7847 N VANTAGE AVE 91605
Certificate Information: 7847 N VANTAGE AVE 91605
- Application / Permit
- 17016-20000-26044
- Plan Check / Job No.
- B17VN13465
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER AB 2299 & SB 1069.
- Permit Issued
- Issued on 1/12/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/7/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 9/15/2017 | STANLEY RAAP |
| Corrections Issued | 9/15/2017 | STANLEY RAAP |
| Plan Check Approved | 1/10/2018 | MENA WASSEF |
| Issued | 1/12/2018 | LADBS |
| CofO in Progress | 5/10/2022 | CHRISTOPHER DELLEFIELD |
| CofO Issued | 8/11/2022 | MICHAEL SMITH |
| Permit Finaled | 8/11/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/9/2018 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/9/2018 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 1/9/2018 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/25/2018 | Approved | LEE HELLINGER |
| PLUMBING-Rough | 1/25/2018 | Partial Approval | LEE HELLINGER |
| BUILDING-Rough-Frame | 7/18/2018 | Not Ready for Inspection | PIERRE VEGA |
| Final | 7/18/2018 | Corrections Issued | PIERRE VEGA |
| Green Building Final | 7/18/2018 | Not Ready for Inspection | PIERRE VEGA |
| Green Building Rough | 7/18/2018 | Not Ready for Inspection | PIERRE VEGA |
| SGSOV-Seismic Gas S/O Valve | 7/18/2018 | SGSOV Not Ready | PIERRE VEGA |
| Smoke Detectors | 7/18/2018 | Not Ready for Inspection | PIERRE VEGA |
| BUILDING-Rough-Frame | 8/16/2018 | No Access for Inspection | PIERRE VEGA |
| Deck | 8/16/2018 | No Access for Inspection | PIERRE VEGA |
| Final | 8/16/2018 | No Access for Inspection | PIERRE VEGA |
| Green Building Final | 8/16/2018 | No Access for Inspection | PIERRE VEGA |
| Green Building Rough | 8/16/2018 | Not Ready for Inspection | PIERRE VEGA |
| SGSOV-Seismic Gas S/O Valve | 8/16/2018 | SGSOV Not Ready | PIERRE VEGA |
| Smoke Detectors | 8/16/2018 | No Access for Inspection | PIERRE VEGA |
| BUILDING-Rough-Frame | 8/31/2018 | Not Ready for Inspection | PIERRE VEGA |
| Deck | 8/31/2018 | Not Ready for Inspection | PIERRE VEGA |
| Final | 8/31/2018 | Not Ready for Inspection | PIERRE VEGA |
| Green Building Final | 8/31/2018 | Not Ready for Inspection | PIERRE VEGA |
| Green Building Rough | 8/31/2018 | Not Ready for Inspection | PIERRE VEGA |
| SGSOV-Seismic Gas S/O Valve | 8/31/2018 | SGSOV Not Ready | PIERRE VEGA |
| Smoke Detectors | 8/31/2018 | Not Ready for Inspection | PIERRE VEGA |
| Deck | 9/27/2018 | No Access for Inspection | PIERRE VEGA |
| BUILDING-Rough-Frame | 12/14/2018 | No Access for Inspection | PIERRE VEGA |
| Deck | 12/14/2018 | No Access for Inspection | PIERRE VEGA |
| Final | 12/14/2018 | No Access for Inspection | PIERRE VEGA |
| Green Building Final | 12/14/2018 | No Access for Inspection | PIERRE VEGA |
| Green Building Rough | 12/14/2018 | No Access for Inspection | PIERRE VEGA |
| SGSOV-Seismic Gas S/O Valve | 12/14/2018 | SGSOV Not Ready | PIERRE VEGA |
| Smoke Detectors | 12/14/2018 | No Access for Inspection | PIERRE VEGA |
| BUILDING-Rough-Frame | 1/7/2019 | No Access for Inspection | MICHAEL SMITH |
| Deck | 1/7/2019 | No Access for Inspection | MICHAEL SMITH |
| Final | 1/7/2019 | No Access for Inspection | MICHAEL SMITH |
| Green Building Final | 1/7/2019 | No Access for Inspection | MICHAEL SMITH |
| Green Building Rough | 1/7/2019 | No Access for Inspection | MICHAEL SMITH |
| SGSOV-Seismic Gas S/O Valve | 1/7/2019 | SGSOV Not Required | MICHAEL SMITH |
| Smoke Detectors | 1/7/2019 | No Access for Inspection | MICHAEL SMITH |
| Special/Order Compliance | 1/7/2019 | Not Ready for Inspection | PIERRE VEGA |
| BUILDING-Rough-Frame | 3/13/2019 | Corrections Issued | ROBERT MINASSIANS |
| BUILDING-Rough-Frame | 6/6/2019 | Corrections Issued | ROBERT MINASSIANS |
| ELECTRICAL-Rough | 6/6/2019 | Not Ready for Inspection | ROBERT MINASSIANS |
| Gas Test | 6/6/2019 | Not Ready for Inspection | ROBERT MINASSIANS |
| HVAC-Rough | 6/6/2019 | Corrections Issued | ROBERT MINASSIANS |
| PLUMBING-Rough | 6/6/2019 | Corrections Issued | ROBERT MINASSIANS |
| Special/Order Compliance | 6/6/2019 | Approved | JOHN HAYES |
| Special/Order Compliance | 6/26/2019 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 6/27/2019 | Corrections Issued | ROBERT MINASSIANS |
