2001 E 7TH ST 90021

Certificate Information: 2001 E 7TH ST 90021

Application / Permit
17016-20002-28384
Plan Check / Job No.
B20VN16082
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
SUPPL PERMIT TO REVISE FLOOR PLAN (ARCH ONLY) @ 1ST & 2ND FLRS TO INCREASE OCCUPANT LOAD & REDUCE 2ND FLOOR ADDITION. REMOVE HANDICAP ACCESSIBLE LIFT & REPLACE WITH SPIRAL STAIRS. CLOSE UP ONE EXIT DOOR ALONG MATEO ST. (STRUCT PLAN CHECK 18016-20002-25395). SEE COMMENTS.
Permit Issued
Issued on 7/1/2021
Issuing Office
Current Status
Permit Finaled on 4/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/18/2020 APPLICANT
Assigned to Plan Check Engineer 12/23/2020 HAYATO TSUCHIYA
Corrections Issued 12/26/2020 HAYATO TSUCHIYA
Quality Review Completed 12/30/2020 STEVEN KIM
Disabled Access Plans Picked Up 1/14/2021 APPLICANT
Applicant returned to address corrections 3/10/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 5/22/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 5/25/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 6/5/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 6/10/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 6/30/2021 HAYATO TSUCHIYA
Plan Check Approved 7/1/2021 HAYATO TSUCHIYA
Issued 7/1/2021 APPLICANT
Building Plans Picked Up 7/6/2021 APPLICANT
Permit Finaled 4/3/2023 RAFAEL ESPINOZA

Permit Application Clearance Information

Fire Marshall Fire Life Safety Cleared 3/15/2021 MENOA AGHAJANI
Redevelopment Project Area Cleared 4/19/2021 DAVID URITA
DAS Clearance Cleared 5/11/2021 HAYATO TSUCHIYA

Contact Information

Contractor Nishiya Co Inc; Lic. No.: 986627-B 1501 PALOS VERDES NORTH   SPACE 21    HARBOR CITY, CA 90710
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 7/8/2021 Partial Approval MARK FERRARI
Drywall Nailing 7/19/2021 Approved LANNY MERRICK
Drywall Nailing 8/27/2021 Partial Approval DAVID TSAU
Light Gage Steel Frame 11/18/2021 Not Ready for Inspection MARK FERRARI
Light Gage Steel Frame 11/19/2021 Approved MARK FERRARI
Drywall Nailing 1/11/2022 Approved MARK FERRARI
Special/Order Compliance 2/4/2022 Not Ready for Inspection MARK FERRARI
Special/Order Compliance 2/7/2022 Partial Inspection MARK FERRARI
Excavation/Setback/Form/Re-Bar 2/17/2022 Partial Approval MARK FERRARI
Excavation/Setback/Form/Re-Bar 3/1/2022 Partial Approval MARK FERRARI
Special/Order Compliance 5/13/2022 Partial Inspection MARK FERRARI
Final 6/24/2022 No Access for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 6/24/2022 Not Ready for Inspection RAFAEL ESPINOZA
Special/Order Compliance 12/9/2022 Partial Inspection MARK FERRARI
Pre-Inspection 1/4/2023 Approved RAFAEL CORTES
Final 3/28/2023 Not Ready for Inspection JULIAN CAPUCETTI
Reinforced Masonry Frame 3/28/2023 Approved JULIAN CAPUCETTI
Final 4/3/2023 Permit Finaled RAFAEL ESPINOZA