5911 N WILBUR AVE 91356
Certificate Information: 5911 N WILBUR AVE 91356
- Application / Permit
- 17016-20000-25330
- Plan Check / Job No.
- B17VN13094
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- CONVERT (E) GARAGE INTO (N) RECREATION ROOM W/ HALF BATH & STORAGE; ADD CARPORT (24'-6" X 20')
- Permit Issued
- Issued on 1/10/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/31/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 9/21/2017 | NILOOFAR MEHRAIN |
| Green Plans Picked Up | 9/28/2017 | APPLICANT |
| Corrections Issued | 10/17/2017 | NILOOFAR MEHRAIN |
| Quality Review Completed | 10/17/2017 | GUANG MIN TUNG |
| Building Plans Picked Up | 10/20/2017 | APPLICANT |
| Applicant returned to address corrections | 11/14/2017 | NILOOFAR MEHRAIN |
| Plan Check Approved | 11/28/2017 | NILOOFAR MEHRAIN |
| Issued | 1/10/2018 | LADBS |
| CofO in Progress | 3/22/2022 | STEVEN BACK |
| Permit Finaled | 3/22/2022 | JOHN JANSON |
| CofO Issued | 3/22/2022 | JOHN JANSON |
| Permit Finaled | 3/22/2022 | JOHN JANSON |
Permit Application Clearance Information
| Green Code | Cleared | 11/9/2017 | MICKEY YAMASHITA |
| Hydrant and Access approval | Cleared | 11/9/2017 | JOHN DALLAS |
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2017 | RAVIL MANAPOV |
| Low Impact Development | Cleared | 11/21/2017 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 11/21/2017 | RAVIL MANAPOV |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 3/3/2020 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 3/3/2020 | Approved | STEVEN BACK |
| Green Building Rough | 3/3/2020 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Rough | 3/3/2020 | Approved | STEVEN BACK |
| PLUMBING-Rough | 3/3/2020 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 3/6/2020 | Approved | STEVEN BACK |
| Shower Pan | 3/6/2020 | Approved | STEVEN BACK |
| Insulation | 3/13/2020 | Approved | STEVEN BACK |
| Drywall Nailing | 3/19/2020 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 4/23/2020 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 4/23/2020 | Approved | STEVEN BACK |
| Final | 4/23/2020 | OK to Issue CofO | STEVEN BACK |
| Footing/Foundation/Slab | 4/23/2020 | Approved | STEVEN BACK |
| Green Building Final | 4/23/2020 | Approved | STEVEN BACK |
| Green Building Rough | 4/23/2020 | Approved | STEVEN BACK |
| HVAC-Final | 4/23/2020 | Approved | STEVEN BACK |
| PLUMBING-Final | 4/23/2020 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 4/23/2020 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 4/23/2020 | Approved | STEVEN BACK |