| Rough-Elec/Plmb/HVAC | 6/27/2019 | Corrections Issued | ROBERT MINASSIANS |
| Special/Order Compliance | 6/27/2019 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 2/18/2020 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 2/18/2020 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 2/18/2020 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 2/18/2020 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 2/28/2020 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 2/28/2020 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 2/28/2020 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 3/2/2020 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 3/2/2020 | Not Ready for Inspection | JOHN HAYES |
| Pre-Inspection | 3/2/2020 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 3/4/2020 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 3/4/2020 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 3/4/2020 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 3/6/2020 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 3/6/2020 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 3/6/2020 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 3/9/2020 | Not Ready for Inspection | PIERRE VEGA |
| Excavation/Setback/Form/Re-Bar | 3/9/2020 | Partial Approval | PIERRE VEGA |
| PLUMBING-Rough | 3/9/2020 | Not Ready for Inspection | PIERRE VEGA |
| BUILDING-Rough-Frame | 3/20/2020 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 3/20/2020 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 3/24/2020 | Partial Approval | BEAU COLLINS |
| ELECTRICAL-Rough | 4/10/2020 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 4/10/2020 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 4/10/2020 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 4/13/2020 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 4/13/2020 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 4/13/2020 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 4/14/2020 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2020 | Partial Approval | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 4/14/2020 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 4/30/2020 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 4/30/2020 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 4/30/2020 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 4/30/2020 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 5/6/2020 | Approved | JOHN HAYES |
| Green Building Rough | 5/6/2020 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 5/6/2020 | Approved | JOHN HAYES |
| Insulation | 5/7/2020 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 5/7/2020 | Approved | JOHN HAYES |
| Drywall Nailing | 5/15/2020 | Approved | GREGG CUMMINGS |
| Final | 9/23/2020 | Corrections Issued | MICHAEL TEMPLE |
| Green Building Final | 9/23/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Smoke Detectors | 9/23/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Final | 10/21/2020 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 10/21/2020 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 10/21/2020 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 10/29/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 10/29/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 10/29/2021 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 10/29/2021 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 10/29/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 10/29/2021 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 10/29/2021 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 11/3/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 11/3/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 11/3/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 5/2/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 5/2/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 5/2/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 5/4/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 5/6/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 5/10/2022 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |