM CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 10/2/2019 | Corrections Issued | MICHAEL TEMPLE |
| Excavation/Setback/Form/Re-Bar | 10/4/2019 | Not Ready for Inspection | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 10/8/2019 | Approved | MICHAEL TEMPLE |
| Deputy Reinf. Concrete | 10/15/2019 | Conditional Approval | DAVID FEILER |
| Final | 3/21/2022 | Corrections Issued | JUAN VALENZUELA |
| Final | 5/9/2023 | Corrections Issued | KEVIN SARGSYAN |
| Final | 8/31/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Final | 11/15/2023 | OK to Issue CofO | KEVIN SARGSYAN |