1133 S CLARK DR 90035
Certificate Information: 1133 S CLARK DR 90035
- Application / Permit
- 17016-20000-09756
- Plan Check / Job No.
- B17VN05382
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION AND CONVERT (E) 16' x 18' DET. GARAGE TO AN ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 . COMPLY WITH DEPARTMENT ORDER effective date 11/01/2016. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 7/17/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/18/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/18/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2017 | SIAVOSH POURSABAHIAN |
| Corrections Issued | 4/18/2017 | JEFFREY TANGONAN |
| Applicant returned to address corrections | 5/11/2017 | CHRISTOPHER KOMANCHECK |
| Applicant returned to address corrections | 5/18/2017 | SAM CHANG |
| Applicant returned to address corrections | 12/13/2017 | JAYDON NGUYEN |
| Applicant returned to address corrections | 5/8/2018 | PRANITA SHAH |
| Plan Check Approved | 7/11/2018 | YAQUB MIRZA |
| Issued | 7/17/2018 | LADBS |
| CofO in Progress | 4/12/2022 | JOEL WILLIAMS |
| Permit Finaled | 4/18/2022 | DANIEL SANCHEZ |
| CofO Issued | 4/18/2022 | DANIEL SANCHEZ |
| Permit Finaled | 4/18/2022 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 5/3/2017 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 5/3/2017 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 5/3/2017 | CELINA MORENO |
| Sewer availability | Cleared | 5/3/2017 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 6/28/2017 | PATRICK MISCHLICH |
| Roof/Waste drainage to street | Cleared | 10/17/2017 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 10/17/2017 | MARKOS PEREZ-BRAN |
| CPC | Cleared | 6/19/2018 | EDBER MACEDO |
| CPC | Cleared | 6/19/2018 | EDBER MACEDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rahman, Moksudur; Lic. No.: C69263 | 14616 MCKENDREE AVE CHINO, CA 91708 |
Inspector Information
| PETER RUBIO, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN TCHANG, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| RYAN TAGUINES, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/23/2018 | Not Ready for Inspection | JOHN MATTILLO |
| BUILDING-Rough-Frame | 8/5/2019 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Final | 8/5/2019 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 8/5/2019 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Green Building Final | 8/5/2019 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Green Building Rough | 8/5/2019 | Not Ready for Inspection | ARTHUR SARGSYAN |
| METHANE-Barrier | 8/5/2019 | Not Ready for Inspection | ARTHUR SARGSYAN |
| METHANE-Final | 8/5/2019 | Not Ready for Inspection | ARTHUR SARGSYAN |
| METHANE-Rough | 8/5/2019 | Not Ready for Inspection | ARTHUR SARGSYAN |
| METHANE-Subgrade | 8/5/2019 | Not Ready for Inspection | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 8/5/2019 | SGSOV Not Ready | ARTHUR SARGSYAN |
| Smoke Detectors | 8/5/2019 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Special/Order Compliance | 3/10/2021 | Corrections Issued | JUSTIN CURTIS |
| BUILDING-Rough-Frame | 10/1/2021 | Corrections Issued | PATRICK QUALEY |
| ELECTRICAL-Final | 10/1/2021 | Corrections Issued | PATRICK QUALEY |
| Final | 10/1/2021 | Corrections Issued | PATRICK QUALEY |
| Footing/Foundation/Slab | 10/1/2021 | Corrections Issued | PATRICK QUALEY |
| Green Building Final | 10/1/2021 | Corrections Issued | PATRICK QUALEY |
| Green Building Rough | 10/1/2021 | Approved | PATRICK QUALEY |
| Interior/Exterior Lathing | 10/1/2021 | Corrections Issued | PATRICK QUALEY |
| METHANE-Barrier | 10/1/2021 | Approved | PATRICK QUALEY |
| METHANE-Final | 10/1/2021 | Approved | PATRICK QUALEY |
| METHANE-Rough | 10/1/2021 | Approved | PATRICK QUALEY |
| METHANE-Subgrade | 10/1/2021 | Approved | PATRICK QUALEY |
| PLUMBING-Final | 10/1/2021 | Corrections Issued | PATRICK QUALEY |
| SGSOV-Seismic Gas S/O Valve | 10/1/2021 | SGSOV Approved | PATRICK QUALEY |
| Shower Pan | 10/1/2021 | Corrections Issued | PATRICK QUALEY |
| Smoke Detectors | 10/1/2021 | Corrections Issued | PATRICK QUALEY |
| BUILDING-Rough-Frame | 1/11/2022 | Corrections Issued | PATRICK QUALEY |
| ELECTRICAL-Final | 1/11/2022 | Approved | PATRICK QUALEY |
| Final | 1/11/2022 | Corrections Issued | PATRICK QUALEY |
| Footing/Foundation/Slab | 1/11/2022 | Corrections Issued | PATRICK QUALEY |
| Green Building Final | 1/11/2022 | Approved | PATRICK QUALEY |
| Smoke Detectors | 1/11/2022 | Corrections Issued | PATRICK QUALEY |
| Special/Order Compliance | 1/12/2022 | Partial Inspection | PATRICK QUALEY |
| BUILDING-Rough-Frame | 2/3/2022 | Approved | PATRICK QUALEY |
| Final | 2/3/2022 | Corrections Issued | PATRICK QUALEY |
| Footing/Foundation/Slab | 2/3/2022 | Approved | PATRICK QUALEY |
| Smoke Detectors | 2/3/2022 | Approved | PATRICK QUALEY |
| Final | 4/12/2022 | OK to Issue CofO | JOEL WILLIAMS |