5309 N DON PIO DR 91364
Certificate Information: 5309 N DON PIO DR 91364
- Application / Permit
- 17016-20000-23592
- Plan Check / Job No.
- B17VN12165
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER AB 2299 AND SB 1069.
- Permit Issued
- Issued on 9/20/2017
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/5/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/16/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2017 | SIAVOSH POURSABAHIAN |
| Corrections Issued | 8/16/2017 | STANLEY RAAP |
| Applicant returned to address corrections | 8/31/2017 | ALDOUS CHIC |
| Plan Check Approved | 9/20/2017 | TROY DEGUZMAN |
| Issued | 9/20/2017 | LADBS |
| CofO in Progress | 5/14/2019 | JOSEPH SAGEN |
| Permit Finaled | 8/5/2020 | DONALD SUNSERI |
| CofO Issued | 8/5/2020 | DONALD SUNSERI |
| Permit Finaled | 8/5/2020 | DONALD SUNSERI |
Permit Application Clearance Information
| Address approval | Cleared | 8/16/2017 | JOSEPH RHYU |
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2017 | JOSEPH RHYU |
| Grading Pre-Inspection | Cleared | 8/16/2017 | STANLEY RAAP |
| Sewer availability | Cleared | 8/16/2017 | JOSEPH RHYU |
| Construction near power lines | Cleared | 9/18/2017 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 9/25/2017 | Not Ready for Inspection | MICHAEL TEMPLE |
| Final | 9/25/2017 | Not Ready for Inspection | MICHAEL TEMPLE |
| Green Building Final | 9/25/2017 | Not Ready for Inspection | MICHAEL TEMPLE |
| Green Building Rough | 9/25/2017 | Not Ready for Inspection | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 9/25/2017 | SGSOV Not Ready | MICHAEL TEMPLE |
| Smoke Detectors | 9/25/2017 | Not Ready for Inspection | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 9/28/2017 | Corrections Issued | JOHN COLEMAN |
| Final | 9/28/2017 | Not Ready for Inspection | JOHN COLEMAN |
| Green Building Final | 9/28/2017 | Not Ready for Inspection | JOHN COLEMAN |
| Green Building Rough | 9/28/2017 | Not Ready for Inspection | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 9/28/2017 | SGSOV Not Ready | JOHN COLEMAN |
| Smoke Detectors | 9/28/2017 | Not Ready for Inspection | JOHN COLEMAN |
| BUILDING-Rough-Frame | 11/19/2018 | Corrections Issued | JOHN COLEMAN |
| Final | 11/19/2018 | Not Ready for Inspection | JOHN COLEMAN |
| Green Building Final | 11/19/2018 | Not Ready for Inspection | JOHN COLEMAN |
| Green Building Rough | 11/19/2018 | Not Ready for Inspection | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 11/19/2018 | SGSOV Not Ready | JOHN COLEMAN |
| Smoke Detectors | 11/19/2018 | Approved | JOHN COLEMAN |
| ELECTRICAL-Final | 4/5/2019 | Not Ready for Inspection | JOSEPH SAGEN |
| PLUMBING-Final | 4/5/2019 | Not Ready for Inspection | JOSEPH SAGEN |
| ELECTRICAL-Final | 4/26/2019 | Approved | JOSEPH SAGEN |
| Footing/Foundation/Slab | 4/26/2019 | Approved | JOSEPH SAGEN |
| PLUMBING-Final | 4/26/2019 | Not Ready for Inspection | JOSEPH SAGEN |
| BUILDING-Rough-Frame | 5/13/2019 | Approved | JOSEPH SAGEN |
| Final | 5/13/2019 | OK to Issue CofO | JOSEPH SAGEN |
| Green Building Final | 5/13/2019 | Approved | JOSEPH SAGEN |
| Green Building Rough | 5/13/2019 | Approved | JOSEPH SAGEN |
| HVAC-Final | 5/13/2019 | Approved | JOSEPH SAGEN |
| PLUMBING-Final | 5/13/2019 | Approved | JOSEPH SAGEN |
| SGSOV-Seismic Gas S/O Valve | 5/13/2019 | SGSOV Approved | JOSEPH SAGEN |