2252 1/2 E DUVALL ST 90031
Certificate Information: 2252 1/2 E DUVALL ST 90031
- Application / Permit
- 17016-10001-16917
- Plan Check / Job No.
- B20LA20598
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPLEMENTAL TO 17016-40000-16917 CHG PLNS FROM GABLE ROOF TO FLAT ROOF
- Permit Issued
- Issued on 12/14/2020
- Issuing Office
- Current Status
- Permit Finaled on 4/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2020 | AMIR DANAI |
| Corrections Issued | 11/13/2020 | AMIR DANAI |
| Plan Check Approved | 12/4/2020 | ADAM HEGAZI |
| Issued | 12/14/2020 | APPLICANT |
| Building Plans Picked Up | 12/16/2020 | APPLICANT |
| Permit Finaled | 4/11/2022 | THOMAS LOGRASSO |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Christiansen, Scott; Lic. No.: C37989 | 710 WILSHIRE BLVD_#230 SANTA MONICA, CA 90401 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2020 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 1/19/2021 | Not Ready for Inspection | RUBEN SALAS |
| ELECTRICAL-Rough | 1/19/2021 | Not Ready for Inspection | RUBEN SALAS |
| MERV13>=Rough | 1/19/2021 | Not Ready for Inspection | RUBEN SALAS |
| PLUMBING-Rough | 1/19/2021 | Not Ready for Inspection | RUBEN SALAS |
| PLUMBING-Rough | 2/1/2021 | Partial Inspection | COREY HUPP |
| PLUMBING-Rough | 2/5/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 3/8/2021 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Rough | 3/8/2021 | Partial Approval | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 3/8/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 3/8/2021 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 3/17/2021 | Approved | SCOTT FINNILA |
| Interior/Exterior Lathing | 3/17/2021 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Rough | 3/17/2021 | Approved | SCOTT FINNILA |
| Wood Frame | 3/17/2021 | Approved | SCOTT FINNILA |
| Insulation | 5/24/2021 | Approved | SCOTT FINNILA |
| Drywall Nailing | 7/6/2021 | Approved | CHRISTOPHER DELLEFIELD |