7029-7031 S EARLDOM AVE 90293

Certificate Information: 7029-7031 S EARLDOM AVE 90293

Application / Permit
17016-30000-29743
Plan Check / Job No.
B17WL05880
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT PORTION OF EXISTING GARAGE INTO JADU
Permit Issued
Issued on 7/22/2021
Issuing Office
Current Status
CofO Issued on 9/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/10/2017 APPLICANT
Assigned to Plan Check Engineer 10/12/2017 TARIK SAOUD
Corrections Issued 10/17/2017 TARIK SAOUD
Quality Review Completed 10/24/2017 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 2/5/2021 APPLICANT
Plan Check Approved 7/6/2021 TARIK SAOUD
Issued 7/22/2021 APPLICANT
CofO in Progress 9/1/2023 BOBBY KEY
Permit Finaled 9/9/2023 DANIEL ORRANTE
CofO Issued 9/9/2023 DANIEL ORRANTE
Permit Finaled 9/9/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/25/2017 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 10/25/2017 HISASHI KOBAYAKAWA
Grading Pre-Inspection Cleared 10/25/2017 TIMOTHY POWELL
Sewer availability Cleared 10/25/2017 HISASHI KOBAYAKAWA
Miscellaneous Cleared 12/15/2020 TERRI OSBORNE
ZA Case Cleared 12/15/2020 TERRI OSBORNE
Specific Plan Cleared 4/26/2021 KEVIN ARUCAN
Coastal Zone Cleared 5/3/2021 MINDY NGUYEN

Contact Information

Contractor Owner-Builder       ,
Engineer Yaprak,, Taskin Tolga; Lic. No.: C72927 560 31ST ST      MANHATTAN BEACH, CA 90266

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 12/13/2021 Corrections Issued BOBBY KEY
PLUMBING-Rough 12/13/2021 Approved BOBBY KEY
ELECTRICAL-Rough 12/16/2021 Approved BOBBY KEY
BUILDING-Rough-Frame 2/17/2022 Conditional Approval BOBBY KEY
Green Building Rough 2/17/2022 Approved BOBBY KEY
HVAC-Rough 2/17/2022 Approved BOBBY KEY
Insulation 2/17/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 2/24/2022 Approved BOBBY KEY
Drywall Nailing 2/24/2022 Approved BOBBY KEY
Final 2/24/2022 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 2/24/2022 Partial Approval BOBBY KEY
Final 4/18/2022 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 4/18/2022 Approved BOBBY KEY
Final 8/16/2023 Corrections Issued KENNETH NAGLE
Final 8/24/2023 Corrections Issued BOBBY KEY
Smoke Detectors 8/24/2023 Approved BOBBY KEY
ELECTRICAL-Final 9/1/2023 Approved BOBBY KEY
Final 9/1/2023 OK to Issue CofO BOBBY KEY
HVAC-Final 9/1/2023 Approved BOBBY KEY
PLUMBING-Final 9/1/2023 Approved BOBBY KEY