266 1/2 W 17TH ST 90731
Certificate Information: 266 1/2 W 17TH ST 90731
- Application / Permit
- 17016-40000-03051
- Plan Check / Job No.
- B17SP00100
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Converting a existing recreation room to a accessory dwelling unit per AB-2299 & SB 1069.
- Permit Issued
- Issued on 1/14/2020
- Issuing Office
- Valley
- Current Status
- Issued on 1/14/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/10/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 3/9/2017 | ZAW HAN |
| Corrections Issued | 3/13/2017 | ZAW HAN |
| Quality Review Completed | 3/21/2017 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 7/6/2017 | ZAW HAN |
| Plan Check Approved | 1/9/2020 | ZAW HAN |
| Issued | 1/14/2020 | LADBS |
Permit Application Clearance Information
| Address approval | Cleared | 8/2/2017 | AREZOO RAHIMI |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2017 | AREZOO RAHIMI |
| Sewer availability | Cleared | 8/2/2017 | AREZOO RAHIMI |
| Coastal Zone | Cleared | 11/12/2019 | TREVOR MARTIN |
Contact Information
| Architect | Ng, Edward Lok Gin; Lic. No.: C16840 | 3147 LEES AVENUE LONG BEACH, CA 90808 |
| Contractor | Gibson Design / Build; Lic. No.: 810077-B | 512 DE SOTO DR HEMET, CA 92543 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/21/2020 | Partial Inspection | ANSON MAGLASANG |
| ELECTRICAL-Rough | 1/27/2020 | Corrections Issued | ANSON MAGLASANG |
| PLUMBING-Rough | 1/27/2020 | Corrections Issued | ANSON MAGLASANG |
| ELECTRICAL-Rough | 2/19/2020 | Conditional Approval | ANSON MAGLASANG |
| PLUMBING-Rough | 2/19/2020 | Partial Approval | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 2/24/2020 | Not Ready for Inspection | ANSON MAGLASANG |
| HVAC-Rough | 2/24/2020 | Corrections Issued | ANSON MAGLASANG |
| Insulation | 2/24/2020 | Corrections Issued | ANSON MAGLASANG |
| PLUMBING-Rough | 2/24/2020 | Approved | ANSON MAGLASANG |
| Drywall Nailing | 3/13/2020 | Approved | ANSON MAGLASANG |
| PLUMBING-Rough | 3/13/2020 | Approved | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 4/23/2020 | Not Ready for Inspection | JOHN KLARIN |
| Final | 4/23/2020 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Final | 4/23/2020 | Not Ready for Inspection | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 4/23/2020 | SGSOV Not Ready | JOHN KLARIN |
| Smoke Detectors | 4/23/2020 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Final | 4/27/2020 | Approved | JOHN KLARIN |
| Pre-Inspection | 4/27/2020 | Corrections Issued | JOHN KLARIN |