500 WORLD WAY 90045
Certificate Information: 500 WORLD WAY 90045
- Application / Permit
- 17016-10003-33718
- Plan Check / Job No.
- B19LA01460
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (3) Airport Building
- Work Description
- SUPPLEMENTAL PERMIT TO 17016-10000-33718 : DEFERRED DESIGN ITEM FOR METAL STUD FRAMMING INTERIOR AND EXTERIOR IN TERMINAL 5. >>> > NO PERMIT FEE, NO CHANGE IN THE ORIGINAL VALUATION >>>>
- Permit Issued
- Issued on 3/11/2019
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 8/11/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2019 | EDUARDO RODRIGUEZ |
| Corrections Issued | 1/26/2019 | EDUARDO RODRIGUEZ |
| Quality Review Completed | 1/30/2019 | MINYE PAK |
| Building Plans Picked Up | 2/1/2019 | APPLICANT |
| Applicant returned to address corrections | 3/5/2019 | EDUARDO RODRIGUEZ |
| Plan Check Approved | 3/11/2019 | EDUARDO RODRIGUEZ |
| Issued | 3/11/2019 | LADBS |
| Permit Finaled | 8/11/2020 | JONATHAN ALLEN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Performance Contracting Inc; Lic. No.: 474795-B | 11145 THOMPSON AVENUE LENEXA, KS 66219 |
| Engineer | Mahaffey,, Riley Jay; Lic. No.: C51006 | 201 N MAPLE GROVE RD STE 100 BOISE, ID 83704 |
Inspector Information
| NICK LAROCCA, (213) 473-2153 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 4/15/2019 | Not Ready for Inspection | ALBERT COMISARI |
| T-Bar Ceiling | 4/15/2019 | Conditional Approval | ALBERT COMISARI |
| Final | 4/25/2019 | Not Ready for Inspection | TIMOTHY GRIFFITH |
| T-Bar Ceiling | 4/25/2019 | Partial Approval | TIMOTHY GRIFFITH |
| Drywall Nailing | 4/27/2019 | Off-Hour Fees Due | |
| Drywall Nailing | 4/27/2019 | Partial Approval | TIMOTHY GRIFFITH |
| Light Gage Steel Frame | 4/27/2019 | Off-Hour Fees Due | |
| Light Gage Steel Frame | 4/27/2019 | Partial Approval | TIMOTHY GRIFFITH |
| Drywall Nailing | 5/3/2019 | Partial Approval | TIMOTHY GRIFFITH |
| Light Gage Steel Frame | 5/3/2019 | Partial Approval | TIMOTHY GRIFFITH |
| Final | 5/21/2019 | Not Ready for Inspection | TIMOTHY GRIFFITH |
| T-Bar Ceiling | 5/21/2019 | Partial Approval | TIMOTHY GRIFFITH |
| Final | 8/11/2020 | Permit Finaled | JONATHAN ALLEN |