2501 W VERNON AVE 90008
Certificate Information: 2501 W VERNON AVE 90008
- Application / Permit
- 17016-10001-17992
- Plan Check / Job No.
- B20LA04258
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (18) Day Care Facility adults
- Work Description
- Supplemental to permit application 17016-10000-17992 to change the pool backfill method by keeping the pool sheel in place instead of removing it. Original scope of work: PROPOSED PARTIAL CHANGE OF USE OF BUILDING FROM INDOOR SWIMMING POOL TO OFFICE AND PARTIAL RESTRIPING OF PARKING LOT, HOURS OF OPERATION IS LIMITED TO 7AM TO 11PM.
- Permit Issued
- Issued on 3/4/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 10/24/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2020 | QUAN NGHIEM |
| Plan Check Approved | 3/3/2020 | QUAN NGHIEM |
| Issued | 3/4/2020 | LADBS |
| Permit Finaled | 10/12/2021 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Sanchez, C Efrain; Lic. No.: C25553 | 570 ORANGE GROVE PLACE PASADENA, CA 91103 |
| Contractor | C - 1 Construction Corporation; Lic. No.: 878835-B | 3810 WILSHIRE BLVD SUITE #2206 LOS ANGELES, CA 90010 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 3/9/2020 | Partial Inspection | RUSSELL BONVOULOIR |
| Grading Pre-Inspection | 7/22/2020 | Conditional Approval | LANNY MERRICK |
| Deputy Drilled-In Anchors | 8/18/2020 | Conditional Approval | LEOPOLDO MENDOZA |
| Footing/Foundation/Slab | 10/14/2020 | Approved | LANNY MERRICK |
| Insulation | 11/12/2020 | Partial Approval | LANNY MERRICK |
| Light Gage Steel Frame | 11/12/2020 | Partial Approval | LANNY MERRICK |
| Drywall Nailing | 11/18/2020 | Partial Approval | LANNY MERRICK |
| Footing/Foundation/Slab | 11/18/2020 | Approved | LANNY MERRICK |
| Light Gage Steel Frame | 12/7/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Light Gage Steel Frame | 4/8/2021 | Partial Approval | DANIEL COLLINS |
| Final | 10/12/2021 | Permit Finaled | RUSSELL BONVOULOIR |