1754 N GARFIELD PL 90028

Certificate Information: 1754 N GARFIELD PL 90028

Application / Permit
17016-70000-37823
Plan Check / Job No.
B17SL01632
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) STORAGE ROOM TO A.D.U. PER LAMC section 12.22A, 33 (c)-(d)
Permit Issued
Issued on 6/25/2020
Issuing Office
Current Status
CofO Issued on 5/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2017 APPLICANT
Assigned to Plan Check Engineer 1/4/2018 YAQUB MIRZA
Plans on Hold 2/26/2018 SIAVOSH POURSABAHIAN
Hold Released 8/1/2018 BILL STUTSMAN
Corrections Issued 8/1/2018 YAQUB MIRZA
Quality Review Completed 8/8/2018 BILL STUTSMAN
Plan Check Approved 5/28/2020 YAQUB MIRZA
Issued 6/25/2020 APPLICANT
Building Plans Picked Up 6/30/2020 APPLICANT
CofO in Progress 5/15/2026 CRAIG VAUGHAN
Permit Finaled 5/16/2026 DEROLD HAUFF
CofO Issued 5/16/2026 DEROLD HAUFF
Permit Finaled 5/16/2026 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 3/20/2018 SARAH ABOULHOSN
Address approval Cleared 9/21/2018 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 9/21/2018 JEANETTE VONG
Roof/Waste drainage to street Cleared 9/21/2018 STEVE MELGAR
Sewer availability Cleared 9/21/2018 STEVE MELGAR
Hydrant and Access approval Cleared 9/26/2018 ROBERT DUFF
Grading Pre-Inspection Cleared 10/15/2018 PATRICK MISCHLICH
Specific Plan Cleared 6/12/2019 JASON HERNANDEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/19/2020 Approved JOSEPH MCGARRY
Pre-Inspection 9/1/2022 Corrections Issued JOAQUIN GREENOUGH
Pre-Inspection 1/18/2024 Corrections Issued ROY SPAULDING
Pre-Inspection 4/7/2025 Partial Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 5/7/2025 Approved CRAIG VAUGHAN
PLUMBING-Rough 5/7/2025 Partial Approval CRAIG VAUGHAN
Wood Frame 6/2/2025 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 6/11/2025 Partial Approval CRAIG VAUGHAN
Underground Mechanical 6/11/2025 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 6/23/2025 Approved ENRIQUE MIRELES
Green Building Rough 6/23/2025 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 6/23/2025 Approved ENRIQUE MIRELES
Shower Pan 6/23/2025 Approved ENRIQUE MIRELES
Insulation 6/30/2025 Approved JOSH MEISTER
Drywall Nailing 7/3/2025 Corrections Issued RONNIE MEDINA
Shower Pan 7/3/2025 Approved RONNIE MEDINA
Service/Power Release 7/8/2025 Not Ready for Inspection CRAIG VAUGHAN
Interior/Exterior Lathing 7/17/2025 Partial Approval CRAIG VAUGHAN
Service/Power Release 7/17/2025 Not Ready for Inspection CRAIG VAUGHAN
Drywall Nailing 7/21/2025 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 7/21/2025 Approved CRAIG VAUGHAN
Final 11/14/2025 Corrections Issued CRAIG VAUGHAN
Green Building Final 11/14/2025 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 11/14/2025 SGSOV Not Required CRAIG VAUGHAN
Smoke Detectors 11/14/2025 Approved CRAIG VAUGHAN
Final 11/19/2025 Not Ready for Inspection CRAIG VAUGHAN
Final 11/26/2025 Not Ready for Inspection CRAIG VAUGHAN
Final 3/11/2026 Not Ready for Inspection CRAIG VAUGHAN
Final 4/29/2026 Partial Inspection CRAIG VAUGHAN
Final 5/14/2026 OK to Issue CofO CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 5/14/2026 Approved CRAIG VAUGHAN