978 N WHITE KNOLL DR 90012
Certificate Information: 978 N WHITE KNOLL DR 90012
- Application / Permit
- 17016-10000-38501
- Plan Check / Job No.
- B17LA23805
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft story retrofit per LABC CHAPTER 93. Install SCCS and wood shear walls
- Permit Issued
- Issued on 7/15/2020
- Issuing Office
- Current Status
- CofC Issued on 2/16/2021
Permit Application Status History
| Submitted | 12/28/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 1/18/2018 | DEAN RYAN REYES |
| Corrections Issued | 2/1/2018 | DEAN RYAN REYES |
| Quality Review Completed | 2/6/2018 | CELESTE MORRIS |
| Building Plans Picked Up | 3/5/2018 | APPLICANT |
| Applicant returned to address corrections | 5/17/2018 | DEAN RYAN REYES |
| Applicant returned to address corrections | 8/8/2018 | DEAN RYAN REYES |
| Plan Check Approved | 8/21/2018 | DEAN RYAN REYES |
| No Progress | 6/4/2019 | DANIEL SANJUAN |
| Plan Check Approved | 10/10/2019 | DANIEL SANJUAN |
| Issued | 7/15/2020 | APPLICANT |
| OK for CofC | 2/1/2021 | MARK FERRARI |
| CofC Issued | 2/16/2021 | DAVID TSAU |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 6/30/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Weinstein Construction Corporation; Lic. No.: 630439-B | 15102 RAYMER STREET VAN NUYS, CA 91405 |
| Engineer | Zhuang, Wenbin; Lic. No.: S5236 | 184 S ALTADENA DRIVE PASADENA, CA 91107 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/28/2020 | Approved | MARK FERRARI |
| Wood Frame | 8/4/2020 | Approved | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 8/10/2020 | Approved | MARK FERRARI |
| Deputy Steel/Welding | 8/11/2020 | Conditional Approval | MARK FERRARI |
| Deputy Wood Construction | 8/17/2020 | Conditional Approval | VAHE KELEDJIAN |
| Structural Steel Frame | 8/18/2020 | Partial Approval | MARK FERRARI |
| Wood Frame | 8/18/2020 | Partial Approval | MARK FERRARI |
| Interior/Exterior Lathing | 9/18/2020 | Corrections Issued | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2020 | Corrections Issued | MARK FERRARI |
| Interior/Exterior Lathing | 12/28/2020 | Approved | MARK FERRARI |
| Final | 2/1/2021 | OK for CofC | MARK FERRARI |
| METHANE-Final | 2/1/2021 | Approved | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 2/1/2021 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 2/1/2021 | Approved | MARK FERRARI |