11612 W CULVER BLVD 1-40 90066
Certificate Information: 11612 W CULVER BLVD 1-40 90066
- Application / Permit
- 17020-10000-03046
- Plan Check / Job No.
- B17LA20183
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Apartment
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- TEMPORARY SHORING FOR 16010-10000-05035
- Permit Issued
- Issued on 4/13/2018
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 7/24/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/26/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2017 | LARRY LEE |
| Corrections Issued | 11/28/2017 | LARRY LEE |
| Quality Review Completed | 12/4/2017 | WING SUEN |
| Building Plans Picked Up | 12/12/2017 | APPLICANT |
| Applicant returned to address corrections | 1/4/2018 | LARRY LEE |
| Plan Check Approved | 1/30/2018 | LARRY LEE |
| Issued | 4/13/2018 | LADBS |
| Permit Finaled | 7/24/2020 | NICK LAROCCA |
Permit Application Clearance Information
| Work Adjacent to Public Way | Cleared | 1/26/2018 | CHIU TAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/30/2018 | NAZILA NOORIFAR |
Contact Information
| Contractor | P And N Construction Inc; Lic. No.: 800653-B | 8730 WILSHIRE BLVD #202 BEVERLY HILLS, CA 90211 |
| Engineer | Berkoz, Ertunga; Lic. No.: S2504 | 4665 ELLENITA AVE TARZANA, CA 91356 |
Inspector Information
| VASIL MIHALEV, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 8/8/2018 | Approved | NICK LAROCCA |
| Deputy Steel/Welding | 8/8/2018 | Conditional Approval | NICK LAROCCA |
| Deputy Grading | 8/9/2018 | Conditional Approval | NICK LAROCCA |
| Deputy Steel/Welding | 8/9/2018 | Conditional Approval | NICK LAROCCA |
| Deputy Grading | 8/10/2018 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 8/10/2018 | Approved | DERRICK SPENCER |
| Deputy Grading | 8/13/2018 | Approved | DERRICK SPENCER |
| Deputy Grading | 8/14/2018 | Approved | DERRICK SPENCER |
| Deputy Grading | 8/15/2018 | Approved | DERRICK SPENCER |
| Deputy Grading | 8/16/2018 | Conditional Approval | TONY HARTONO |
| Footing/Foundation/Slab | 8/20/2018 | Partial Approval | DERRICK SPENCER |
| Piling/Pier/Caisson | 8/28/2018 | Partial Inspection | NICK LAROCCA |
| Deputy Grading | 8/30/2018 | Approved | NICK LAROCCA |
| Deputy Grading | 8/31/2018 | Approved | NICK LAROCCA |
| Deputy Grading | 9/10/2018 | Approved | NICK LAROCCA |
| Deputy Grading | 9/11/2018 | Approved | NICK LAROCCA |
| Deputy Grading | 9/12/2018 | Approved | NICK LAROCCA |
| Deputy Steel/Welding | 9/14/2018 | Approved | NICK LAROCCA |
| Deputy Grading | 9/17/2018 | Approved | NICK LAROCCA |
| Deputy Grading | 9/18/2018 | Approved | NICK LAROCCA |
| Deputy Grading | 9/19/2018 | Approved | NICK LAROCCA |
| Deputy Grading | 9/20/2018 | Approved | NICK LAROCCA |
| Deputy Grading | 9/21/2018 | Approved | NICK LAROCCA |
| Deputy Grading | 9/24/2018 | Approved | NICK LAROCCA |
| Deputy Grading | 9/25/2018 | Approved | NICK LAROCCA |
| Deputy Grading | 9/26/2018 | Approved | NICK LAROCCA |
| Deputy Grading | 9/27/2018 | Approved | NICK LAROCCA |
| Deputy Grading | 9/28/2018 | Approved | NICK LAROCCA |
| Deputy Steel/Welding | 10/1/2018 | Approved | NICK LAROCCA |
| Deputy Steel/Welding | 10/2/2018 | Approved | NICK LAROCCA |
| Deputy Steel/Welding | 10/3/2018 | Conditional Approval | NICK LAROCCA |
| Deputy Steel/Welding | 10/5/2018 | Approved | NICK LAROCCA |
| Deputy Grading | 10/10/2018 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Grading | 10/11/2018 | Approved | NICK LAROCCA |
| Deputy Grading | 10/12/2018 | Conditional Approval | NICK LAROCCA |
| Deputy Steel/Welding | 10/18/2018 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 10/19/2018 | Conditional Approval | NICK LAROCCA |
| Piling/Pier/Caisson | 10/29/2018 | Partial Inspection | NICK LAROCCA |