1544 S CANFIELD AVE 90035
Certificate Information: 1544 S CANFIELD AVE 90035
- Application / Permit
- 17016-20000-25195
- Plan Check / Job No.
- B17VN13031
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (20' X 21') (E) GARAGE & (20' X 20') (E) REC ROOM INTO ACCESSORY DWELLING UNIT PER AB 2299 AND SB 1069 PER WFPP
- Permit Issued
- Issued on 9/18/2017
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/30/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 8/31/2017 | RAPHAEL ROSAS |
| Corrections Issued | 9/1/2017 | RAPHAEL ROSAS |
| Quality Review Completed | 9/1/2017 | GUANG MIN TUNG |
| Building Plans Picked Up | 9/5/2017 | APPLICANT |
| Plan Check Approved | 9/18/2017 | RAPHAEL ROSAS |
| Issued | 9/18/2017 | LADBS |
| CofO in Progress | 3/8/2023 | DAVID FEILER |
| Permit Finaled | 3/15/2023 | DANIEL ORRANTE |
| CofO Issued | 3/15/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/15/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/7/2017 | KENNETH PHAM |
| Roof/Waste drainage to street | Cleared | 9/7/2017 | KENNETH PHAM |
| Sewer availability | Cleared | 9/7/2017 | KENNETH PHAM |
| CPC | Cleared | 9/11/2017 | DENNIS CHEW |
| CPC | Cleared | 9/11/2017 | DENNIS CHEW |
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2017 | EDUARDO PEDROZA |
| Grading Pre-Inspection | Cleared | 9/18/2017 | RAPHAEL ROSAS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/12/2017 | Partial Inspection | ROBERT VORHIS |
| Pre-Inspection | 10/16/2017 | Partial Inspection | ROBERT VORHIS |
| PLUMBING-Rough | 7/10/2020 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 1/13/2021 | Approved | EVAN COOPER |
| PLUMBING-Rough | 1/13/2021 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 2/12/2021 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 2/12/2021 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 2/12/2021 | Corrections Issued | EVAN COOPER |
| METHANE-Rough | 2/12/2021 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 2/18/2021 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 2/18/2021 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 2/18/2021 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2021 | Corrections Issued | EVAN COOPER |
| Green Building Rough | 3/3/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 3/3/2021 | Partial Approval | EVAN COOPER |
| Insulation | 3/11/2021 | Approved | EVAN COOPER |
| Drywall Nailing | 3/24/2021 | Conditional Approval | KEVIN SARGSYAN |
| Sewer | 6/9/2021 | Approved | EVAN COOPER |
| Underground Mechanical | 6/9/2021 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 3/7/2023 | Approved | JEREMY TODD |
| Drywall Nailing | 3/7/2023 | Approved | JEREMY TODD |
| ELECTRICAL-Final | 3/7/2023 | Approved | JEREMY TODD |
| Final | 3/7/2023 | OK to Issue CofO | JEREMY TODD |
| Green Building Final | 3/7/2023 | Approved | JEREMY TODD |
| HVAC-Final | 3/7/2023 | Approved | JEREMY TODD |
| PLUMBING-Final | 3/7/2023 | Approved | JEREMY TODD |
| SGSOV-Seismic Gas S/O Valve | 3/7/2023 | SGSOV Approved | JEREMY TODD |
| Smoke Detectors | 3/7/2023 | Approved | JEREMY TODD |