1079 N AMALFI DR 90272

Certificate Information: 1079 N AMALFI DR 90272

Application / Permit
17016-30000-26017
Plan Check / Job No.
B17WL05195
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Additions and interior remodel to the existing SFD with attached garage. Additions consist of converting a portion of the garage to habitable area and fill-in of 2nd floor areas that are open to the 1st floor. No exterior work (See comments).
Permit Issued
Issued on 10/19/2017
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/8/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/11/2017 APPLICANT
Assigned to Plan Check Engineer 9/14/2017 JOSE RODRIGUEZ
Corrections Issued 9/20/2017 JOSE RODRIGUEZ
Green Plans Picked Up 9/22/2017 APPLICANT
Quality Review Completed 9/28/2017 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 9/29/2017 APPLICANT
Applicant returned to address corrections 10/11/2017 JOSE RODRIGUEZ
Plan Check Approved 10/18/2017 JOSE RODRIGUEZ
Issued 10/19/2017 LADBS
CofO in Progress 6/8/2021 KENNETH NAGLE
Permit Finaled 6/8/2021 KENNETH NAGLE
CofO Issued 6/8/2021 KENNETH NAGLE
Permit Finaled 6/8/2021 KENNETH NAGLE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 9/29/2017 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 9/29/2017 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 9/29/2017 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 9/29/2017 HISASHI KOBAYAKAWA
Sewer availability Cleared 9/29/2017 HISASHI KOBAYAKAWA
Grading Pre-Inspection Cleared 10/2/2017 PATRICK MISCHLICH
Low Impact Development Cleared 10/2/2017 SAM NAVID
Green Code Cleared 10/17/2017 KAMRAN GHOTBI RAVANDI
GPI Written Notices Cleared 10/18/2017 JOSE RODRIGUEZ

Contact Information

Architect Mineau, Kenneth William; Lic. No.: C19133 140 LOMA MEDIA      SANTA BARBARA, CA 93103
Engineer Parker, Leo Augustine; Lic. No.: S2829 1927 PONTIUS AVE      LOS ANGELES, CA 90025

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/7/2017 Approved JOHN LUMB
Footing/Foundation/Slab 12/12/2017 Partial Approval KENNETH NAGLE
Footing/Foundation/Slab 12/14/2017 Partial Inspection RICHARD STEINBACH
Deputy Drilled-In Anchors 12/27/2017 Partial Approval JOHN LUMB
Footing/Foundation/Slab 1/9/2018 Partial Approval JOHN LUMB
Deputy Drilled-In Anchors 1/29/2018 Partial Approval JOHN LUMB
HVAC-Rough 4/10/2018 Not Ready for Inspection KENNETH NAGLE
HVAC-Rough 5/18/2018 Approved KENNETH NAGLE
ELECTRICAL-Rough 5/24/2018 Approved KENNETH NAGLE
PLUMBING-Rough 5/24/2018 Partial Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 7/13/2018 Partial Approval KENNETH NAGLE
BUILDING-Rough-Frame 7/20/2018 Not Ready for Inspection KENNETH NAGLE
Green Building Rough 7/20/2018 Not Ready for Inspection KENNETH NAGLE
BUILDING-Rough-Frame 7/26/2018 Not Ready for Inspection KENNETH NAGLE
Green Building Rough 7/26/2018 Not Ready for Inspection KENNETH NAGLE
ELECTRICAL-Rough 10/12/2018 Partial Inspection KENNETH NAGLE
PLUMBING-Rough 10/12/2018 Partial Inspection KENNETH NAGLE
Green Building Rough 11/5/2018 Approved KENNETH NAGLE
HVAC-Rough 11/5/2018 Approved KENNETH NAGLE
BUILDING-Rough-Frame 11/7/2018 Approved KENNETH NAGLE
Green Building Rough 11/7/2018 Approved KENNETH NAGLE
Insulation 11/19/2018 Not Ready for Inspection MICHAEL PELHAM
Insulation 11/29/2018 No Access for Inspection KENNETH NAGLE
Insulation 11/30/2018 No Access for Inspection KENNETH NAGLE
Insulation 12/4/2018 Approved KENNETH NAGLE
Drywall Nailing 12/21/2018 Approved KENNETH NAGLE
Interior/Exterior Lathing 12/27/2018 Not Ready for Inspection RICHARD STEINBACH
Shower Pan 12/31/2018 Approved KENNETH NAGLE
Interior/Exterior Lathing 1/2/2019 Approved KENNETH NAGLE
Gas Test 7/24/2019 Partial Approval DANNY TOLENTINO
Shower Pan 1/15/2020 Approved MICHAEL TEMPLE
Special/Order Compliance 1/15/2020 Corrections Issued MICHAEL TEMPLE
PLUMBING-Rough 5/20/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 9/25/2020 Approved TIM CHRISTENSEN
PLUMBING-Final 12/8/2020 Corrections Issued ANDREW NAVE
HVAC-Final 12/18/2020 Corrections Issued CHRIS CHRISTENSEN
PLUMBING-Final 12/18/2020 Approved CHRIS CHRISTENSEN
HVAC-Final 1/28/2021 Corrections Issued ANDREW NAVE
HVAC-Final 2/5/2021 Approved JUAN VALENZUELA
ELECTRICAL-Final 3/1/2021 Corrections Issued JOHNNY MIRANDA
ELECTRICAL-Final 3/5/2021 Approved ANDREW NAVE
Final 4/21/2021 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 4/21/2021 Approved JUAN VALENZUELA
Green Building Final 4/21/2021 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 4/21/2021 SGSOV Approved JUAN VALENZUELA
Smoke Detectors 4/21/2021 Approved JUAN VALENZUELA
Final 5/7/2021 Conditional Approval JUAN VALENZUELA