6565 E PICKWICK ST 90042
Certificate Information: 6565 E PICKWICK ST 90042
- Application / Permit
- 17020-10000-02996
- Plan Check / Job No.
- B17LA19274
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- TWO 10 FT HIGH RETAINING WALLS (140 FT LONG).
- Permit Issued
- Issued on 9/10/2021
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 9/6/2024
Permit Application Status History
| Submitted | 10/20/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 11/2/2017 | NIKTA MOUSAVI |
| Corrections Issued | 11/14/2017 | NIKTA MOUSAVI |
| Green Plans Picked Up | 11/15/2017 | APPLICANT |
| Quality Review Completed | 12/11/2017 | BILL STUTSMAN |
| Applicant returned to address corrections | 2/16/2018 | NIKTA MOUSAVI |
| Applicant returned to address corrections | 4/20/2018 | NIKTA MOUSAVI |
| Applicant returned to address corrections | 5/10/2018 | NIKTA MOUSAVI |
| Applicant returned to address corrections | 6/7/2018 | NIKTA MOUSAVI |
| Applicant returned to address corrections | 9/8/2020 | LUIS RINCON |
| Applicant returned to address corrections | 10/6/2020 | LUIS RINCON |
| Applicant returned to address corrections | 1/6/2021 | LUIS RINCON |
| Applicant returned to address corrections | 3/11/2021 | LUIS RINCON |
| Applicant returned to address corrections | 4/10/2021 | LUIS RINCON |
| Applicant returned to address corrections | 5/13/2021 | LUIS RINCON |
| Applicant returned to address corrections | 6/25/2021 | LUIS RINCON |
| Plan Check Approved | 8/12/2021 | LUIS RINCON |
| Issued | 9/10/2021 | APPLICANT |
| Building Plans Picked Up | 9/10/2021 | APPLICANT |
| Permit Finaled | 9/5/2024 | LANNY MERRICK |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/29/2018 | LEE GUILBEAUX |
| HPOZ | Cleared | 10/3/2019 | STEVEN WECHSLER |
| Landscape for retaining wall | Cleared | 10/3/2019 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 10/3/2019 | STEVEN WECHSLER |
| ZA Case | Cleared | 10/3/2019 | STEVEN WECHSLER |
| ZA Case | Cleared | 10/3/2019 | STEVEN WECHSLER |
| ZI | Cleared | 10/3/2019 | STEVEN WECHSLER |
| Construction near power lines | Cleared | 10/17/2019 | WALTER RAMIREZ |
| Encroachment in public way | Cleared | 11/8/2019 | ELAINE LEI |
| Work Adjacent to Public Way | Cleared | 11/8/2019 | BOK GOH |
| Excavation more than 5-ft deep | Cleared | 1/2/2020 | CALOSHA APPROVED |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Husain, Shahzain; Lic. No.: C62744 | 1710 N MOORPARK RD #100 THOUSAND OAKS, CA 91360 |
| Engineer | Lee,, Allen C; Lic. No.: GE2781 | 11823 SLAUSON AVE STE 46 SANTA FE SPRINGS, CA 90670 |
| Engineer | Lewis, Stephen H; Lic. No.: C70304 | 169 S BALDWIN AVE SIERRA MADRE, CA 91024 |
| Engineer | Mar,, Larry L; Lic. No.: C55069 | 4425 BEULAH DR LA CANADA, CA 91011 |
Inspector Information
| JONATHAN HOM, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT HUGHES, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/3/2022 | Partial Approval | MATTHEW JENKINS |
| Footing/Foundation/Slab | 5/4/2022 | Not Ready for Inspection | ROBERT HUGHES |
| Footing/Foundation/Slab | 5/10/2022 | Not Ready for Inspection | ROBERT HUGHES |
| Footing/Foundation/Slab | 5/17/2022 | Partial Approval | ROBERT HUGHES |
| Footing/Foundation/Slab | 5/25/2022 | Partial Approval | ROBERT HUGHES |
| Masonry Wall/Backfill | 6/7/2022 | Partial Approval | ROBERT HUGHES |
| Masonry Wall/Backfill | 6/21/2022 | Partial Approval | ROBERT HUGHES |
| Footing/Foundation/Slab | 7/7/2022 | Partial Approval | ROBERT HUGHES |
| Masonry Wall/Backfill | 7/7/2022 | Partial Approval | ROBERT HUGHES |
| Special/Order Compliance | 7/12/2022 | Corrections Issued | ROBERT HUGHES |
| Masonry Wall/Backfill | 7/21/2022 | Partial Approval | ROBERT HUGHES |
| Masonry Wall/Backfill | 7/29/2022 | Not Ready for Inspection | ROBERT HUGHES |
| Masonry Wall/Backfill | 8/5/2022 | Partial Approval | ROBERT HUGHES |
| Footing/Foundation/Slab | 7/7/2023 | Corrections Issued | ROBERT HUGHES |
| Final | 9/5/2024 | Permit Finaled | LANNY MERRICK |