12827 W RANGOON ST 91331

Certificate Information: 12827 W RANGOON ST 91331

Application / Permit
17016-20000-06971
Plan Check / Job No.
B17VN03984
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(12) Manufacturing
Work Description
CHANGE OF USE AND TENANT IMPROVEMENT TO EXISTING MANUFACTURING BUILDING TO CONVERT TO WAREHOUSE FOR HIGH HAZARD CHEMICAL STORGAE AND DISTIBUTION.
Permit Issued
Issued on 4/4/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 11/20/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/23/2017 APPLICANT
Disabled Access Plans Picked Up 4/6/2017 APPLICANT
Assigned to Plan Check Engineer 4/13/2017 KAMRAN GHOTBI RAVANDI
Corrections Issued 4/17/2017 KAMRAN GHOTBI RAVANDI
Quality Review Completed 4/21/2017 TIEN JEN WANG
Building Plans Picked Up 4/25/2017 APPLICANT
Applicant returned to address corrections 7/11/2017 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 7/21/2017 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 8/24/2017 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 8/29/2017 KAMRAN GHOTBI RAVANDI
Plan Check Approved 9/14/2017 KAMRAN GHOTBI RAVANDI
Issued 4/4/2019 LADBS
CofO in Progress 11/19/2024 ANDREW DORSO
Permit Finaled 11/20/2024 JEFFREY DURAN
CofO Issued 11/20/2024 JEFFREY DURAN
Permit Finaled 11/20/2024 JEFFREY DURAN

Permit Application Clearance Information

"Q" conditions Cleared 7/5/2017 STEVEN WECHSLER
Miscellaneous Cleared 7/5/2017 STEVEN WECHSLER
ZA Case Cleared 7/5/2017 STEVEN WECHSLER
DAS Clearance Cleared 8/23/2017 NORLITO MEDRANO
Fire Marshall Fire Life Safety Cleared 8/23/2017 OSCAR SALGADO JR
Eng Process Fee Ord 176,300 Cleared 8/24/2017 KENNETH PHAM
Sewer availability Cleared 8/24/2017 KENNETH PHAM

Contact Information

Contractor Gibson Construction; Lic. No.: 451517-B 28383 HAWKS RIDGE DRIVE      CANYON COUNTRY, CA 91351
Engineer Yaghi, Shucri Ibrahim; Lic. No.: C43205 112 E CHAPMAN AVE STE D      ORANGE, CA 92866

Inspector Information

ANDREW DORSO, (818) 374-7520 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/30/2019 Partial Inspection ANDREW DORSO
Pre-Inspection 4/30/2019 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 5/30/2019 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 6/12/2019 Partial Inspection ANDREW DORSO
Deputy Drilled-In Anchors 6/13/2019 Conditional Approval ANDREW DORSO
Footing/Foundation/Slab 6/17/2019 Partial Inspection ANDREW DORSO
Light Gage Steel Frame 6/20/2019 Approved ANDREW DORSO
Drywall Nailing 6/24/2019 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 6/24/2019 Partial Inspection ANDREW DORSO
Drywall Nailing 7/3/2019 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 7/8/2019 Corrections Issued ANDREW DORSO
Excavation/Setback/Form/Re-Bar 7/25/2019 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 8/5/2019 Partial Approval ROBERT DAVIS
Wood Frame 8/7/2019 Not Ready for Inspection ANDREW DORSO
Footing/Foundation/Slab 8/16/2019 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 8/23/2019 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 10/4/2019 Partial Inspection ANDREW DORSO
Pre-Inspection 10/23/2019 Corrections Issued ANDREW DORSO
Wood Frame 10/24/2019 Not Ready for Inspection ANDREW DORSO
Wood Frame 11/4/2019 Partial Inspection ANDREW DORSO
Drywall Nailing 11/12/2019 Partial Inspection ANDREW DORSO
Deputy Steel/Welding 7/24/2020 Conditional Approval ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 7/27/2020 SGSOV Not Ready RONALD PACHECO
Final 10/8/2021 Corrections Issued ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 10/8/2021 SGSOV Not Ready ANDREW DORSO
Smoke Detectors 10/8/2021 Not Ready for Inspection ANDREW DORSO
Wood Frame 10/8/2021 Approved ANDREW DORSO
Final 4/26/2023 Not Ready for Inspection ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 4/26/2023 SGSOV Approved ANDREW DORSO
Smoke Detectors 4/26/2023 Not Ready for Inspection ANDREW DORSO
Final 5/30/2023 Not Ready for Inspection ANDREW DORSO
Smoke Detectors 5/30/2023 Not Ready for Inspection ANDREW DORSO
Final 6/5/2023 Not Ready for Inspection ANDREW DORSO
Smoke Detectors 6/5/2023 Not Ready for Inspection ANDREW DORSO
Final 7/3/2023 Not Ready for Inspection ROBERT DAVIS
Smoke Detectors 7/3/2023 No Access for Inspection ROBERT DAVIS
Final 9/25/2024 Partial Approval ANDREW DORSO
Pre-Inspection 9/25/2024 Partial Approval ANDREW DORSO
Smoke Detectors 9/25/2024 Approved ANDREW DORSO
Final 11/19/2024 OK to Issue CofO ANDREW DORSO