1509 N MARLAY DR 90069
Certificate Information: 1509 N MARLAY DR 90069
- Application / Permit
- 17020-10000-03170
- Plan Check / Job No.
- B17LA20376
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Fence Wall
- Work Description
- NEW 50' LONG 18' HIGH IMPACT WALL AND PLANTER WALL ON PILES ON THE REAR OF THE LOT
- Permit Issued
- Issued on 8/26/2020
- Issuing Office
- Current Status
- Permit Finaled on 9/23/2021
Permit Application Status History
| Submitted | 11/7/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2017 | SINA KHOSRAVI |
| Green Plans Picked Up | 12/1/2017 | APPLICANT |
| Corrections Issued | 12/12/2017 | SINA KHOSRAVI |
| Quality Review Completed | 12/27/2017 | BILL STUTSMAN |
| Building Plans Picked Up | 12/29/2017 | APPLICANT |
| Applicant returned to address corrections | 4/27/2018 | SINA KHOSRAVI |
| Applicant returned to address corrections | 5/31/2018 | SINA KHOSRAVI |
| Applicant returned to address corrections | 2/6/2020 | SINA KHOSRAVI |
| Applicant returned to address corrections | 2/7/2020 | SINA KHOSRAVI |
| Plan Check Approved | 8/26/2020 | SINA KHOSRAVI |
| Issued | 8/26/2020 | APPLICANT |
| Permit Finaled | 9/22/2021 | ALEXANDER HELFER |
Permit Application Clearance Information
| Landscape for retaining wall | Cleared | 5/16/2018 | FIPE LEILUA |
Contact Information
| Contractor | Marino Pool And Spa; Lic. No.: 528696-B | 5739 KANAN RD #364 AGOURA HILLS, CA 91301 |
| Engineer | Lau, David Harkwong; Lic. No.: C34961 | 12467 W WASHINGTON BLVD LOS ANGELES, CA 90066 |
| Engineer | Rybak, Richard; Lic. No.: GE2131 | 20312 TAU PLACE CHATSWORTH, CA 91311 |
| Geologist | Haenschke, Eirik Francis; Lic. No.: EG1597 | 9001 MONOGRAM AVENUE NORTH HILLS, CA 91343 |
Inspector Information
| ROBERT PINA, (213) 482-0404 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 4/22/2021 | Approved | VASIL MIHALEV |
| Excavation/Setback/Form/Re-Bar | 4/22/2021 | Not Ready for Inspection | VASIL MIHALEV |
| Piling/Pier/Caisson | 4/22/2021 | Approved | VASIL MIHALEV |
| Pre-Inspection | 4/22/2021 | Approved | VASIL MIHALEV |
| Footing/Foundation/Slab | 4/28/2021 | Approved | ALEXANDER HELFER |
| Deputy Reinf. Concrete | 5/5/2021 | Conditional Approval | VASIL MIHALEV |
| Footing/Foundation/Slab | 5/19/2021 | Approved | VASIL MIHALEV |
| Reinforced Concrete Frame | 6/8/2021 | Approved | ALEXANDER HELFER |
| Deputy Shotcrete | 6/11/2021 | Approved | VASIL MIHALEV |
| Footing/Foundation/Slab | 7/1/2021 | Approved | VASIL MIHALEV |
| Deputy Shotcrete | 7/7/2021 | Approved | VASIL MIHALEV |
| Final | 7/26/2021 | Not Ready for Inspection | ALEXANDER HELFER |
| Masonry Wall/Backfill | 7/26/2021 | Approved | ALEXANDER HELFER |
| Reinforced Concrete Frame | 7/26/2021 | Approved | ALEXANDER HELFER |
| Final | 9/22/2021 | Permit Finaled | ALEXANDER HELFER |