1325-1329 E PALMETTO ST 90013

Certificate Information: 1325-1329 E PALMETTO ST 90013

Application / Permit
17016-20000-18429
Plan Check / Job No.
B17VN09858
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
COMBINE TWO CONTIGUOUS BUILDINGS TO BE ONE BUILDING AND CHANGE OF USE FROM WAREHOUSE, LAUNDRY MAT TO OFFICE AT 1ST & 2ND FLOOR OF (E) TWO STORY WAREHOUSE. INTERIOR TENANT IMPROVEMENT TO ADD NEW BATHROOMS AT 1ST & 2ND FLOORS. ADD TWOSTAIRWAYS AND STAIR ENCLOSURE. NEW RAMP - SEE COMMENTS
Permit Issued
Issued on 9/19/2017
Issuing Office
Metro
Current Status
CofO Issued on 7/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/6/2017 APPLICANT
Assigned to Plan Check Engineer 7/13/2017 MOURAD AZIZ
Corrections Issued 7/18/2017 MOURAD AZIZ
Quality Review Completed 7/18/2017 GUANG MIN TUNG
Building Plans Picked Up 7/25/2017 APPLICANT
Disabled Access Plans Picked Up 7/25/2017 APPLICANT
Applicant returned to address corrections 8/21/2017 MOURAD AZIZ
Plan Check Approved 9/11/2017 MOURAD AZIZ
Issued 9/19/2017 LADBS
CofO in Progress 7/13/2021 LANNY MERRICK
CofO Issued 7/20/2021 ERNESTO CORRAL
Permit Finaled 7/20/2021 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 8/21/2017 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/21/2017 LEE GUILBEAUX
Sewer availability Cleared 8/21/2017 LEE GUILBEAUX
DAS Clearance Cleared 8/25/2017 MOURAD AZIZ

Contact Information

Architect El, Bayar Sami M; Lic. No.: C26080 22834 BRENFORD STREET      WOODLAND HILLS, CA 91364
Contractor Casey'S Custom Construction; Lic. No.: 553222-B 5169 OCEAN VIEW BLVD      LA CANADA, CA 91011
Engineer Tan, Charles; Lic. No.: S4758 3161 DRIGGS AVENUE      ROSEMEAD, CA 91770

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/28/2017 Partial Inspection ERNESTO CORRAL
Reinforced Concrete Frame 1/16/2018 Approved FELIX CEBALLOS
Deputy Drilled-In Anchors 2/8/2018 Partial Approval FELIX CEBALLOS
Footing/Foundation/Slab 2/12/2018 Partial Inspection ERNESTO CORRAL
Deputy Drilled-In Anchors 3/27/2018 Partial Approval FELIX CEBALLOS
Reinforced Concrete Frame 3/28/2018 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 4/11/2018 Partial Approval FELIX CEBALLOS
METHANE-Rough 4/11/2018 Partial Approval FELIX CEBALLOS
Drywall Nailing 4/17/2018 Partial Approval FELIX CEBALLOS
Wood Frame 5/15/2018 Approved ERNESTO CORRAL
Drywall Nailing 5/25/2018 Partial Approval FELIX CEBALLOS
Drywall Nailing 5/29/2018 Partial Inspection ERNESTO CORRAL
Special/Order Compliance 5/29/2018 Approved ERNESTO CORRAL
Wood Frame 6/15/2018 Not Ready for Inspection FELIX CEBALLOS
Pre-Inspection 10/11/2018 Approved ERNESTO CORRAL
Drywall Nailing 3/20/2020 Not Ready for Inspection RONALD PACHECO
Drywall Nailing 3/23/2020 Not Ready for Inspection RONALD PACHECO
Final 6/9/2020 Not Ready for Inspection RONALD PACHECO
METHANE-Final 6/9/2020 Not Ready for Inspection RONALD PACHECO
METHANE-Rough 6/9/2020 Not Ready for Inspection RONALD PACHECO
Reinforced Masonry Frame 6/9/2020 Not Ready for Inspection RONALD PACHECO
SGSOV-Seismic Gas S/O Valve 6/9/2020 SGSOV Not Ready RONALD PACHECO
Smoke Detectors 6/9/2020 Not Ready for Inspection RONALD PACHECO
Special/Order Compliance 6/9/2020 Not Ready for Inspection RONALD PACHECO
Final 7/31/2020 Not Ready for Inspection LANNY MERRICK
METHANE-Final 7/31/2020 Not Ready for Inspection LANNY MERRICK
METHANE-Rough 7/31/2020 Not Ready for Inspection LANNY MERRICK
Reinforced Masonry Frame 7/31/2020 Not Ready for Inspection LANNY MERRICK
SGSOV-Seismic Gas S/O Valve 7/31/2020 SGSOV Approved LANNY MERRICK
Smoke Detectors 7/31/2020 Partial Inspection LANNY MERRICK
Final 8/11/2020 Not Ready for Inspection LANNY MERRICK
METHANE-Final 8/11/2020 Approved LANNY MERRICK
METHANE-Rough 8/11/2020 Not Ready for Inspection LANNY MERRICK
Reinforced Masonry Frame 8/11/2020 Not Ready for Inspection LANNY MERRICK
Smoke Detectors 8/11/2020 Approved LANNY MERRICK
Final 12/8/2020 Not Ready for Inspection LANNY MERRICK
Reinforced Masonry Frame 12/8/2020 Not Ready for Inspection LANNY MERRICK
Final 4/9/2021 Not Ready for Inspection RONALD PACHECO
Reinforced Masonry Frame 4/9/2021 Not Ready for Inspection RONALD PACHECO
Final 6/2/2021 Partial Approval LANNY MERRICK
Reinforced Masonry Frame 6/2/2021 Approved LANNY MERRICK
Special/Order Compliance 6/4/2021 Not Ready for Inspection LANNY MERRICK
Final 6/16/2021 Conditional Approval JONATHAN QUACH
Final 6/21/2021 Not Ready for Inspection LANNY MERRICK
Special/Order Compliance 6/21/2021 Partial Inspection LANNY MERRICK
Special/Order Compliance 6/23/2021 Not Ready for Inspection LANNY MERRICK
Final 6/30/2021 Not Ready for Inspection LANNY MERRICK
Final 7/15/2021 Partial Approval LANNY MERRICK