12500 W BURBANK BLVD 91607

Certificate Information: 12500 W BURBANK BLVD 91607

Application / Permit
17016-20001-23744
Plan Check / Job No.
B19VN09386
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(18) School Building
Work Description
SUPPLEMENTAL TO 17016-20000-23744. REVISE ARCHITECT & STRUCTURAL PLAN, CHANGE ENGINEER OF RECORD WITH (N) STRUCTURAL PLAN FOR PROPOSED SCHOOL BUILDING CORRECT MAC.OCCUPANT LOAD FOR E OCCUPANCY FROM 175 TO 57 STUDENTS PER CPC-2016-2690-CU-SPP, ADD NEW SKYLIGHTS, T.I. SCHOOL BUILDING.
Permit Issued
Issued on 11/6/2019
Issuing Office
Valley
Current Status
Permit Finaled on 12/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/6/2019 APPLICANT
Assigned to Plan Check Engineer 6/20/2019 CHON CHIO KUO
Corrections Issued 6/24/2019 CHON CHIO KUO
Quality Review Completed 6/25/2019 STEVEN KIM
Building Plans Picked Up 6/26/2019 APPLICANT
Disabled Access Plans Picked Up 6/26/2019 APPLICANT
Green Plans Picked Up 6/26/2019 APPLICANT
Applicant returned to address corrections 9/10/2019 CHON CHIO KUO
Applicant returned to address corrections 9/19/2019 CHON CHIO KUO
Plan Check Approved 9/26/2019 CHON CHIO KUO
Issued 11/6/2019 LADBS
Permit Finaled 12/24/2024 ROBERT DAVIS

Permit Application Clearance Information

Hold Cleared 6/24/2019 CHON CHIO KUO
Green Code Cleared 9/17/2019 DAVID MATSON
DAS Clearance Cleared 9/18/2019 CHON CHIO KUO
"Q" conditions Cleared 9/19/2019 DAISY BENICIA
CPC Cleared 9/19/2019 DAISY BENICIA
Specific Plan Cleared 9/19/2019 DAISY BENICIA
Fire Marshall Fire Life Safety Cleared 9/24/2019 OSCAR SALGADO JR

Contact Information

Contractor Nicon Construction Co; Lic. No.: 532461-B 11684 VENTURA BOULEVARD #272      STUDIO CITY, CA 91604
Engineer Mayer,, Robert; Lic. No.: S1991 5109 BELLAIRE AVENUE      N HOLLYWOOD, CA 91607

Inspector Information

JEFFREY FULTON, (818) 374-1132 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/18/2020 Partial Approval ROBERT DAVIS
Deputy Drilled-In Anchors 4/3/2020 Conditional Approval ROBERT DAVIS
Footing/Foundation/Slab 4/6/2020 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 4/14/2020 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 5/18/2020 Conditional Approval ROBERT DAVIS
Deputy Drilled-In Anchors 9/17/2020 Approved ROBERT DAVIS
Footing/Foundation/Slab 9/17/2020 Partial Approval ROBERT DAVIS
Deputy Drilled-In Anchors 10/2/2020 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 10/13/2020 Conditional Approval ROBERT DAVIS
Final 7/26/2021 Not Ready for Inspection ROBERT DAVIS
Footing/Foundation/Slab 7/26/2021 Approved ROBERT DAVIS
Green Building Final 7/26/2021 Not Ready for Inspection ROBERT DAVIS
Green Building Rough 7/26/2021 Approved ROBERT DAVIS
Reinforced Masonry Frame 7/26/2021 Approved ROBERT DAVIS
Smoke Detectors 7/26/2021 Not Ready for Inspection ROBERT DAVIS
Final 8/11/2021 Not Ready for Inspection ROBERT DAVIS
Green Building Final 8/11/2021 Not Ready for Inspection ROBERT DAVIS
Smoke Detectors 8/11/2021 Not Ready for Inspection ROBERT DAVIS
Final 12/24/2024 Permit Finaled ROBERT DAVIS
Green Building Final 12/24/2024 Approved ROBERT DAVIS
Smoke Detectors 12/24/2024 Approved ROBERT DAVIS