2252 1/2 E DUVALL ST 90031

Certificate Information: 2252 1/2 E DUVALL ST 90031

Application / Permit
17016-40000-16917
Plan Check / Job No.
B17SP00567
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
convert garage to an adu per AB 2299 and SB 1069
Permit Issued
Issued on 6/23/2017
Issuing Office
Metro
Current Status
CofO Issued on 9/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/22/2017 APPLICANT
Assigned to Plan Check Engineer 6/22/2017 JAMES DETCHMENDY
Corrections Issued 6/22/2017 JAMES DETCHMENDY
Plan Check Approved 6/23/2017 ARSALAN SHABESTARI
Issued 6/23/2017 LADBS
CofO in Progress 9/26/2022 THOMAS LOGRASSO
Permit Finaled 9/30/2022 DEROLD HAUFF
CofO Issued 9/30/2022 DEROLD HAUFF
Permit Finaled 9/30/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/22/2017 ROCHELLE DUNGCA
Eng Process Fee Ord 176,300 Cleared 6/22/2017 ROCHELLE DUNGCA
Sewer availability Cleared 6/22/2017 ROCHELLE DUNGCA
ZI Cleared 6/22/2017 DANALYNN DOMINGUEZ

Contact Information

Contractor Gibson Design / Build; Lic. No.: 810077-B 1118 PACIFIC AVE      LONG BEACH, CA 90813
Engineer Christiansen, Scott; Lic. No.: C37989 710 WILSHIRE BLVD_#230      SANTA MONICA, CA 90401

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/21/2019 Approved ROBERT MCDOWELL
Deputy Drilled-In Anchors 8/3/2020 Partial Approval RUBEN SALAS
Deputy Other (see comments) 8/3/2020 Partial Approval RUBEN SALAS
PLUMBING-Rough 8/11/2020 Not Ready for Inspection DAVID CHAN
Footing/Foundation/Slab 8/19/2020 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 8/19/2020 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 8/24/2020 Approved HAMIK HARTOUNIAN
Sewer 8/24/2020 Approved HAMIK HARTOUNIAN
Underground Mechanical 8/24/2020 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/26/2020 Partial Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/28/2020 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/22/2020 Corrections Issued DAVID CHAN
PLUMBING-Rough 2/1/2021 Partial Inspection COREY HUPP
ELECTRICAL-Rough 3/17/2021 Approved SCOTT FINNILA
Interior/Exterior Lathing 3/17/2021 Partial Approval SCOTT FINNILA
PLUMBING-Rough 3/17/2021 Approved SCOTT FINNILA
Wood Frame 3/17/2021 Approved SCOTT FINNILA
Insulation 5/24/2021 Approved SCOTT FINNILA
Drywall Nailing 7/6/2021 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 4/11/2022 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 8/1/2022 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Final 8/1/2022 Not Ready for Inspection THOMAS LOGRASSO
Final 8/1/2022 Corrections Issued THOMAS LOGRASSO
Green Building Final 8/1/2022 Not Ready for Inspection THOMAS LOGRASSO
Green Building Rough 8/1/2022 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Final 8/1/2022 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 8/1/2022 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 8/1/2022 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 9/21/2022 Approved THOMAS LOGRASSO
Final 9/21/2022 Not Ready for Inspection THOMAS LOGRASSO
Green Building Final 9/21/2022 Approved THOMAS LOGRASSO
Green Building Rough 9/21/2022 Approved THOMAS LOGRASSO
Smoke Detectors 9/21/2022 Approved THOMAS LOGRASSO
Final 9/26/2022 OK to Issue CofO THOMAS LOGRASSO