1325-1329 E PALMETTO ST 90013
Certificate Information: 1325-1329 E PALMETTO ST 90013
- Application / Permit
- 17016-20000-18429
- Plan Check / Job No.
- B17VN09858
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- COMBINE TWO CONTIGUOUS BUILDINGS TO BE ONE BUILDING AND CHANGE OF USE FROM WAREHOUSE, LAUNDRY MAT TO OFFICE AT 1ST & 2ND FLOOR OF (E) TWO STORY WAREHOUSE. INTERIOR TENANT IMPROVEMENT TO ADD NEW BATHROOMS AT 1ST & 2ND FLOORS. ADD TWOSTAIRWAYS AND STAIR ENCLOSURE. NEW RAMP - SEE COMMENTS
- Permit Issued
- Issued on 9/19/2017
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/20/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/6/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2017 | MOURAD AZIZ |
| Corrections Issued | 7/18/2017 | MOURAD AZIZ |
| Quality Review Completed | 7/18/2017 | GUANG MIN TUNG |
| Building Plans Picked Up | 7/25/2017 | APPLICANT |
| Disabled Access Plans Picked Up | 7/25/2017 | APPLICANT |
| Applicant returned to address corrections | 8/21/2017 | MOURAD AZIZ |
| Plan Check Approved | 9/11/2017 | MOURAD AZIZ |
| Issued | 9/19/2017 | LADBS |
| CofO in Progress | 7/13/2021 | LANNY MERRICK |
| CofO Issued | 7/20/2021 | ERNESTO CORRAL |
| Permit Finaled | 7/20/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 8/21/2017 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2017 | LEE GUILBEAUX |
| Sewer availability | Cleared | 8/21/2017 | LEE GUILBEAUX |
| DAS Clearance | Cleared | 8/25/2017 | MOURAD AZIZ |
Contact Information
| Architect | El, Bayar Sami M; Lic. No.: C26080 | 22834 BRENFORD STREET WOODLAND HILLS, CA 91364 |
| Contractor | Casey'S Custom Construction; Lic. No.: 553222-B | 5169 OCEAN VIEW BLVD LA CANADA, CA 91011 |
| Engineer | Tan, Charles; Lic. No.: S4758 | 3161 DRIGGS AVENUE ROSEMEAD, CA 91770 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/28/2017 | Partial Inspection | ERNESTO CORRAL |
| Reinforced Concrete Frame | 1/16/2018 | Approved | FELIX CEBALLOS |
| Deputy Drilled-In Anchors | 2/8/2018 | Partial Approval | FELIX CEBALLOS |
| Footing/Foundation/Slab | 2/12/2018 | Partial Inspection | ERNESTO CORRAL |
| Deputy Drilled-In Anchors | 3/27/2018 | Partial Approval | FELIX CEBALLOS |
| Reinforced Concrete Frame | 3/28/2018 | Partial Inspection | ERNESTO CORRAL |
| Light Gage Steel Frame | 4/11/2018 | Partial Approval | FELIX CEBALLOS |
| METHANE-Rough | 4/11/2018 | Partial Approval | FELIX CEBALLOS |
| Drywall Nailing | 4/17/2018 | Partial Approval | FELIX CEBALLOS |
| Wood Frame | 5/15/2018 | Approved | ERNESTO CORRAL |
| Drywall Nailing | 5/25/2018 | Partial Approval | FELIX CEBALLOS |
| Drywall Nailing | 5/29/2018 | Partial Inspection | ERNESTO CORRAL |
| Special/Order Compliance | 5/29/2018 | Approved | ERNESTO CORRAL |
| Wood Frame | 6/15/2018 | Not Ready for Inspection | FELIX CEBALLOS |
| Pre-Inspection | 10/11/2018 | Approved | ERNESTO CORRAL |
| Drywall Nailing | 3/20/2020 | Not Ready for Inspection | RONALD PACHECO |
| Drywall Nailing | 3/23/2020 | Not Ready for Inspection | RONALD PACHECO |
| Final | 6/9/2020 | Not Ready for Inspection | RONALD PACHECO |
| METHANE-Final | 6/9/2020 | Not Ready for Inspection | RONALD PACHECO |
| METHANE-Rough | 6/9/2020 | Not Ready for Inspection | RONALD PACHECO |
| Reinforced Masonry Frame | 6/9/2020 | Not Ready for Inspection | RONALD PACHECO |
| SGSOV-Seismic Gas S/O Valve | 6/9/2020 | SGSOV Not Ready | RONALD PACHECO |
| Smoke Detectors | 6/9/2020 | Not Ready for Inspection | RONALD PACHECO |
| Special/Order Compliance | 6/9/2020 | Not Ready for Inspection | RONALD PACHECO |
| Final | 7/31/2020 | Not Ready for Inspection | LANNY MERRICK |
| METHANE-Final | 7/31/2020 | Not Ready for Inspection | LANNY MERRICK |
| METHANE-Rough | 7/31/2020 | Not Ready for Inspection | LANNY MERRICK |
| Reinforced Masonry Frame | 7/31/2020 | Not Ready for Inspection | LANNY MERRICK |
| SGSOV-Seismic Gas S/O Valve | 7/31/2020 | SGSOV Approved | LANNY MERRICK |
| Smoke Detectors | 7/31/2020 | Partial Inspection | LANNY MERRICK |
| Final | 8/11/2020 | Not Ready for Inspection | LANNY MERRICK |
| METHANE-Final | 8/11/2020 | Approved | LANNY MERRICK |
| METHANE-Rough | 8/11/2020 | Not Ready for Inspection | LANNY MERRICK |
| Reinforced Masonry Frame | 8/11/2020 | Not Ready for Inspection | LANNY MERRICK |
| Smoke Detectors | 8/11/2020 | Approved | LANNY MERRICK |
| Final | 12/8/2020 | Not Ready for Inspection | LANNY MERRICK |
| Reinforced Masonry Frame | 12/8/2020 | Not Ready for Inspection | LANNY MERRICK |
| Final | 4/9/2021 | Not Ready for Inspection | RONALD PACHECO |
| Reinforced Masonry Frame | 4/9/2021 | Not Ready for Inspection | RONALD PACHECO |
| Final | 6/2/2021 | Partial Approval | LANNY MERRICK |
| Reinforced Masonry Frame | 6/2/2021 | Approved | LANNY MERRICK |
| Special/Order Compliance | 6/4/2021 | Not Ready for Inspection | LANNY MERRICK |
| Final | 6/16/2021 | Conditional Approval | JONATHAN QUACH |
| Final | 6/21/2021 | Not Ready for Inspection | LANNY MERRICK |
| Special/Order Compliance | 6/21/2021 | Partial Inspection | LANNY MERRICK |
| Special/Order Compliance | 6/23/2021 | Not Ready for Inspection | LANNY MERRICK |
| Final | 6/30/2021 | Not Ready for Inspection | LANNY MERRICK |
| Final | 7/15/2021 | Partial Approval | LANNY MERRICK |