5906-5908 N CAHILL AVE 91356

Certificate Information: 5906-5908 N CAHILL AVE 91356

Application / Permit
17016-20000-29644
Plan Check / Job No.
B17VN15325
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert (E) 20'0"x 24'7" attached recreation room into a New Accessory Dwelling Unit per AB 2299 and SB 1069.
Permit Issued
Issued on 12/11/2017
Issuing Office
Valley
Current Status
CofO Issued on 3/5/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/10/2017 APPLICANT
Assigned to Plan Check Engineer 10/12/2017 DANNY MORALES
Corrections Issued 10/19/2017 DANNY MORALES
Quality Review Completed 10/19/2017 GUANG MIN TUNG
Building Plans Picked Up 10/24/2017 APPLICANT
Plan Check Approved 11/22/2017 DANNY MORALES
Issued 12/11/2017 LADBS
CofO in Progress 3/5/2020 STEVEN BACK
CofO Issued 3/5/2020 DONALD SUNSERI
Permit Finaled 3/5/2020 DONALD SUNSERI

Permit Application Clearance Information

Address approval Cleared 11/14/2017 EDUARDO PEDROZA
Eng Process Fee Ord 176,300 Cleared 11/14/2017 EDUARDO PEDROZA
Sewer availability Cleared 11/14/2017 EDUARDO PEDROZA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/23/2018 No Access for Inspection PETER FOLLING
Pre-Inspection 4/11/2018 Partial Inspection BRYAN MEYER
Pre-Inspection 11/14/2018 Approved BRYAN MEYER
Insulation 2/22/2019 Corrections Issued DAVID SANDOVAL
Insulation 2/28/2019 Partial Approval DAVID SANDOVAL
Insulation 3/5/2019 Partial Approval JOHN COLEMAN
Drywall Nailing 3/11/2019 Partial Approval JOHN JANSON
Drywall Nailing 4/15/2019 Not Ready for Inspection SEAN WIRCH
Shower Pan 4/15/2019 Corrections Issued SEAN WIRCH
PLUMBING-Rough 4/25/2019 No Access for Inspection JOHN COLEMAN
ELECTRICAL-Rough 5/7/2019 Not Ready for Inspection SEAN WIRCH
PLUMBING-Rough 5/7/2019 Not Ready for Inspection SEAN WIRCH
ELECTRICAL-Final 5/16/2019 Corrections Issued DAVID SANDOVAL
Rough-Elec/Plmb/HVAC 6/4/2019 Approved DAVID SANDOVAL
Drywall Nailing 6/17/2019 Approved SEAN WIRCH
ELECTRICAL-Final 6/17/2019 Not Ready for Inspection SEAN WIRCH
BUILDING-Rough-Frame 7/23/2019 Approved MICHAEL YOUNG
Final 7/23/2019 Corrections Issued MICHAEL YOUNG
SGSOV-Seismic Gas S/O Valve 7/23/2019 SGSOV Not Ready MICHAEL YOUNG
Smoke Detectors 7/23/2019 Approved MICHAEL YOUNG
Final 9/18/2019 Corrections Issued STEVEN BACK
SGSOV-Seismic Gas S/O Valve 9/18/2019 SGSOV Gas Company STEVEN BACK
Final 12/2/2019 Corrections Issued STEVEN BACK
Final 12/14/2019 Not Ready for Inspection JOSEPH SAGEN
Final 12/31/2019 Not Ready for Inspection STEVEN BACK
Final 1/30/2020 Corrections Issued STEVEN BACK
PLUMBING-Final 2/10/2020 Corrections Issued STEVEN BACK
Final 2/24/2020 Corrections Issued STEVEN BACK
Service/Power Release 2/24/2020 Not Ready for Inspection STEVEN BACK
Final 3/4/2020 OK to Issue CofO STEVEN BACK
SGSOV-Seismic Gas S/O Valve 3/4/2020 SGSOV Approved STEVEN BACK