607 S PARK VIEW ST 90057
Certificate Information: 607 S PARK VIEW ST 90057
- Application / Permit
- 17016-10010-15610
- Plan Check / Job No.
- B22LA02678
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (11) Hotel
- Work Description
- SUPPLEMENTAL PERMIT TO 17016-10008-015610 UPDATE INTERIOR WALL LAYOUTS OF LIGHT HOSEKEEPING GUESTROOMS RELOCATE TRASH ROOM FROM BASEMENT TO (E) STORAGE ROOM ON B1 LEVEL RECONFIGURE STAIR 5 FROM BASEMENT TO 1ST FLOOR TO REMOVE OPENING IN FLOOR REMOVE CONVENIENCE STAIR 18 AT 4TH FLOOR REMOVE DEMISING WALLS OF (E) 4TH FLOOR OFFICE LAYOUT TO OPEN OFFICE UPDATE INTERIOR WALL LAYOUT OF FLECIBLE EVENT SPACE ROOM 515 REVISE CORRIDOR ON FLOORS 6-11
- Permit Issued
- Issued on 9/1/2022
- Issuing Office
- Metro
- Current Status
- Issued on 9/1/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | SINA KHOSRAVI |
| Corrections Issued | 3/15/2022 | SINA KHOSRAVI |
| Building Plans Picked Up | 3/21/2022 | APPLICANT |
| Quality Review Completed | 3/30/2022 | CHARLES CHANG |
| Plan Check Approved | 8/24/2022 | SINA KHOSRAVI |
| Issued | 9/1/2022 | APPLICANT |
Permit Application Clearance Information
| Historic monument | Cleared | 4/15/2022 | LAMBERT GIESSINGER |
| Fire Marshal Fire Life Safety | Cleared | 8/16/2022 | DOMINIQUE MEDINA |
| DAS Clearance | Cleared | 8/18/2022 | SINA KHOSRAVI |
Contact Information
| Architect | Liljegren,, Karin J; Lic. No.: C28158 | 600 CRANE BLVD LOS ANGELES, CA 90065 |
| Contractor | Path Pdx Llc; Lic. No.: 1080705-B | 1331 NW LOVEJOY ST STE 950 PORTLAND, OR 97209 |
| Engineer | Adams,, Jelisa Thomas; Lic. No.: GE3092 | 26632 EL TOBOSO MISSION VIEJO, CA 92691 |
| Engineer | Tremayne, William Eijiro; Lic. No.: S5866 | 130 SUTTER ST STE 400 SAN FRANCISCO, CA 94104 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/17/2023 | Partial Inspection | KATY RAMIREZ |
| Drywall Nailing | 1/18/2023 | Partial Approval | KATY RAMIREZ |
| Excavation/Setback/Form/Re-Bar | 1/20/2023 | Partial Approval | KATY RAMIREZ |
| Excavation/Setback/Form/Re-Bar | 2/8/2023 | Partial Approval | KATY RAMIREZ |
| Insulation | 2/14/2023 | Partial Approval | KATY RAMIREZ |
| Insulation | 2/23/2023 | Partial Approval | KATY RAMIREZ |
| Excavation/Setback/Form/Re-Bar | 2/28/2023 | Partial Approval | KATY RAMIREZ |
| Reinforced Concrete Frame | 3/7/2023 | Partial Approval | KATY RAMIREZ |
| Insulation | 10/3/2023 | Not Ready for Inspection | KATY RAMIREZ |
| Insulation | 10/4/2023 | Partial Approval | KATY RAMIREZ |
| Insulation | 10/10/2023 | Partial Approval | KATY RAMIREZ |
| Deputy Reinf. Concrete | 11/3/2023 | Conditional Approval | KATY RAMIREZ |
| Pre-Inspection | 11/14/2023 | Partial Inspection | KATY RAMIREZ |
| Light Gage Steel Frame | 11/27/2023 | Not Ready for Inspection | KATY RAMIREZ |
| Insulation | 11/30/2023 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 11/30/2023 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 12/4/2023 | Not Ready for Inspection | KATY RAMIREZ |
| Drywall Nailing | 12/7/2023 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 12/12/2023 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 12/14/2023 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 12/20/2023 | Partial Approval | RICARDO ROBLES |
| Light Gage Steel Frame | 2/7/2024 | Partial Inspection | KATY RAMIREZ |
| Wood Frame | 2/20/2024 | Partial Approval | LUIS CCAMACHO |
| Light Gage Steel Frame | 3/15/2024 | Partial Approval | LUIS CCAMACHO |
| Light Gage Steel Frame | 4/5/2024 | Partial Approval | LUIS CCAMACHO |
| Light Gage Steel Frame | 4/25/2024 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 5/8/2024 | Partial Approval | RAFAEL CORTES |
| Light Gage Steel Frame | 5/10/2024 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 5/15/2024 | Partial Approval | RAMAZANALI ALMASI |
| Drywall Nailing | 5/16/2024 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 5/20/2024 | Partial Approval | JEROME BLACKWOOD |
| Insulation | 5/20/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| Light Gage Steel Frame | 5/20/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| Deputy Steel/Welding | 5/23/2024 | No Access for Inspection | MICHAEL ROSENBERG |
| Insulation | 6/3/2024 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 6/3/2024 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 6/10/2024 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 6/21/2024 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 6/24/2024 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 8/1/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| Light Gage Steel Frame | 8/9/2024 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 8/15/2024 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 8/15/2024 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 8/20/2024 | Partial Approval | JEROME BLACKWOOD |
