14411 W VANOWEN ST 91405

Certificate Information: 14411 W VANOWEN ST 91405

Application / Permit
17016-20000-08446
Plan Check / Job No.
B17VN04706
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CHANGE OF USE FROM OFFICE TO APARTMENT HOUSE PER ZA-2018-3223-ZV-ZAA. RE-STRIPE PARKING LOT.
Permit Issued
Issued on 3/19/2021
Issuing Office
Current Status
Issued on 3/19/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/5/2017 APPLICANT
Disabled Access Plans Picked Up 4/13/2017 APPLICANT
Assigned to Plan Check Engineer 4/27/2017 ALBERT SERVIN
Corrections Issued 5/1/2017 RUDOLF KINAR MELIKOFF
Quality Review Completed 5/4/2017 TIEN JEN WANG
Building Plans Picked Up 5/8/2017 APPLICANT
Applicant returned to address corrections 8/7/2017 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 8/18/2017 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 11/13/2017 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 7/15/2019 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 9/11/2019 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 11/9/2020 ALBERT SERVIN
Plan Check Approved 11/13/2020 ALBERT SERVIN
Issued 3/19/2021 APPLICANT
TCO Issued (Expire Date: 02-14-2026) 8/18/2025 RICKEY JACKSON
TCO Issued (Expire Date: 08-09-2026) 2/10/2026 JEFFREY DURAN

Permit Application Clearance Information

Address approval Cleared 7/25/2017 HOWARD COOPER
Eng Process Fee Ord 176,300 Cleared 7/25/2017 JOHN LIN
Hydrant and Access approval Cleared 7/25/2017 JOHN DALLAS
ZA Case Cleared 7/25/2017 DAISY BENICIA
Fire Marshall Fire Life Safety Cleared 8/2/2017 MENOA AGHAJANI
Highway dedication Cleared 8/24/2017 LEE GUILBEAUX
Prkng lot landscape/Water mgmt Cleared 8/28/2017 DENNIS CHEW
Miscellaneous Cleared 10/25/2017 MARC WOERSCHING
Opn space landscape/Water mgmt Cleared 10/31/2017 DENNIS CHEW
ZA Case Cleared 10/31/2017 DENNIS CHEW
DAS Clearance Cleared 8/29/2019 RUDOLF KINAR MELIKOFF
Permit Cleared 8/29/2019 GABRIEL ROBLES
Green Code Cleared 2/18/2020 MICHAEL AYERS
Miscellaneous Cleared 4/27/2020 MARITZA PRZEKOP
ZA Case Cleared 4/27/2020 MARITZA PRZEKOP
Sewer availability Cleared 11/10/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Medina,, Ferdinand Casaclang; Lic. No.: C88007 1051 S HOLT AVE APT F      LOS ANGELES, CA 90035

Inspector Information

SEAN GRIFFITH, (818) 374-1102 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/18/2021 Partial Approval HAMID PISHEHVAR
Wood Frame 9/3/2021 Not Ready for Inspection CAMERON CHABAN
Green Building Rough 4/20/2022 Not Ready for Inspection CAMERON CHABAN
Wood Frame 4/20/2022 Not Ready for Inspection CAMERON CHABAN
Green Building Rough 7/29/2022 Not Ready for Inspection JEFFREY FULTON
Pre-Inspection 7/29/2022 Partial Inspection JEFFREY FULTON
Wood Frame 7/29/2022 Corrections Issued JEFFREY FULTON
Green Building Rough 9/9/2022 Not Ready for Inspection CAMERON CHABAN
Wood Frame 9/9/2022 Not Ready for Inspection CAMERON CHABAN
Green Building Rough 9/16/2022 Not Ready for Inspection CAMERON CHABAN
Wood Frame 9/16/2022 Not Ready for Inspection CAMERON CHABAN
Green Building Rough 9/20/2022 Not Ready for Inspection ANDREW DORSO
Wood Frame 9/20/2022 Corrections Issued ANDREW DORSO
Green Building Rough 10/13/2022 Not Ready for Inspection JEFFREY DURAN
Wood Frame 10/13/2022 Corrections Issued JEFFREY DURAN
Green Building Rough 10/20/2022 Approved CAMERON CHABAN
Wood Frame 10/20/2022 Conditional Approval CAMERON CHABAN
Insulation 11/15/2022 Partial Approval DANIEL VARNUM
Wood Frame 5/12/2023 Partial Approval STEVEN LEVITT
Insulation 7/28/2023 Approved STEVEN LEVITT
Drywall Nailing 8/3/2023 Partial Approval STEVEN LEVITT
Drywall Nailing 8/9/2023 Partial Approval KENNETH ROBERTS
Interior/Exterior Lathing 9/27/2023 Corrections Issued STEVEN LEVITT
Interior/Exterior Lathing 9/29/2023 Approved STEVEN LEVITT
Footing/Foundation/Slab 2/20/2024 Approved STEVEN LEVITT
Footing/Foundation/Slab 2/28/2024 Partial Approval STEVEN LEVITT
Drywall Nailing 5/28/2024 Not Ready for Inspection STEVEN LEVITT
Final 5/28/2024 Not Ready for Inspection STEVEN LEVITT
Green Building Final 5/28/2024 Not Ready for Inspection STEVEN LEVITT
SGSOV-Seismic Gas S/O Valve 5/28/2024 SGSOV Not Ready STEVEN LEVITT
Smoke Detectors 5/28/2024 Not Ready for Inspection STEVEN LEVITT
Wood Frame 5/28/2024 Not Ready for Inspection STEVEN LEVITT
Pre-Inspection 3/25/2025 Partial Inspection DEANDRE HOFFMAN
Excavation/Setback/Form/Re-Bar 4/28/2025 Not Ready for Inspection ANDREW DORSO
Reinforced Concrete Frame 4/28/2025 Not Ready for Inspection ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 4/28/2025 SGSOV Not Ready ANDREW DORSO
Footing/Foundation/Slab 4/29/2025 Not Ready for Inspection DEANDRE HOFFMAN
Masonry Wall/Backfill 4/29/2025 Not Ready for Inspection DEANDRE HOFFMAN
Interior/Exterior Lathing 6/6/2025 Partial Approval DANIEL VARNUM
Drywall Nailing 6/13/2025 Approved DEANDRE HOFFMAN
Final 6/13/2025 Not Ready for Inspection DEANDRE HOFFMAN
Green Building Final 6/13/2025 Not Ready for Inspection DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 6/13/2025 SGSOV Not Ready DEANDRE HOFFMAN
Smoke Detectors 6/13/2025 Not Ready for Inspection DEANDRE HOFFMAN
Wood Frame 6/13/2025 Approved DEANDRE HOFFMAN
Special/Order Compliance 6/24/2025 Partial Inspection ANDREW DORSO
Pre-Inspection 7/16/2025 Partial Inspection ANDREW DORSO
Final 7/31/2025 Partial Inspection ANDREW DORSO
Green Building Final 7/31/2025 Approved ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 7/31/2025 SGSOV Approved ANDREW DORSO
Smoke Detectors 7/31/2025 Not Ready for Inspection ANDREW DORSO
Final 8/15/2025 OK for TCO ANDREW DORSO
Smoke Detectors 8/15/2025 Approved ANDREW DORSO
Special/Order Compliance 1/27/2026 Conditional Approval ANDREW DORSO