6101 W PICKFORD PL 90035
Certificate Information: 6101 W PICKFORD PL 90035
- Application / Permit
- 17016-30000-32777
- Plan Check / Job No.
- B17WL06474
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert attached one car garage to Accessory Dwelling Unit Per AB 2299 & SB 1069.
- Permit Issued
- Issued on 11/22/2017
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/6/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/3/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 11/3/2017 | HARLEN CARRAHER |
| Corrections Issued | 11/6/2017 | HARLEN CARRAHER |
| Plan Check Approved | 11/22/2017 | HARLEN CARRAHER |
| Issued | 11/22/2017 | LADBS |
| CofO in Progress | 1/28/2026 | STUART CHAPMAN |
| No Progress | 1/28/2026 | DEROLD HAUFF |
| CofO in Progress | 1/28/2026 | DEROLD HAUFF |
| CofO in Progress | 1/29/2026 | OSVALDO PARAMO |
| No Progress | 1/29/2026 | DEROLD HAUFF |
| CofO in Progress | 1/29/2026 | DEROLD HAUFF |
| Permit Finaled | 2/6/2026 | DEROLD HAUFF |
| CofO Issued | 2/6/2026 | DEROLD HAUFF |
| Permit Finaled | 2/6/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/13/2017 | KENNETH PHAM |
| Eng Process Fee Ord 176,300 | Cleared | 11/13/2017 | KENNETH PHAM |
| Permit | Cleared | 11/13/2017 | KENNETH PHAM |
| Sewer availability | Cleared | 11/13/2017 | KENNETH PHAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/26/2018 | Not Ready for Inspection | MATTHEW NUCKOLLS |
| Sewer | 10/5/2018 | No Access for Inspection | KATHRYN BUTTERWORTH |
| Special/Order Compliance | 9/16/2019 | Partial Inspection | CHRISTOPHER DELLEFIELD |
| Deputy Drilled-In Anchors | 4/27/2023 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 6/26/2023 | Approved | JOSE AVILA |
| PLUMBING-Rough | 7/6/2023 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 7/17/2023 | Approved | JOSE AVILA |
| Green Building Rough | 7/17/2023 | Approved | JOSE AVILA |
| METHANE-Final | 7/17/2023 | Approved | JOSE AVILA |
| METHANE-Rough | 7/17/2023 | Approved | JOSE AVILA |
| Shower Pan | 7/21/2023 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 1/2/2024 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 1/2/2024 | SGSOV Not Ready | BRENDAN MORELLI |
| Pre-Inspection | 1/4/2024 | Partial Inspection | SCOTT FINNILA |
| Final | 1/17/2024 | Partial Approval | STUART CHAPMAN |
| Green Building Final | 1/17/2024 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 1/17/2024 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 1/17/2024 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 2/9/2024 | Approved | STUART CHAPMAN |
| Final | 2/9/2024 | Conditional Approval | STUART CHAPMAN |
| HVAC-Final | 2/9/2024 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 2/9/2024 | Approved | STUART CHAPMAN |
| Final | 9/30/2024 | Corrections Issued | STUART CHAPMAN |
| Final | 1/28/2026 | OK to Issue CofO | STUART CHAPMAN |