1250 W SUNSET BLVD 90026
Certificate Information: 1250 W SUNSET BLVD 90026
- Application / Permit
- 17016-10002-37729
- Plan Check / Job No.
- B19LA25563
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- SUPPLEMENTAL TO 17016-10000-37729, INSTALL METHANE MITIGATION SYSTEM FOR THE BUILDING
- Permit Issued
- Issued on 1/28/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 3/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/4/2019 | LARRY LEE |
| Plan Check Approved | 12/4/2019 | LARRY LEE |
| Issued | 1/28/2020 | LADBS |
| Permit Finaled | 3/11/2024 | RAMAZANALI ALMASI |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Calgroup Construction & Design; Lic. No.: 770304-B | P O BOX 8998 FOUNTAIN VALLEY, CA 92728 |
| Geologist | Siskowic,, John Gary; Lic. No.: GEO8255 | 515 S CATALINA AVE APT A REDONDO BEACH, CA 90277 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Rough | 1/29/2020 | Not Ready for Inspection | RONALD PACHECO |
| Deputy Methane Barrier | 2/7/2020 | Conditional Approval | LANNY MERRICK |
| Deputy Methane Barrier | 2/10/2020 | Conditional Approval | RONALD PACHECO |
| Deputy Methane Barrier | 2/11/2020 | Conditional Approval | RONALD PACHECO |
| Final | 3/11/2024 | Permit Finaled | RAMAZANALI ALMASI |
| METHANE-Final | 3/11/2024 | Approved | RAMAZANALI ALMASI |
| Smoke Detectors | 3/11/2024 | Approved | RAMAZANALI ALMASI |