| Deputy Drilled-In Anchors | 8/21/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 8/21/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 8/21/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Light Gage Steel Frame | 8/26/2024 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 8/29/2024 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 9/4/2024 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 9/5/2024 | Partial Approval | JEROME BLACKWOOD |
| Footing/Foundation/Slab | 9/9/2024 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 9/9/2024 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 9/11/2024 | Partial Approval | LUIS CCAMACHO |
| Light Gage Steel Frame | 9/11/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Deputy Drilled-In Anchors | 9/12/2024 | Conditional Approval | RAMAZANALI ALMASI |
| Deputy Reinf. Concrete | 9/12/2024 | Conditional Approval | RAMAZANALI ALMASI |
| Deputy Steel/Welding | 9/12/2024 | Conditional Approval | RAMAZANALI ALMASI |
| Light Gage Steel Frame | 9/12/2024 | Partial Approval | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 9/16/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| Light Gage Steel Frame | 9/16/2024 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 9/19/2024 | Partial Approval | PAUL BAZERKANIAN |
| Light Gage Steel Frame | 9/24/2024 | Approved | DARRYL ARNOLD |
| Drywall Nailing | 9/30/2024 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 9/30/2024 | Partial Approval | JEROME BLACKWOOD |
| Interior/Exterior Lathing | 10/4/2024 | Partial Approval | PAUL BAZERKANIAN |
| Light Gage Steel Frame | 10/18/2024 | Partial Approval | PAUL BAZERKANIAN |
| Light Gage Steel Frame | 10/23/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| Footing/Foundation/Slab | 10/24/2024 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 10/29/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| Special/Order Compliance | 10/29/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| Light Gage Steel Frame | 11/4/2024 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 11/7/2024 | No Access for Inspection | JEROME BLACKWOOD |
| Light Gage Steel Frame | 11/12/2024 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 11/15/2024 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 11/26/2024 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 11/26/2024 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 12/5/2024 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 12/5/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| Deputy Steel/Welding | 12/11/2024 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 12/11/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| Drywall Nailing | 12/23/2024 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 12/23/2024 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 12/30/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| Light Gage Steel Frame | 1/2/2025 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 1/7/2025 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 1/15/2025 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Light Gage Steel Frame | 1/15/2025 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Drywall Nailing | 1/23/2025 | Partial Inspection | RONALD JIMENEZ |
| Light Gage Steel Frame | 1/23/2025 | Partial Inspection | RONALD JIMENEZ |
| Drywall Nailing | 1/29/2025 | Approved | DARRYL ARNOLD |
| Light Gage Steel Frame | 1/29/2025 | Conditional Approval | DARRYL ARNOLD |
| Light Gage Steel Frame | 2/7/2025 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 2/18/2025 | Not Ready for Inspection | PAUL BAZERKANIAN |
| Light Gage Steel Frame | 2/18/2025 | Partial Approval | PAUL BAZERKANIAN |
| Drywall Nailing | 2/20/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| Light Gage Steel Frame | 2/20/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| Light Gage Steel Frame | 2/26/2025 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 3/6/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| Light Gage Steel Frame | 3/26/2025 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 4/7/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| Drywall Nailing | 4/10/2025 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 7/15/2025 | Partial Approval | JOEY BUCHANAN |
| T-Bar Ceiling | 7/15/2025 | Not Ready for Inspection | PAUL BAZERKANIAN |
| Light Gage Steel Frame | 8/20/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| Light Gage Steel Frame | 10/15/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| Light Gage Steel Frame | 10/20/2025 | Partial Approval | PAUL BAZERKANIAN |